ENGR 3000- Exam 2
The chances of a risk event occurring as a project proceeds through its life cycle tends
Slowly drop
The cost impact of a risk event occurring as a project proceeds through its life cycle tends to
Slowly rise
When developing a new software package, the software must be designed, the code must be written, and the code must be tested. This is an example of a ______ constraint.
Technical
Design flaws being revealed after the fact, extreme weather conditions, and accidents occurring are examples of:
Things going wrong on a project
Which of the following is not one of the types of project constraints?
Time
In practice, estimating processes are frequently classified as
Top down/bottom up
An activity is on the critical path if its___is the lowest in the network.
Total slack
(True/False) Budget reserves are setup to cover identified risks associated with specific segments of a project while management reserves are set up to cover unidentified risks associated with the total project.
True
(True/False) Change management systems involve reporting, controlling, and recording changes to the project baseline.
True
(True/False) General and Administrative costs are usually allocated as a percent of the total of a direct cost such as labor, materials, or equipment.
True
(True/False) In a Risk Severity Matrix a green zone risk is considered inconsequential and ignored unless their status changes
True
(True/False) Organization culture can significantly influence project time and cost estimates
True
(True/False) Phase estimating is used when a project cannot be rigorously defined because of the uncertainty of design or the final product.
True
(True/False) Project networks are built using nodes and arrows
True
(True/False) Since the goal is to find problems before they happen, the project manager should encourage critical thinking when it comes to risk identification.
True
(True/False) The ideal approach to estimating project time and costs is to use both the top-down and the bottom-up approach.
True
(True/False) The probability that a risk event will occur is higher during the initial stages of a project
True
(True/False) The use of past experience is almost always used primarily in the initial phases of a project.
True
Contingency funding is made up of budget reserves and management reserves.
True
Different activities along the same path can have different total slack
True
Risks such as inflation and monetary exchange rates are not usually included in a project's risk assessment
True
A(n) _____is an element in the project that consumes time.
activity
Activities which can take place at the same time are termed
parallel activity
Which of the following represents an activity on an AON project network?
A node
______ estimates are most likely to use low cost, efficient methods.
Bottom-up
Top-down estimates are most likely to occur during the ______ phase.
Concept
Which of the following is not one of the basic rules to follow when developing project networks?
Conditional statements are allowed but looping statements are not allowed
Which of the following is a potential consequence of failing to schedule limited resources?
Costly activity delays, Costly project delays, Difficulty in taking quick corrective actions
Which of the following correctly calculates the early finish for an activity?
ES +DUR
The process of forecasting or approximating the time and cost of completing project deliverable is called
Estimating
(True/False) An activity includes only one work package
False
(True/False) Bottom-up-estimating is another name for overzealous top management estimates
False
(True/False) Due to the impact over a long period of time, risk events that occur in the early stages of a project will have a greater cost impact than those that occur in later stages.
False
(True/False) During risk identification the smaller risks should be identified first because they will naturally lead to identifying the larger risks.
False
(True/False) Estimating the total cost of a house by multiplying the total square feet by a cost per square foot is an example of the apportion method of estimating costs.
False
(True/False) Project estimates should be broken down into as much detail than and with as much accuracy as possible.
False
(True/False) The Consensus method of estimating costs is a bottom-up technique
False
(True/False) The forward pass through a project network determines the critical path
False
(True/False) The project structure chosen to manage the project will have little impact on the actual project work to be accomplished.
False
(True/False) The risk identification process should be limited to just the core project team.
False
Which of the following is not one of the potential responses to a specific risk event?
Ignoring
In the beginning the focus of risk management should be on risks that
Impact the whole project
Which of the following is a good condition for top-down estimating?
Internal, small project
Which of the following correctly calculates the late start for an activity?
LF- DUR
Learning curves are more likely to apply in situations where most of the costs are
Labor
Which of the following would be considered a direct project cost?
Labor, Materials, Equipment
Arrows on an AON project network represent:
Project flow and Dependency
Ed is looking over the actual results of projects and comparing them to what was estimated. He notices that projects that took six months or longer to complete were noticeably more off the estimates. Which of the following factors is he recognizing?
Planning horizon
________ activities must be completed immediately before a particular activity.
Predecessor
Merge activity in an activity that has more than one activity immediately preceding it (more than one dependency arrow flowing to it)
Longest path through the network
In a project network, _____ (recycling through a set of activities) is not permitted.
Looping
Which of the following is typically included in risk profiles
Management aspects and technical aspects
A _____is an activity that has more than one predecessor.
Merge activity
An activity that has more than one dependency arrow flowing into it is termed a(n)
Merge activity
The 1999 NASA Mars Climate Orbiter is an example of
Mismanaged risk control
When translated into a project network, a work package will become
One or more activities
A good starting point for developing time and cost estimates is
Past experience
Sam the project engineer has been scheduled to run the product system test at the same time he is to build a marketing prototype. This is an example of a ______ constraint.
Resource
Delaying noncritical activities to lower peak demand on resources is known as resource
Resource smoothing
If resources are not adequate to meet peak demands, the resulting reschedule is termed
Resource-constrained scheduling
An uncertain event or condition that, if it occurs, has a positive or negative effect on a project objectives is termed.
Risk
The attempt to recognize and manage potential and unforeseen trouble spots that may occur when a project is implemented is known as
Risk Management
The risk management tool that is divided into three color-coded zones representing major, moderate, and minor risks is the risk
Risk severity matrix
Which of the following is not one of the steps in the risk management process?
Risk tracking
Information to develop a project network is collected from
Work breakdown structure