MGT 399 Final

¡Supera tus tareas y exámenes ahora con Quizwiz!

The following mechanisms help to assure quality expectations are met: 1. Audits, inspections, and standards throughout the project. 2. Inspections only at the end of the project. 3. Only a list of standards is needed at the start of the project 4. No mechanisms are needed to assure quality.

1. Audits, inspections, and standards throughout the project.

The RFP must include the customer requirements and the name of the sponsor's designee True False

False The RFP must include the customer requirements. The name of the sponsor's designee is not required even though knowing the name would be helpful for contacting the sponsor.

This longest path in the overall network diagram is called the network path. True False

False This longest path in the overall network diagram is called the critical path.

Risk response planning involves all the following except 1. developing an action plan to reduce the likelihood of occurrence or potential impact of each risk. 2. establishing a trigger point for when to implement the actions to address each risk. 3. assigning responsibility to specific individuals for implementing each response plan. 4. brainstorming the possible risks that could occur in the project.

4. brainstorming the possible risks that could occur in the project.

Proposals are often organized into three sections: 1. Technical, Cost, and schedule 2. technical, legal, and operational. 3. management, cost, and schedule. 4. technical, management, and cost.

4. technical, management, and cost.


Conjuntos de estudio relacionados

Macroeconomics - 40% of assessment

View Set

P2P Chapter 4 Parliamentary reform and the Great Reform Act 1832

View Set

Labor Unions and Laissez Faire Capitalism

View Set

Bravo Ingredient/Sauce Descriptions

View Set

Chapter Eleven: Federal Tax and Health Insurance

View Set

SAUNDERS Respiratory Practice Questions

View Set

BIO 110 EXAM 4 CHAPTER 16- POPULATION ECOLOGY

View Set