Lesson 6: Bonding Requirements

¡Supera tus tareas y exámenes ahora con Quizwiz!

Which of the following is suitable for accomplishing the bonding on the supply side of the service disconnecting means?

-Listed bonding locknuts -Listed threaded hubs -The grounded service conductor

Effective bonding of metal parts is required to maintain effective continuity from the service to the ? .

-farthest outlet supplied by the system -first panelboard enclosure -first receptacle in the branch circuit -first system overcurrent device

A bonding jumper for a metallic water piping system must be sized according to which of the following?

Table 250.102(C)(1)

Structural metal building framing that is bonded to the service must be bonded using a bonding jumper not smaller than the sizes required in which of the following tables?

Table 250.102(C)(1)

Where a feeder supplies a separate building or structure, and an interconnected metal frame of that structure must be bonded, what NEC table is used to size the bonding jumper?

Table 250.102(C)(1)

An aluminum equipment bonding jumper installed on the load side of a 400-ampere overcurrent protective device must not be smaller than ? .

1 AWG

When a gas furnace is supplied by a 30-ampere branch circuit, what is the minimum size bonding conductor or jumper required for bonding the metal gas piping system?

10 AWG copper

Where concentric, eccentric, or oversized knockouts are encountered in circuits over 250 volts phase to ground, one of the bonding methods in Section 250.92(B)( ? ) through ( ? ) must be applied to ensure the required continuity and conductivity.

2 / 4 250.97

Referring to the drawing, what is the minimum size required for the copper supply-side bonding jumper in this service?

2 AWG

Referring to the drawing, what is the minimum size required for the copper supply-side bonding jumper in this service, and what is the minimum size required for a copper load-side bonding jumper? Note: The circuit breaker is rated at 300 amps.

2 AWG / 4 AWG

What is the minimum-size copper supply-side bonding jumper for a 600-ampere service supplied with two 400 kcmil conductors (800 kcmil is the largest ungrounded service-entrance conductor per phase) if all the conductors are in a single six-inch raceway?

2/0 AWG

Where a building or structure is supplied by a feeder or branch circuit, the bonding jumper to the metal water piping system(s) is required to be sized according to ? , based on the size of the feeder or branch circuit that supplies the building or structure.

250.102(D) Table 250.122

What is the minimum size copper bonding conductor for an interior metal water piping system if the building is supplied by a service that has a large ungrounded service entrance conductor size of 2,500 kcmil?

3/0 AWG

What is the minimum-size copper bonding jumper required for interconnected exposed structural metal if the service is rated 1,000 amperes and supplied by two parallel 600 kcmil copper conductors for each ungrounded service phase conductor?

3/0 AWG

When an equipment bonding jumper is installed on the outside of flexible metal conduit or liquidtight flexible metal conduit, the length of the jumper is generally limited to no more than ? in length.

6'

What is the minimum-size aluminum or copper-clad aluminum equipment bonding jumper required for a range receptacle installed in a metal box where the branch circuit is protected by a 60-ampere circuit breaker?

8 AWG

Which of the following methods is not suitable for establishing bonding connections for circuits over 250 volts phase to ground?

A locknut on the outside and a bushing on the inside of metal enclosure

According to the NEC Style Manual, the phrase "likely to become energized" is best described by which of the following?

Failure of insulation on

A supply-side bonding jumper is installed only at the service.

False

Reducing washers are not suitable for non-service bonding in circuits greater than 250 volts to ground and circuits less than 250 volts to ground.

False

The bonding connection for a metal water piping system is required to be readily accessible unless it is a buried connection or a connection made using the exothermic welding process.

False

Bonding of electrical equipment is important for a grounded system because it accomplishes all but which of the following?

I. It always provides grounding connection to the Earth. II. It eliminates voltage gradients in the earth.

List the three characteristics that an effective ground-fault return path is required to have in order to maintain and provide adequate safety.

II. Be electrically continuous IV. Have sufficiently low impedance to limit the voltage to ground and to facilitate the operation of the circuit protective devices V. Have the capacity to conduct safely any fault current likely to be imposed on it

Which part of Article 250 provides specific electrical bonding requirements?

Part V

? requires that metal water piping systems and other metal piping systems installed within or attached to buildings or structures be bonded.

Section 250.104

Which of the following tables is used to size bonding conductors or jumpers for interior metal water piping systems?

Table 250.102(C)(1)

Which NEC table is used to size equipment bonding jumpers on the load side of a fuse or circuit breaker?

Table 250.122

An equipment bonding jumper from a metal box to a grounding-type receptacle is not necessary for a self-grounding type receptacle.

True

An equipment bonding jumper is permitted to be installed either inside or outside of a raceway or enclosure.

True

Bonding wedges are suitable for use to accomplish the bonding required by 250.92(B)(2) through (4).

True

Standard boxes with concentric and eccentric knockouts that are listed as suitable for bonding can be used in circuits greater than 250 volts to ground and circuits less than 250 volts phase-to-ground.

True

The grounded conductor of each separately derived system shall be bonded to the nearest available point of the metal water piping system(s) in the area served by the separately derived system.

True

The largest size bonding jumper or conductor required for interconnected exposed structural metal building frames is 3/0 AWG copper or 250 kcmil aluminum or copper-clad aluminum.

True

Where more than one raceway enters or leaves a switchboard, pull or junction box, or other equipment, it is permissible to use a single conductor to bond these raceways to the equipment where sized appropriately.

True

Nonconductive coatings on equipment to be grounded shall be removed from threads and other contact surfaces to ensure good electrical continuity or else shall be connected by means of fittings designed to make such removal unnecessary.

True 250.12

Which of the following is not recognized in the Code as an acceptable method of attaching bonding jumpers to circuits and equipment?

VI. Sheet metal screws VII. Solder connections

When two conductive parts are connected together to establish electrical continuity and conductivity between them, they are ? .

bonded

The metal water piping system is permitted to be bonded to the service equipment enclosure, the grounded conductor at the service, the grounding electrode conductor where large enough, or to one or more grounding ? .

electrodes

A(n) ? is generally required to connect the grounding terminal of a grounding-type receptacle to a grounded box.

equipment bonding jumper

A(n) ? is the connection between two or more portions of the equipment grounding conductor.

equipment bonding jumper

Where loosely jointed metal raceways are used, and especially where there are expansion-deflection or deflection fittings or expansion joints with telescoping sections of raceways, the NEC requires that they be made electrically continuous by the use of a(n) ? unless the fitting is listed for use without a field-installed equipment bonding jumper.

equipment bonding jumper

Fittings for wiring methods such as electrical metallic tubing and rigid metal conduit are required to be ? .

listed

A ? is a conductor installed on the supply side of a service or separately derived system to ensure the required electrical conductivity between metal parts required to be electrically connected.

supply-side bonding jumper

A system bonding jumper is the connection between the grounded conductor and the equipment grounding conductor or ? , or both, at a separately derived system.

supply-side bonding jumper


Conjuntos de estudio relacionados

Marketing 3650 Ch. 10 Practice Test

View Set

Natural Disasters Exam 2, Chapter 7 Exam (Volcano Case Histories:Killer Events), Chapter 6 Exam (Volcanic Eruptions:Plate Tectonics and Magma)

View Set