DSM 14
The EOQ lot size quantity would be ___________.
200
Each X requires 2 of component Y; each Y requires 4 of part Z. The lead time for assembly of X is 1 week. The lead time for the manufacturer of Y is 1 week. The lead time for procurement of Z is 6 weeks. The cumulative lead time for X is __________ weeks.
8
Which of the following best describes a gross material requirements plan?
A schedule that shows total demand for an item, when it must be ordered from a supplier, or when production must start
Capacity planning in closed-loop MRP does not do which of the following?
Adds in additional capacity
Material requirements planning (MRP) does not consider __________.
Capacity
Effective use of MRP and other dependent demand models does not require which of the following?
Cost of individual components
Which of the following statements regarding the gross material requirements plan is false?
It includes inventory on hand
Which of the following is false concerning enterprise resource planning?
It is inexpensive to implement.
What lot-sizing technique is generally preferred when inventory holding costs are extremely high?
L4L
Which of the following lot-sizing techniques results in the lowest holding costs?
L4L
MRP II is accurately described as:
MRP augmented by other resource variables
The __________ is the MRP input detailing which end items are to be produced, when they are needed, and in what quantities.
Master production schedule
A paint company mixes ten different base colors into 3,000 different color options. If the MPS is organized around the ten different base colors, their bills of material are classified as:
Modular
Firms making many different final products use __________ to facilitate production scheduling.
Modular bill
Linking a part requirement with a parent component that caused the requirement is referred to as:
Pegging
Which of the following is not a key benefit of MRP?
Quality increases
All of the following are advantages of enterprise resource planning except it __________.
Requires additional training
Which of the following statements regarding MRP in services is true?
Services such as restaurant meals illustrate dependent demand, and require product structure trees, bills-of-material, and scheduling.
Which of the following is a step towards integrating MRP and finite capacity?
Using smaller buckets
Enterprise Resource Planning __________.
automates and integrates the majority of business processes
The phrase "demand related to the demand for other products" describes __________.
dependent demand
In MRP, system nervousness is caused by __________.
management's attempt to continually respond to minor changes in production requirements
A document calls for the production of 50 small garden tractors in week 1; 50 small garden tractors and 100 riding mowers in week 2; 100 riding mowers and 200 garden utility carts in week 3; and 100 riding mowers in week 4. This document is most likely a __________.
master production schedule
Distortion in MRP systems can be minimized when safety stock is held at the __________.
raw material level
If a load report (resource requirements profile) shows a work center scheduled beyond capacity, then __________
the work center's load may be smoothed