Construction Management Exam 2
indirect costs
(aka overhead/general conditions) costs to manage and deliver the materials, labor, equipment, and subcontracts employed on any job, includes supervision, job trailer expense, temporary utilities, testing and inspections, and job photographs, security, etc
project evaluation
(post-mortems) last step in post construction, Opportunity for construction management team to review successes and hurdles.
query list
A list of questions and needed clarifications compiled by an estimator as they review the plans and specs during the estimating process.
capital project
A long-term investment project that will increase the organization's assets
Liquidated Damages
An amount of money paid to owner for each day the project goes over completion date in contract, not in all contracts
unbalanced bids
Bidding some items at inflated prices and compensating by bidding other items at below-cost prices changes cash flow of project, increases unit price of early cost items, may be related to expected variations in quantities
Permitting/ inspection process
CM team must be vigilant in pursuing timely building permit release, superintendent must be fully aware of inspection requirements connected to the proj.
superintendent
Coordinates all of the on-site construction activities. He/she is the daily point contact for the owner other representatives
implied warranty
Deal with products, materials, and equipment
add-ons
Describes the taxes, overhead and profit added to the estimate after all other costs have been calculated..
working drawings
Drawings that convey all of the information needed to manufacture and assemble a design.
bid depositories
Facility used to collect subcontractor bids
capital expenditure
Funds used by a company to acquire or upgrade physical assets such as property, industrial buildings or equipment. This type of outlay is made by companies to maintain or increase the scope of their operations. These expenditures can include everything from replacing a roof to building a brand new factory.
factors that influence trust
History and experience, Competence and ability, Similarities and differences, Relative power and authority, Character
Project Manager (PM)
Leader of the team, usually with extensive experience in construction and management
committed listening
Listening intently to another person to make sure that you clearly understand what they mean by the words they are speaking without judging, assessing, or negating what they are saying
Mangement
Manage things - comes with title like project manager = schedules, budgets, safety program
final documentation
Package of documents to be submitted to the owner including, Warranties, Operation and Maintenance manuals, Inspection and testing reports, and As-built drawings
Quantity Surveyors
People who count up and calculate quantities of materials, labor, and equipment
land development
Refers to altering the landscape in any number of ways such as: changing landforms from a natural or semi-natural state for a purpose such as agriculture or housing
subcontracts
Sections of the job are out for bid to respective trades and prices are returned to the general contractor. Once the General contractor is selected the subcontract is then executed with each trade contractor, scope is important when choosing subcontracts
Certificate of Occupancy
Signifies all life safety code requirements are met prior to anyone occupying the building, issued by building officials
scope sheet
Similar to a work package, a scope sheet describes the items of work to be performed under a particular trade heading. It often accompanies a subcontractor's bid or a request for quotation.
committed speaking
Speaking with intention and purpose, using words specifically to clearly convey your exact meaning
due dilligence
The process of identifying any problems or areas of concern that exist and addressing them during the preconstruction phase, site investigation/soil testing
Unforeseen Conditions
Unknown physical conditions at the site that were not anticipated by the owner or the contractor
commissioning
a process of testing and checking all equipment and systems within the facility at the end of a project to assure proper functioning and operation. This may also include the training of owner personnel in the operation and maintenance of the equipment
alternates
a request included in the bidding documents asking the contractor to supply a price for some type of variation from the base bid. Allow the owner some flexibility in modifying the cost of a project when the bids are submitted by varying the quantity or quality of protions of the job. add- add to the base bid deduct- reduce the base amount
estimate
a summary, based on the best information available, of probable quantities and costs of materials, labor, equipment, and subcontracts to complete a project, includes taxes, overhead, and profit, can make or break project
Vulnerability based trust
accountability - Establishing honesty among team members through authentic check-ins and providing the support needed to make sure all team members, and thereby the project, succeed.
commitment management
accountability - The practice of being aware of each team member's tasks and deliverables, checking-in with them periodically, and helping when needed for the success of the project
cost
actual dollars spent for materials, labor, equipment, services, insurance, etc
The procurement stage
aka buying out the job, purchasing labor, materials, equipment, and subcontracts
Pre-Construction services
anticipatory planning, analytical, and evaluation activities that occur before construction begins, often during the design phase when at-risk CM, or design build is employed as the project delivery method
contract administraitor
assists PM and superintendent with contract details
Work Breakdown Structure (WBS)
basic building blocks of estimate and schedule, organizes work by breaking down each divisions of work into a separate work package, each is detailed items of work bundled together under a particular trade
pre-estimate
become famileir with requirements of project by: reviewing plans and specs, pre-bid meeting, site visit
pre-bid meeting
bidder's estimators usually sent to project site to ask questions
value
combination of design, quality, usefulness, character, style, location, amenities, functionality, desirability
lump sum estimates
common in construction, construction cost=cost of materials, labor, equipment, subcontracts, overhead, bonds, permits and fees, and markup
unit price estimates
common in engineering, bidders receive schedule of bid items/quantities, project cost=sum of the quantities for each bid item multiplied by the contractor's bid
pre-construction meeting
construction stage, when building is ready to start, superintendent will hold a pre-construction meeting for all subcontractors and major material suppliers, sets tone and ground rules (safety, meetings, scheduling)
completing the estimate
contractor delivers bid to owner, bid procedures specifies when and how contractors will know they've been awarded the contract
addenda
contractor identified errors in plans/specs, issued 4 days before bid due
direct costs
costs that actually go into building the facility such as materials, labor, equipment and subcontracts
quality of work
defined by standards in specifications
The design and bidding stages
design, bidding, contract award, notice to proceed
preconstruction time frame
design-bid-build, preconstruction after design is complete at-risk CM, design-build, and other alternative methods, pre-construction begins with design phase and overlaps with construction
balancing estimating and bidding
develop most probable cost, balance of being low often enough while maintaining profitable operations
allowances
dollars that are to be included in the bid, detailed in the specs
time of construction
estimator must anticipate changes in prices and availability of labor
calculating quantities
first determine quantities of materials/labor/general conditions then apply a unit price factor to the equation i.e. each, linear feet, square feet
project/field engineer
first step in progressing through the ranks of project management. Primarily handle paperwork such as requests for information (RFI), submittals, and shop drawings
product-oriented generating value perspective
focus on a product or building element you can provide for less money
punchlist
guides project punchout detailed list of items still to be completed, complied from lists by the owner, architect, contractor
site visit
important, site conditions are harder to understand in the plans/specs Consider distance from office, site conditions, access, soil, security requirement, traffic, storage
effective collaboration and team integration
integrated team creates new options and solutions that a single person would not have come up with collaborate=work together integrate=blend together
ethical commitment
keeping your word, honesty, fairly compensating employees, paying subs/vendors on time, rewarding superior performance
management factors
knowing owner or architect = slow/difficult, have to watch inexperienced subcontractor carefully
leadership
lead people - can be executed at any level = empower, encourage, inspire
land entitlement
legal process of obtaining approvals from a governing municipality to allow for the development of a certain building type
function or performance generating value perspective
look for alternative products to provide the same, or better, function and performance
effective communication
make specific requests, only accept committed responses, hold yourself and others accountable for the request and what was promised committed listening/speaking
alternative project delivery methods
most common are At-risk CM and design build, overlap design and construction to Better manage risks Generate better value and Eliminate waste owner benefits with lower costs, grater value, efficiency, higher quality, more innovation the project team, the owners, designers, contractors, vendors, persoeel, etc using collaboration, coordination, and communication give benefits of newest technology and advancemnts in materials and methods
markup
not profit, Distinguish own forces work versus work done by others
construction operations
on-site project team must be able to answer questions of the subs and owner and uses requests for informationterm- to clarify the designers intent, coordinates of all trades must be proactively managed for a smooth job
the bidding stage
plans/specs produced for bidders, stage is coordinated by either the architect or CM in assisting the owner in contractor selection
Project team key components
poeple, trust, accountability, ethical commitment
addenda
pre-bid plan/spec changes
value engineering
preconstruction best used during the design phase, but many owners haphazardly apply it during the construction phase which can lead to decreased value, applied correctly = enhanced results
life-cycle cost analysis
preconstruction calculating return on investment considering payoff and Initial first cost, Service cost, Maintenance cost, Operating cost, Disposal cost
Feasibility Studies
preconstruction done in very early stages to determine success of project for owners purpose, pros/cons examined, ensures decisions makers have the info they need before making a go/no-go decision
estimating churn
preconstruction during conceptual estimating new estimates based on the cost model must be put together multiple times during design to ensure the project is staying on budget, ensures no surprises with final project cost
constructability reviews
preconstruction performed by project manager during pre-construction to ease the construction process and look at quality, value, code compliance, schedule, sustainability, energy efficiency, and anything else deemed important to the owner's ultimate goals
conceptual estimating
preconstruction used during design to ensure completed design is within owners budget, if not during design over budget is common and owners options are: Increase budget to meet the design, redesign to the budget, Ask the contractor to perform value engineering
cost model
preconstruction used to create a working budget to guide design by allocating budget limits to design elements and systems, developed with project program including overall quantities. Added to that are the quality standards desired by the owner and current unit pricing
integrated project leader
primary accountability associated with leading design-build team, may take place of PM or PM reports to IPL, skills are communication, strategic foresight, emotional intelligence
Steps of the design stage
programming and feasibility, schematic design, design development, contract documents, as-builts
pre-construction
project manager leads assembling the team that will complete the job, detailed planning is invaluable, one of the hardest stages to manage, number of team members and when they're assigned to the team depends on project size/complexity
Project closeout steps
project punchout substantial completion final inspection certificate of occupancy commissioning final documentation final completion
factors impacting project cost
project size, complexity, site location, time of construction, quality of work, market conditions, management factors
Project overhead vs general overhead
project specific items that do not pertain to a specific item of work in the project, VS, general and administrative expense (running of the business)
substantial completion
punch list competed, designer determines facility can be utilized for intended purpose, end of project and beginning of warranty period, payments due to contractor are released
pricing the work
quantities are first half of estimate, now plug in the unit costs for each item of material, labor, equipment, and general conditions in your estimate, source of costs and their reliability is estimators primary concern
estimating process concerns
quantities, pricing, productivity
price
related to what the market will bear, owner may be given price greater than the cost for anticipated inflation, Increasing material prices, Labor shortages, Weather delays
mobilization
setting up, getting ready for construction, and laying out the site to be a safe and efficient environment (site layout, earthwork)
AEC culture shift and challenges
shifting towards collaborative nature, Challenges = Low-bid mentality, Competing agendas, Large diverse teams, Multigenerational workforce, Technology
decommissioning
shutting down a building and removing it safely from operational use
building the estimate
start form 48 divisions of CSI master format outline, common way to organize estimate use work breakdown structure
Value Engineering/analysis
to optimize resources by reviewing designs, products, materials, installation methods, applications, and execution to get the best value for the owner. Impacted by delivery method. Include field personnel who can provide valuable info
Pre-construction services evolution
today is a distinct part of the construction process, became more common as more alternative delivery methods are used
obtaining subcontractor/vendor bids
today they make up bulk of estimate, While the estimating team is putting together their own pricing for self performed work, they must also be gathering prices from subs for work they are not going to self perform, to ensure solid bids: includes soliciting the bids, receiving the bids, analyzing the bids, and choosing the bids
detailed estimates
used with complete set of plans and specs, as their accuracy increases, so does the time/skill required to complete the estimate
preliminary estimates
used with preliminary drawings with overall dimensions, slightly higher accuracy to establish initial budgets and financing, never used to commit to contract price
market conditions
when construction contracts are scarce cost becomes very competitive, estimate will reflect this
conceptual estimate
when there are no drawings, to help owner determine feasibility
express warranty
work will be preformed in a good and workmanlike manner