3D0XX 17. Projects and Requirements Function: Agile Principles and Methodologies
Identify the five phases of the Agile project management model.
Adapting (c) O Closing (c) Envisioning (c) Exploring (c) O Planning O Monitoring Speculating (c)
Which five ADAPT requirements are necessary for successfully transitioning to an Agile environment?
Awareness (c) Transfer (c) Train Ability (c) Desire (c) Produce Promote (c)
Match each Agile value to its associated priority.
Comprehensive documents (2) Responding to change (1) Working software (1) Contract negotiation (2) Processes and tools Individuals and interactions( (2)
Identify some of the methodologies that can be used for Agile project management.
FDD (c) O AMDD (c) O Lean principles and tools (c) O XP (c) O DSDM (c) O Non-iterative methodologies O Waterfall
What are some methodologies that can be used for Agile project management?
O DAD (c) O Kanban (c) O Crystal methodologies (c) O Non-iterative methodologies O TDD (c) O BDD (c) O Waterfall
Identify the four Scrum inspect and adapt events.
O Daily scrum (c) O Scrum closure O Sprint integration O Sprint retrospective (c) O Sprint review (c) O Sprint planning (c)
Which characteristics describe the Agile method?
O It focuses on the highest-value items first (c) O It allows for feedback to be obtained early and often (c) O It focuses on the costliest items first. O It's only applicable to long-term projects O It identifies issues earlier, and changes are easier to implement (c) O It is incremental (c) O It is iterative (c)
Which are suitable types of contracts for an Agile project?
O Non cost-reimbursable O Time-and-materials contracts (c) O Cost-reimbursable (c) O Not to exceed with fixed-fee contracts (c) O Fixed scope and cost contract O Incentive contracts (c) Service contracts for the series of fixed price contracts (c)
Which are some of the recommended components of a businoss case?
O Outsourcing Partners O Investment (c) O Project requirements O Milestones (c) O Expected payback (c)
What are some of the elements included in a project charter?
O Problem (c) O Finalized budget O Objectives or mission of project (c) O Supplier O Customer (c) O Vision statement (c)
While documentation is a secondary priority for Agile projects, it can still be very helpful. Identify useful types of documentation for Agile projects.
O Project overview (c) O Detailed timeline plans O Requirements documentation (c) O Historical performance data O Vision statement (c)
Identify the contract types that are suitable for an Agile project.
O Service contracts for the series of fixed price contracts (c) O Time-and-materials contracts (c) O Fixed scope and cost contract O Incentive contracts (c) O Cost-reimbursable (c) O Non cost-reimbursable O Not to exceed with fixed-fee contracts (c)
Identify some of the recommended components of a business case.
O Stakeholders O Resourcing costs O Project vision (c) Opportunity (c) Strategy (c) O Goals (c)
What are some useful types of documentation for Agile projects?
O User documentation (c) O Support documentation (c) O Historical performance data O Acceptance testing documents (c) O Detailed timeline plans
Identify some of the elements you include in a project charter.
Success conditions or criteria (c) O Team roles (c) O Resource management plan O Detailed schedule plan O Risks and mitigation (c) O Priorities and compromises (c)