BUS140 Chapter 17 Quiz
What is an immediate predecessor in a network diagram? A.) the activity that follows just after the one in question B.) the parallel activity in a sequence on the next path C.) an activity which occurs just prior to the one in question
an activity which occurs just prior to the one in question
The slack time on the critical path is always what? A.) the sum of all activity slack times on that path B.) subject to variation C.) zero D.) deterministic
Zero
Which of the following is calculated in a forward pass? A.) slack B.) LS = LF - activity time C.) ES = 0 D.) ES + Activity time = EF
ES = 0 ES + activity time = EF
Which of the following would enable a team member to be assigned to a project by the project manager? A.) necessary knowledge and skills B.) the candidate's apathy for the project C.) low interference from the other projects that the candidate is involved in D.) ability to work well with others
necessary knowledge and skills, low interference from the other projects that the candidate is involved in, ability to work well with others
In critical chain project management the critical path is viewed as a what? A.) diagram B.) bottleneck C.) buffer D.) capacity
bottleneck
Similar to the theory of contraints, critical chain project management uses what to support the critical path? A.) slack B.) buffers C.) constraints
buffers
The three probabilistic time estimates form a distribution curve known as what? A.) beta distribution B.) pessimistic distribution C.) optimistic distribution D.) delta distribution
beta distribution
The phases of a project life cycle do not overlap T/F
False
Projects typically have three types of targets. What are they? A.) B.) C.)
Time, cost, performance
Early start and finish times involve a forward pass and late start and finish times use a backwards pass through the network T/F
True
Network diagram
a "big picture" visual aid that is used to estimate project duration, identify activities that are critical for timely project completion, identify areas where slack time exists, and develop activity schedules
Select the best definition of a work breakdown structure A.) what happens when behavioral issues damage a team cohesion B.) a detailed accounting of everything spent on a project C.) a hierarchical listing of what must be done during a project
a hierarchical listing of what must be done during a project
Gantt charts
a visual aid used to plan and monitor individual activities
Risk management
analyses of potential failures or problems, assessment of their likelihood and consequences, and contingency plans
Select from below which are the key managerial decisions which determine the success of projects A.) deciding which equipment to buy or lease B.) choosing the project team members C.) managing and controlling project resources D.) selecting which projects to implement
choosing the project team members, managing and controlling project resources, selecting which projects to implement
In project management, shortening activity durations by applying additional resources to it is called A.) optimizing B.) tasking C.) crashing
crashing
Put the steps of the project life cycle in order from start to finish A.) definition B.) execution C.) planning D.) termination
definition planning execution termination
Operating in an environment of uncertainty, projects are subject to what negative outcomes? A.) delays, budget overruns, inability to meet technical requirements B.) using all constraining resources from the buffers C.) selecting virtual project teams with language and cultural difficulties
delays, budget overruns, inability to meet technical requirements
When interpreting network diagrams in PERT/CPM, if the time estimates are fairly certain they are said to be what? A.) critical B.) deterministic C.) probabilistic
deterministic
Workers on a project are usually evaluated based on the team's overall contribution since project work is often based on (blank) (blank)
team efforts
When using a computing algorithm to analyze large network diagrams, what are the following pieces of information needed for each activity? A.) owner, description, predecessor, and successor B.) arrow, node, event, slack C.) early start, early finish, late start, late finish
early start, early finish, late start, late finish
With proper risk management all cost, schedule, and technical risks can always be avoided on a project T/F
false
Select from the following list all the advantages of using PERT/CPM for project management A.) highlights the slack and in the schedule where resources can be pulled if needed B.) provides a useful graphical display of major project activities C.) allows the project manager to virtually ignore non-critical path activities
highlights the slack and in the schedule where resources can be pulled if needed, provides a useful graphical display of major project activities
What are some "cons" of working on a project? A.) if a project is long term, there may not be a "next" project to go to B.) if a project is unsuccessful, it reflects on team members C.) potentially working for two bosses D.) projects require meeting new people
if a project is long term, there may not be a "next" project to go to, if a project is unsuccessful, it reflects on team members, potentially working for two bosses
What are some "pros" of working on a project? A.) if project is successful, gives team increased status B.) often are paid the same as remaining in the functional sub-organization C.) dynamic, stimulating environment D.) meet new people not previously worked with before
if project is successful, gives team increased status, dynamic, stimulating environment, meet new people not previously worked with before
From the following list, which are the potential disadvantages of virtual project teams A.) language or cultural differences B.) lack of team cohesion from not being physically co-located C.) project slippage from moving to another project too quickly
language or cultural differences, lack of team cohesion from not being physically co-located
Which of the following is a correct formula for calculating slack for a task? A.) Early start - early finish B.) late start - late finish C.) late finish - late start D.) late start - early start
late start - early start LS - ES OR late finish - early finish LF - EF
Which of these is the knowledge area for a project manager concerned with acquisition and contracting plans, sellers' responses and selections, contract administration and closure? A.) managing scope B.) managing procurement C.) managing risk
managing procurement
Which of these is the knowledge area for a project manager concerned with involves breaking down what needs to be done to complete the project and managing the project through a work breakdown structure? A.) managing scope B.) managing risk C.) managing time/schedule
managing scope
All of the following are example of projects except which? A.) reengineering a process B.) merging two companies C.) designing a new project D.) manufacturing the daily quota
manufacturing the daily quota
If members of a project team report formally to a functional manager what type of organization is it? A.) matrix B.) projectized C.) non-profit
matrix
What type of organization integrates the activities of specialists within a functional framework? A.) traditional B.) projectized C.) matrix
matrix
Select from the following list all of the errors in PERT/CPM that can potentially be made A.) precedence relationships may be incorrect or missing B.) risks probability and impacts are scored too low C.) some activities may inadvertently omitted D.) activity owners may estimate durations too high or low
precedence relationships may be incorrect or missing, some activities may inadvertently omitted, activity owners may estimate durations too high or low
PERT and CPM stand for what? A.) project estimate and risk tool / complete project model B.) program evaluation and review technique / critical path method C.) project education repository tool / critical project model
program evaluation and review technique / critical path method
Work breakdown structure
an initial planning tool that is needed to develop a list of activities, activity sequences, and a realistic budget
Which probability distribution is commonly used to model the inherent variability of activity time estimates in project management? A.) normal distribution B.) uniform distribution C.) binomial distribution D.) beta distribution
beta distribution
What are the two main parts of the project initiation phase of the life cycle? A.) metrics and schedule B.) concept and feasibility analysis C.) budget and tasks D.) reassignment and disposition
concept and feasibility analysis
What is a network diagram, which is used by the PERT and CPM project management techniques? A.) diagram of servers and relevant databases used on a project and how all are connected B.) diagram of project activities that shows their sequential relationships with arrows and nodes C.) a Gantt chart that shows all the major activities and durations on a project
diagram of project activities that shows their sequential relationships with arrows and nodes
What is the main limitation of Gantt chart when using for project management? A.) the length of time necessary to prepare it B.) small font is difficult to read C.) does not show relationship between activities D.) cannot fit enough activities on the chart
does not show relationships between activities
What is used in AOA diagrams to clarify relations, such as two activities that have the same starting and ending nodes? A.) immediate predecessor B.) arrows C.) dummy activity
dummy activity
If a budget was too optimistic, it was (blank) the actual cost A.) higher than B.) lower than C.) the same as
lower
When using a Gantt chart with a complex project, what tool should be used in conjuction with the chart? A.) network diagram B.) project life cycle C.) work breakdown structure
network diagram
What is the main difference between the two forms of network diagrams, activity-on-arrow and activity-on-node? A.) there are no differences since activities are represented in each form of network diagram B.) nodes represent events on AOA and arrows show relationships between activities on AON C.) nodes represent activities on AOA and show start and finish points on AON
nodes represent events on AOA and arrows show relationships between activities on AON
Why are only activities on the critical path candidates for crashing? A.) the critical path contains all of the project activities at risk B.) only the critical path directly affects the completion date C.) the critical path contains the most schedule slack D.) the critical path activities cost the least
only the critical path directly affects the completion date
Which of the following statements about risk probability and cost are true A.) probability of occurence of a risk is highest at the start B.) probability of occurence of a risk is equal throughout the project C.) the cost to overcome a risk is lowest at the end of a project
probability of occurence of a risk is highest at the start
On virtual project teams, as a project nears completion, if resources are transitioned too quickly to new projects, this can cause A.) synergies B.) reassessed priorities C.) project slippage
project slippage
What is the function of a work breakdown structure? A.) provide the basis for detailed time and cost estimates on a project B.) used to generate risks and opportunities for successful project management C.) provides an example to other projects of how not to manage interpersonal dynamics
provide the basis for detailed time and cost estimates on a project
Which of the following are correct about PERT/CPM? A.) provides an estimate of completion time for the overall project schedule B.) usually one or the other tool is implemented, not both C.) useful for large-scale projects to indicate the most critical activities D.) tells how long an activity can be delayed without delaying the project
provides an estimate of completion time for the overall project schedule, useful for large-scale projects to indicate the most critical activities, tells how long an activity can be delayed without delaying the project
Project planning involves all of the following except which? A.) projecting resources and budgetary needs B.) identifying tasks with time estimates C.) setting goals and priorities D.) reassigning employees at closure
reassigning employees at closure
Select all of the rules project managers follow when crashing a schedule A.) recalculate the critical path after each crashing B.) crash the schedule one period at a time C.) exceed the penalty/incentive by up to 50% per period D.) crash the least expensive activity on the critical path
recalculate the critical path after each crashing, crash the schedule one period at a time, crash the least expensive activity on the critical path
Which of the following are characteristics of a project? A.) routine operations B.) requires careful planning and coordination C.) limited time frame D.) involves considerable cost E.) one time operations
requires careful planning and coordination, limited time frame, involves considerable cost, one time operations
Select all of the reasons that project costs may exceed budgeted amounts A.) rework of substandard workmanship B.) experienced project manager C.) weather or supplier delays D.) budget too optimistic
rework of substandard workmanship, weather or supplier delays, budget too optimistic
In the case of dependent paths, what technique is use to analyze probabilistic time estimates? A.) risk probability database B.) simulation C.) PERT/CPM
simulation
What is the term used to denote the allowable slippage for a path or alternately the difference between the length of a path and the critical path? A.) criticality B.) slack C.) precedence D.) event
slack
All of the following are the main tools used in project management except which? A.) network diagram B.) work breakdown structure C.) risk management D.) gantt charts E.) statistical process control
statistical process control
Which of the following factors lead to behavioral problems in projects A.) stress of achieving project milestones on time B.) surprises C.) monetary compensation and promotion D.) decentralized decision making E.) stress of achieving project milestones within the budget
stress of achieving project milestones on time, surprises, decentralized decision making, stress of achieving project milestones within the budget
In PERT/CPM if a time estimate is said to be probabilistic what does this mean A.) the activity can start late without affecting the project's duration B.) the actual activity duration is subject to variation C.) the activity will likely start on time according to the baseline schedule
the actual activity duration is subject to variation
The critical path in a network diagram is defined as what? A.) the longest path from start to finish which determines the overall project duration B.) the sequence of activities on a project which have the highest cost C.) those activities on a project schedule which experience delays but do not affect the overall project completion time
the longest path from start to finish which determines the overall project duration
All of the following information can be produced by the network diagram computing algorithm except which? A.) most expensive path B.) expected project duration C.) slack time D.) critical paths
the most expensive path
In probabilistic time estimation, paths are said to be dependent when what occurs? A.) when each time duration is optimistic B.) when one activity succeeds another C.) the same activity fall on more than one path D.) when there is a critical path
the same activity fall on more than one path
In analyzing path probabilities, what would a negative z value mean? A.) the standard deviation is less than the expected path duration B.) the specified time is earlier than the expected path duration C.) the specified time is later than the expected path duration D.) the standard deviation is less than the specified time
the specified time is earlier than the expected path duration
Select all of the reasons why a project manager would want to shorten the duration of a project A.) to free up resources to work on another project B.) the supplier is delivering material on time C.) incentive payment earned if project completion date is early D.) monetary penalty due if agreed-to schedule is exceeded
to free up resources to work on another project, incentive payment earned if project completion date is early, monetary penalty due if agreed-to schedule is exceeded
It is common for projects to fail, either partially or completely T/F
true
Which is the correct formula for determining path probability? A.) z = (specified time - path mean) / path standard deviation B.) z = (slack time - critical path mean) / path standard deviation C.) z = (specified time - standard deviation) / variance
z = (specified time - path mean) / path standard deviation