7. The main outputs of scope definition are the _____ and project document updates.

ANS: project scope statement

10. The _____ includes the approved project scope statement and its associated WBS and WBS dictionary.

ANS: scope baseline

8. The scope of a project is clear and specific from the start.

FALSE

12. The scope baseline in a WBS consists of the requirements documentation and enterprise environmental factors.

FALSE The scope baseline includes the approved project scope statement and its associated WBS and WBS dictionary.

____________________ is a technique that uses branches radiating out from a core idea to structure thoughts and ideas.

Mind mapping

63. Some organizations prescribe the form and content for WBSs for particular projects. These are known as _____.

guidelines

33. A(n) _____ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project.

work breakdown structure

A(n) ____ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project. a. project charter c. project scope statement b. business case d. work breakdown structure

work breakdown structure

In the WBS, the name of the entire project is the top box, called Level ____. a. 0 c. 2 b. 1 d. 3

1

75. List and briefly describe five approaches for creating work breakdown structures.

*Using Guidelines If guidelines for developing a WBS exist, it is very important to follow them. Some organizations—the U.S. Department of Defense (DOD) for example—prescribe the form and content for WBSs for particular projects. Many organizations provide guidelines and templates for developing WBSs, as well as examples of WBSs from past projects. At the request of many of its members, the Project Management Institute recently developed a WBS Practice Standard to provide guidance for developing and applying the WBS to project management. Project managers and their teams should review appropriate information to develop their unique project WBSs more efficiently. *The Analogy Approach In the analogy approach, you use a similar project's WBS as a starting point. Some organizations keep a repository of WBSs and other project documentation on file to assist people working on projects. Viewing examples of other similar projects' WBSs allows you to understand different ways to create a WBS. *The Top-down and Bottom-up Approaches Most project managers consider the top-down approach of WBS construction to be conventional. To use the top-down approach, start with the largest items of the project and break them into their subordinate items. This process involves refining the work into greater and greater levels of detail. After finishing the process, all resources should be assigned at the work package level. The top-down approach is best suited to project managers who have vast technical insight and a big-picture perspective. In the bottom-up approach, team members first identify as many specific tasks related to the project as possible. They then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS. The bottom-up approach can be very time-consuming, but it can also be a very effective way to create a WBS. Project managers often use the bottom-up approach for projects that represent entirely new systems or approaches to doing a job, or to help create buy-in and synergy with a project team. *Mind Mapping Mind mapping is a technique that uses branches radiating out from a core idea to structure thoughts and ideas. Instead of writing tasks down in a list or immediately trying to create a structure for tasks, mind mapping allows people to write and even draw pictures of ideas in a nonlinear format. This more visual, less structured approach to defining and then grouping tasks can unlock creativity among individuals and increase participation and morale among teams. After discovering WBS items and structure using the mind-mapping technique, you could then translate the information into chart or tabular form. Mind mapping can be used for developing WBSs using the top-down or bottom-up approach.

In the WBS, the main groupings for the work are listed in Level ____. a. 0 c. 2 b. 1 d. 3

2

21. A unit of work should appear at only one place in the WBS.

: TRUE A basic principle of creating a good WBS and its WBS dictionary is that a unit of work should appear at only one place in the WBS.

A(n) _____ is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed. a. requirements traceability matrix b. Gantt chart c. state transition table d. entity-attribute-value model

A

73. List and briefly describe the six main processes involved in project scope management.

1. Planning scope management involves determining how the project's scope and requirements will be managed. The project team works with appropriate stakeholders to create a scope management plan and requirements management plan. 2. Collecting requirements involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them. The project team creates stakeholder requirements documentation, a requirements management plan, and a requirements traceability matrix as outputs of the requirements collection process. 3. Defining scope involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved. The main outputs of scope definition are the project scope statement and updates to project documents. 4. Creating the WBS involves subdividing the major project deliverables into smaller, more manageable components. The main outputs include a work breakdown structure, a WBS dictionary, a scope baseline, and updates to project documents. 5. Verifying scope involves formalizing acceptance of the project deliverables. Key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables during this process. If the deliverables are not acceptable, the customer or sponsor usually requests changes. The main outputs of this process, therefore, are accepted deliverables, change requests, work performance information, and updates to project documents. 6. Controlling scope involves controlling changes to project scope throughout the life of the project—a challenge on many information technology projects. Scope changes often influence the team's ability to meet project time and cost goals, so project managers must carefully weigh the costs and benefits of scope changes. The main outputs of this process are work performance information, change requests, and updates to the project management plan, project documents, and organizational process assets.

Creating the WBS is a subprocess associated with the _____ process in project scope management. a. planning b. monitoring and controlling c. closing d. executing

A

Scope creep refers to: a. the tendency for project scope to keep getting bigger and bigger. b. subdividing project deliverables into smaller pieces. c. the approved project scope statement and its associated WBS. d. a task at the lowest level of the WBS.

A

____ refers to the process of developing a working replica of the system or some aspect of the system. a. Prototyping b. Variance c. Decomposition d. Use case modeling

A

_____ involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them. a. Collecting requirements b. Defining scope c. Controlling scope d. Validating scope

A

_____ involves formal acceptance of the completed project scope by the stakeholders. a. Scope validation b. Scope planning c. Scope control d. Scope baseline

A

9. A(n) _____ is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed. a. requirements traceability matrix b. Gantt chart c. state transition table d. entity-attribute-value model

A A requirements traceability matrix (RTM) is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed.

3. _____ involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them. a. Collecting requirements b. Defining scope c. Controlling scope d. Validating scope

A Collecting requirements involves defining and documenting the features and functions of the products for the project as well as the processes used for creating them. The project team creates requirements documentation and a requirements traceability matrix as outputs of the requirements collection process.

6. Creating the WBS is a subprocess associated with the _____ process in project scope management. a. planning b. monitoring and controlling c. closing d. executing

A Creating the WBS is a subprocess associated with the planning process of the project scope management.

. 23. _____ refers to the process of developing a working replica of the system or some aspect of the system. a. Prototyping b. Variance c. Decomposition d. Use case modeling

A Prototyping involves developing a working replica of the system or some aspect of the system.

20. Scope creep refers to: a. the tendency for project scope to keep getting bigger and bigger. b. subdividing project deliverables into smaller pieces. c. the approved project scope statement and its associated WBS. d. a task at the lowest level of the WBS.

A Scope creep refers to the tendency for project scope to keep getting bigger and bigger.

21. _____ involves formal acceptance of the completed project scope by the stakeholders. a. Scope validation b. Scope planning c. Scope control d. Scope baseline

A Scope validation involves formal acceptance of the completed project deliverables. This acceptance is often achieved by a customer inspection and then sign-off on key deliverables.

43. Which of the following is recommended for the creation of a good WBS?

A unit of work should appear at only one place in the WBS.

74. What is a work breakdown structure? What are the inputs and tools used for creating one?

A work breakdown structure (WBS) is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project. Because most projects involve many people and many different deliverables, it is important to organize and divide the work into logical parts based on how the work will be performed. The WBS is a foundation document in project management because it provides the basis for planning and managing project schedules, costs, resources, and changes. Since the WBS defines the total scope of the project, some project management experts believe that work should not be done on a project if it is not included in the WBS. Therefore, it is crucial to develop a good WBS. The project scope statement, stakeholder requirements documentation, and organizational process assets are the primary inputs for creating a WBS. The main tool or technique is decomposition, that is, subdividing project deliverables into smaller pieces. The outputs of the process of creating the WBS are the WBS itself, the WBS dictionary, a scope baseline, and project document updates.

Work package

A(n) ____ is a task at the lowest level of the WBS.

work package

A(n) ____ is a task at the lowest level of the WBS.

Work breakdown structure

A(n) _____ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project.

work breakdown structure

A(n) _____ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project.

Requirements traceability matrix

A(n) _____ is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed.

requirements traceability matrix

A(n) _____ is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed.

8. A(n) _____ is a deliverable-oriented grouping of the work involved in a project that defines its total scope.

ANS: WBS work breakdown structure

4. Creating the _____ involves subdividing the major project deliverables into smaller, more manageable components.

ANS: WBS work breakdown structure work breakdown structure (WBS) WBS (work breakdown structure)

6. A(n) _____ is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed.

ANS: requirements traceability matrix requirements traceability matrix (RTM) RTM

18. The _____ technique for creating a WBS uses branches radiating from a core idea to structure thoughts and ideas instead of writing down tasks in a list or immediately trying to create a structure for tasks. a. analogy b. bottom-up c. top-down d. mind mapping

ANS: D Mind mapping is a technique that uses branches radiating from a core idea to structure thoughts and ideas.Instead of writing down tasks in a list or immediately trying to create a structure for tasks, mind mapping allows people to write and even draw pictures of ideas in a nonlinear format.

16. _____ is a technique that uses branches radiating out from a core idea to structure thoughts and ideas when creating a WBS.

ANS: Mind mapping

1. _____ includes the processes involved in defining and controlling what work is or is not included in a project.

ANS: Project scope management

22. _____ involves developing a working replica of the system or some aspect of the system.

ANS: Prototyping

5. _____ refer to "conditions or capabilities that must be met by the project or present in the product, service, or result to satisfy an agreement or other formally imposed specification."

ANS: Requirements

2. _____ refers to all the work involved in creating the products of the project and the processes used to create them.

ANS: Scope

20. _____ involves controlling changes to the project scope while keeping project goals and business strategy in mind.

ANS: Scope control

18. _____ is the tendency for project scope to keep getting bigger and bigger.

ANS: Scope creep

23. _____ is a process for identifying and modeling business events, who initiated them, and how the system should respond to them.

ANS: Use case modeling

21. _____ is the difference between planned and actual performance.

ANS: Variance

17. A(n) _____ is a document that describes detailed information about each WBS item.

ANS: WBS dictionary

15. In the _____ approach to creating a WBS, team members first identify as many specific tasks related to the project as possible.

ANS: bottom-up

9. Subdividing the project deliverables into smaller pieces is known as _____.

ANS: decomposition

14. Some organizations prescribe the form and content for WBSs for particular projects. These are known as _____.

ANS: guidelines

19. The main tool for performing scope validation is _____ and group decision making techniques

ANS: inspection

13. A work package is a task at the _____ level of the WBS.

ANS: lowest

3. The main outputs of _____are the project scope statement and updates to project documents.

ANS: scope definition

11. Tasks in a WBS that are decomposed into smaller tasks are called _____ tasks.

ANS: summary

12. PMI uses the term "_____" to describe each level of work in the WBS.

ANS: task

Generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization is known as _____. a. variance b. benchmarking c. prototyping d. decomposition

B

In the _____ approach, team members first identify as many specific tasks related to the project as possible and then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS. a. analogy b. bottom-up c. top-down d. mind mapping

B

The _____ should list and describe all of the deliverables required for the project. a. project charter b. scope statement c. WBS d. Gantt chart

B

The ______ documents how project needs will be analyzed, documented, and managed. a. requirements traceability matrix b. requirements management plan c. WBS d. project scope statement

B

Which of the following is recommended for the creation of a good WBS? a. Any WBS item should be the responsibility of all the people working on it. b. A unit of work should appear at only one place in the WBS. c. Each WBS item should be created assuming that the requirements are inflexible. d. The work content of a WBS item is independent of the WBS items below it.

B

_____ involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved. a. Creating scope b. Defining scope c. Controlling scope d. Validating scope

B

_____ refers to the difference between planned and actual performance. a. Decomposition b. Variance c. Scope validation d. Scope creep

B

_____ uses highly organized and intensive workshops to bring together project stakeholders—the sponsor, users, business analysts, programmers, and so on—to jointly define and design information systems. a. Prototyping b. JAD c. RAD d. Use case modeling

B

8. Generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization is known as _____. a. variance b. benchmarking c. prototyping d. decomposition

B Benchmarking, or generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization, can be used to collect requirements.

4. _____ involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved. a. Creating scope b. Defining scope c. Controlling scope d. Validating scope

B Defining scope involves reviewing the scope management plan, project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved.

17. In the _____ approach, team members first identify as many specific tasks related to the project as possible and then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS. a. analogy b. bottom-up c. top-down d. mind mapping

B In the bottom-up approach, team members first identify as many specific tasks related to the project as possible. They then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS. Project managers often use the bottom-up approach for projects that represent entirely new systems or approaches to doing a job, or to help create buy-in and synergy with a project team.

25. _____ uses highly organized and intensive workshops to bring together project stakeholders—the sponsor, users, business analysts, programmers, and so on—to jointly define and design information systems. a. Prototyping b. JAD c. RAD d. Use case modeling

B Joint Application Design (JAD) uses highly organized and intensive workshops to bring together project stakeholders — the sponsor, users, business analysts, programmers, and so on —to jointly define and design information systems.

19. Which of the following is recommended for the creation of a good WBS? a. Any WBS item should be the responsibility of all the people working on it. b. A unit of work should appear at only one place in the WBS. c. Each WBS item should be created assuming that the requirements are inflexible. d. The work content of a WBS item is independent of the WBS items below it.

B Some basic principles apply to creating any good WBS and its WBS dictionary. Firstly, a unit of work should appear at only one place in the WBS. The work content of a WBS item is the sum of the WBS items below it.

7. The ______ documents how project needs will be analyzed, documented, and managed. a. requirements traceability matrix b. requirements management plan c. WBS d. project scope statement

B The requirements management plan documents how project requirements will be analyzed, documented, and managed.

13. The _____ should list and describe all of the deliverables required for the project. a. project charter b. scope statement c. WBS d. Gantt chart

B The scope statement should list and describe all of the deliverables required for the project. It is very important to ensure consistency between the project charter, scope statement, WBS, and Gantt chart to define the scope of the project accurately.

22. _____ refers to the difference between planned and actual performance. a. Decomposition b. Variance c. Scope validation d. Scope creep

B Variance is the difference between planned and actual performance

Mind mapping can be used for developing WBSs using a. the analogy approach only b. the bottom-up or analogy approach c. the top-down or bottom-up approach d. any approach

C

The _____ approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items. a. analogy b. bottom-up c. top-down d. mind mapping

C

The main technique used in creating a WBS is _____, which involves subdividing project deliverables into smaller pieces. a. conglomeration b. accumulation c. decomposition d. catalyzation

C

The term ______ describes a product produced as part of a project. a. variance b. scope c. deliverable d. work package

C

11. The main technique used in creating a WBS is _____, which involves subdividing project deliverables into smaller pieces. a. conglomeration b. accumulation c. decomposition d. catalyzation

C The main tool or technique involved in creating a WBS is decomposition—that is, subdividing project deliverables into smaller pieces.

1. The term ______ describes a product produced as part of a project. a. variance b. scope c. deliverable d. work package

C Thee term deliverable describes a product created as part of a project. Deliverables can be product related, such as a piece of hardware or software, or process-related, such as a planning document or meeting minutes.

16. The _____ approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items. a. analogy b. bottom-up c. top-down d. mind mapping

C To use the top-down approach, start with the largest items of the project and break them into subordinate items.The top-down approach is best suited to project managers who have vast technical insight and a big-picture perspective.

15. The _____ approach for constructing a WBS involves refining the work into greater and greater levels of detail. a. analogy b. bottom-up c. top-down d. mind mapping

C To use the top-down approach, start with the largest items of the project and break them into subordinate items. This process involves refining the work into greater and greater levels of detail.

26. _____ involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them.

Collecting requirements

____ involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them. a. Collecting requirements c. Controlling scope b. Defining scope d. Verifying scope

Collecting requirements

____ involves controlling changes to project scope throughout the life of the project, which is a challenge on many information technology projects. a. Planning scope c. Controlling scope b. Defining scope d. Verifying scope

Controlling scope

Planning

Creating the WBS is a subprocess associated with the _____ process in project scope management.

planning

Creating the WBS is a subprocess associated with the _____ process in project scope management.

A(n) ____ is a task at the lowest level of the WBS. a. variance b. objective c. deliverable d. work package

D

A(n) _____ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project. a. project charter b. business case c. project scope statement d. work breakdown structure

D

In the _____approach for constructing a WBS, you use a similar project's WBS as a starting point. a. top-down b. bottom-up c. mind-mapping d. analogy

D

Scope refers to: a. each level of work that is outlined in a work breakdown structure. b. the end product created as part of a project that is delivered to the client. c. tasks that are decomposed into smaller tasks in a work breakdown structure. d. the work involved in creating the products and the processes used to create them.

D

The _____ technique for creating a WBS uses branches radiating from a core idea to structure thoughts and ideas instead of writing down tasks in a list or immediately trying to create a structure for tasks. a. analogy b. bottom-up c. top-down d. mind mapping

D

_____ involves formalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables. a. Creating scope b. Defining scope c. Controlling scope d. Validating scope

D

_____ is a process for identifying and modeling business events, who initiated them, and how the system should respond to them. a. Prototyping b. JAD c. RAD d. Use case modeling

D

14. In the _____approach for constructing a WBS, you use a similar project's WBS as a starting point. a. top-down b. bottom-up c. mind-mapping d. analogy

D A method for constructing a WBS is the analogy approach. In the analogy approach, you use a similar project's WBS as a starting point.

12. A(n) ____ is a task at the lowest level of the WBS. a. variance b. objective c. deliverable d. work package

D A work package is a task at the lowest level of the WBS.

10. A(n) _____ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project. a. project charter b. business case c. project scope statement d. work breakdown structure

D After collecting requirements and defining scope, the next step in project scope management is to create a work breakdown structure. A work breakdown structure (WBS) is a deliverable oriented grouping of the work involved in a project that defines its total scope

2. Scope refers to: a. each level of work that is outlined in a work breakdown structure. b. the end product created as part of a project that is delivered to the client. c. tasks that are decomposed into smaller tasks in a work breakdown structure. d. the work involved in creating the products and the processes used to create them.

D Scope refers to all the work involved in creating the products of the project and the processes used to create them.

24. _____ is a process for identifying and modeling business events, who initiated them, and how the system should respond to them. a. Prototyping b. JAD c. RAD d. Use case modeling

D Use case modeling is a process for identifying and modeling business events, who initiated them, and how the system should respond to them. It is an effective tool for understanding requirements of information systems.

5. _____ involves formalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables. a. Creating scope b. Defining scope c. Controlling scope d. Validating scope

D Validating scope involves formalizing acceptance of the project deliverables. Key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables during this process.

27. _____ involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved.

Defining scope

____ involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved. a. Planning scope c. Controlling scope b. Defining scope d. Verifying scope

Defining scope

12. The scope baseline in a WBS consists of the requirements documentation and enterprise environmental factors.

FALSE

13. The WBS is organized solely around project phases.

FALSE

14. A work package represents one component of the product that the project aims to deliver.

FALSE

15. A work package must always represent less than 80 hours of work.

FALSE

16. Given the project management software that is available, it is relatively easy to create a good WBS.

FALSE

17. The tasks in a WBS must be developed as a sequential list of steps.

FALSE

18. The executing tasks of the WBS remain constant from project to project.

FALSE

2. Deliverables are only product-related, such as a piece of hardware or software.

FALSE

21. The format of the WBS dictionary is essentially the same for all projects.

FALSE

5. The project's size, complexity, importance, and other factors do not affect how much effort is spent on collecting requirements for scope planning.

FALSE

7. Project scope statements must include the project boundaries, constraints, and assumptions.

FALSE

16. The tasks in a WBS must be developed as a sequential list of steps.

FALSE A concern when creating a WBS is how to organize it to provide the basis for the project schedule. You should focus on what work needs to be done and how it will be done, not when it will be done. In other words, the tasks do not have to be developed as a sequential list of steps.

13. The WBS is organized solely around project phases.

FALSE A project team often organizes the WBS around project products, project phases, or the project management process groups.

14. A work package represents one component of the product that the project aims to deliver.

FALSE A work package is a task at the lowest level of the WBS. It represents the level of work that the project manager monitors and controls.

15. A work package must always represent less than 80 hours of work.

FALSE A work package represents the level of work that the project manager monitors and controls. If a project has a relatively short time frame and requires weekly progress reports, a work package might represent work completed in one week or less. If a project has a very long time frame and requires quarterly progress reports, a work package might represent work completed in one month or more.

8. The scope of a project is clear and specific from the start.

FALSE As time progresses, the scope of a project should become more clear and specific.

2. Deliverables are only product-related, such as a piece of hardware or software.

FALSE Deliverables can be product-related, such as a piece of hardware or software, or process-related, such as a planning document or meeting minutes.

7. Project scope statements must include the project boundaries, constraints, and assumptions.

FALSE Project scope statements should include at least a product scope description, product user acceptance criteria, and detailed information on all project deliverables. It is also helpful to document other scope-related information, such as the project boundaries, constraints, and assumptions.

17. The executing tasks of the WBS remain constant from project to project.

FALSE The executing tasks vary the most from project to project, but many of the tasks under the other project management process groups would be similar for all projects.

5. The project's size, complexity, importance, and other factors do not affect how much effort is spent on collecting requirements for scope planning.

FALSE The project's size, complexity, importance, and other factors affect how much effort is spent on collecting requirements.

20. The format of the WBS dictionary is essentially the same for all projects.

FALSE WBS dictionary is a document that provides detailed information about each WBS item. The format of the WBS dictionary can vary based on project needs.

A WBS is often depicted as a task-oriented pie chart.

False

A project team always organizes the WBS around project products.

False

A work package must always represent less than 80 hours of work. a. True b. False

False

A work package represents one component of the product that the project aims to deliver. a. True b. False

False

A work package should always represent less than 80 hours of work.

False

Deliverables are only product-related, such as a piece of hardware or software.

False

Deliverables are only product-related, such as a piece of hardware or software. a. True b. False

False

Given the project management software that is available, it is relatively easy to create a good WBS. a. True b. False

False

It is easy to create a good WBS.

False

Project scope statements must include the project boundaries, constraints, and assumptions. a. True b. False

False

Project scope statements should include, at a minimum, a product scope description and detailed information on all project deliverables.

False

The WBS is organized solely around project phases. a. True b. False

False

The executing tasks of the WBS remain constant from project to project.

False

The executing tasks of the WBS remain constant from project to project. a. True b. False

False

The project scope statement provides the basis for planning and managing project schedules, costs, resources, and changes.

False

The project's size, complexity, importance, and other factors do not affect how much effort is spent on collecting requirements for scope planning. a. True b. False

False

The project's size, complexity, importance, and other factors will not affect how much effort is spent on collecting requirements for scope planning.

False

The scope baseline in a WBS consists of the requirements documentation and enterprise environmental factors. a. True b. False

False

The scope of a project is clear and specific from the start. a. True b. False

False

The scope of a project should be clear and specific from the start.

False

The tasks in a WBS must be developed as a sequential list of steps. a. True b. False

False

Benchmarking

Generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization is known as _____.

benchmarking

Generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization is known as _____.

bottom-up

In the _____ approach, team members first identify as many specific tasks related to the project as possible and then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS.

analogy

In the _____approach for constructing a WBS, you use a similar project's WBS as a starting point.

49. _____ uses highly organized and intensive workshops to bring together project stakeholders—the sponsor, users, business analysts, programmers, and so on—to jointly define and design information systems.

JAD

____ uses highly organized and intensive workshops to bring together project stakeholders—the sponsor, users, business analysts, programmers, and so on—to jointly define and design information systems. a. Prototyping c. RAD b. JAD d. Use case modeling

JAD COMPLETION

65. _____ is a technique that uses branches radiating out from a core idea to structure thoughts and ideas when creating a WBS.

Mind mapping

____________________ can be used for developing WBSs using the top-down or bottom-up approach.

Mind mapping

50. _____ includes the processes involved in defining and controlling what work is or is not included in a project.

Project scope management

47. _____ refers to the process of developing a working replica of the system or some aspect of the system.

Prototyping

71. _____ involves developing a working replica of the system or some aspect of the system.

Prototyping

54. _____ refer to "conditions or capabilities that must be met by the project or present in the product, service, or result to satisfy an agreement or other formally imposed specification."

Requirements

51. _____ refers to all the work involved in creating the products of the project and the processes used to create them.

Scope

69. _____ involves controlling changes to the project scope while keeping project goals and business strategy in mind.

Scope control

____________________ involves controlling changes to the project scope.

Scope control

67. _____ is the tendency for project scope to keep getting bigger and bigger.

Scope creep

____________________ is the tendency for project scope to keep getting bigger and bigger.

Scope creep

the tendency for project scope to keep getting bigger and bigger.

Scope creep refers to:

The work involved in creating the products and the processes used to create them.

Scope refers to:

the work involved in creating the products and the processes used to create them.

Scope refers to:

45. _____ involves formal acceptance of the completed project scope by the stakeholders.

Scope validation

____ involves formal acceptance of the completed project scope by the stakeholders. a. Scope verification c. Scope control b. Scope planning d. Scope definition

Scope verification

76. Describe the process of scope verification.

Scope verification involves formal acceptance of the completed project scope by the stakeholders. This acceptance is often achieved by a customer inspection and then sign-off on key deliverables. To receive formal acceptance of the project scope, the project team must develop clear documentation of the project's products and procedures to evaluate if they were completed correctly and satisfactorily. To minimize scope changes, it is crucial to do a good job of verifying project scope. The scope management plan, scope baseline, requirements documentation, requirements traceability matrix, validated deliverables, and work performance data are the main inputs for scope validation. The main tools for performing scope validation are inspection and group decision-making techniques. The customer, sponsor, or user inspects the work after it is delivered and decides if it meets requirements. The main outputs of scope validation are accepted deliverables, change requests, work performance information, and project documents updates.

1. Scope refers to all the work involved in creating the products of the project and the processes used to create them.

TRUE

10. The project scope statement should reference supporting documents, such as product specifications that will affect what products are produced or purchased, or corporate policies, which might affect how products or services are produced.

TRUE

11. The project scope statement, stakeholder requirements documentation, and organizational process assets are the primary inputs for creating a WBS.

TRUE

19. Many organizations provide different guidelines and templates for developing WBSs.

TRUE

20. Mind mapping allows people to write and even draw pictures of ideas in a nonlinear format.

TRUE

22. A unit of work should appear at only one place in the WBS.

TRUE

23. Scope creep if not managed well can lead to the failure of information technology projects.

TRUE

3. Project scope management includes the processes involved in defining and controlling what is or is not included in a project.

TRUE

4. The scope management plan can be informal and broad or formal and detailed, based on the needs of the project.

TRUE

6. Information from the project charter provides a basis for further defining the project scope.

TRUE

9. Many information technology projects also require detailed functional and design specifications for developing software, which also should be referenced in the detailed scope statement.

TRUE

22. Scope creep if not managed well can lead to the failure of information technology projects.

TRUE Even when the project scope is fairly well defined, many IT projects suffer from scope creep—the tendency for project scope to keep getting bigger and bigger. Many IT projects fail due to scope creep.

19. Mind mapping allows people to write and even draw pictures of ideas in a nonlinear format.

TRUE Instead of writing down tasks in a list or immediately trying to create a structure for tasks, mind mapping allows people to write and even draw pictures of ideas in a nonlinear format. This more visual, less structured approach to defining and then grouping tasks can unlock creativity among individuals and increase participation and morale among teams.

9. Many information technology projects also require detailed functional and design specifications for developing software, which also should be referenced in the detailed scope statement.

TRUE Many IT projects require detailed functional and design specifications for developing software, which also should be referenced in the detailed scope statement.

18. Many organizations provide different guidelines and templates for developing WBSs.

TRUE Many organizations provide guidelines and templates for developing WBSs, as well as examples of WBSs from past projects. Microsoft Project 2010 comes with several templates, and more are available on Microsoft's Web site and other sites.

Scope refers to all the work involved in creating the products of the project and the processes used to create them.

TRUE One of the most important and most difficult aspects of project management is defining the scope of a project. Scope refers to all the work involved in creating the products of the project and the processes used to create them.

3. Project scope management includes the processes involved in defining and controlling what is or is not included in a project.

TRUE Project scope management includes the processes involved in defining and controlling what work is or is not included in a project. It ensures that the project team and stakeholders have the same understanding of what products the project will produce and what processes the project team will use to produce them.

6. Information from the project charter provides a basis for further defining the project scope.

TRUE The charter describes the high-level scope, time, and cost goals for the project objectives and success criteria, a general approach to accomplishing the project's goals, and the main roles and responsibilities of important project stakeholders.

11. The project scope statement, stakeholder requirements documentation, and organizational process assets are the primary inputs for creating a WBS.

TRUE The project scope management plan, scope statement, requirements documentation, enterprise environmental factors, and organizational process assets are the primary inputs for creating a WBS.

10. The project scope statement should reference supporting documents, such as product specifications that will affect what products are produced or purchased, or corporate policies, which might affect how products or services are produced.

TRUE The project scope statement should reference supporting documents, such as product specifications that will affect what products are created or purchased, or corporate policies, which might affect how products or services are produced.

4. The scope management plan can be informal and broad or formal and detailed, based on the needs of the project.

TRUE The scope management plan is a subsidiary part of the project management plan. It can be informal and broad or formal and detailed, based on the needs of the project.

top-down

The _____ approach for constructing a WBS involves refining the work into greater and greater levels of detail.

top-down

The _____ approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items.

Scope statement

The _____ should list and describe all of the deliverables required for the project.

scope statement

The _____ should list and describe all of the deliverables required for the project.

Requirements management plan

The ______ documents how project needs will be analyzed, documented, and managed.

Decomposition

The main technique used in creating a WBS is _____, which involves subdividing project deliverables into smaller pieces.

decomposition

The main technique used in creating a WBS is _____, which involves subdividing project deliverables into smaller pieces.

.deliverable

The term ______ describes a product produced as part of a project.

Deliverable

The term ______ describes a product produced as part of a project.

A unit of work should appear at only one place in the WBS.

True

A unit of work should appear at only one place in the WBS. a. True b. False

True

A work package represents the level of work that the project manager monitors and controls.

True

If you want some time-based flow for the work, you can create a WBS using the project management process groups of initiating, planning, executing, monitoring and controlling, and closing as Level 2 in the WBS.

True

Information from the project charter provides a basis for further defining the project scope.

True

Information from the project charter provides a basis for further defining the project scope. a. True b. False

True

Lack of user input leads to problems with managing scope creep and controlling change.

True

Many information technology projects also require detailed functional and design specifications for developing software, which also should be referenced in the detailed scope statement.

True

Many information technology projects also require detailed functional and design specifications for developing software, which also should be referenced in the detailed scope statement. a. True b. False

True

Many organizations provide different guidelines and templates for developing WBSs. a. True b. False

True

Many organizations provide guidelines and templates for developing WBSs.

True

Mind mapping allows people to write and even draw pictures of ideas in a nonlinear format.

True

Mind mapping allows people to write and even draw pictures of ideas in a nonlinear format. a. True b. False

True

Project scope management includes the processes involved in defining and controlling what is or is not included in a project.

True

Project scope management includes the processes involved in defining and controlling what is or is not included in a project. a. True b. False

True

Scope creep if not managed well can lead to the failure of information technology projects. a. True b. False

True

Scope refers to all the work involved in creating the products of the project and the processes used to create them. a. True b. False

True

The format of the WBS dictionary is essentially the same for all projects. a. True b. False

True

The project scope statement should reference supporting documents, such as product specifications that will affect what products are produced or purchased, or corporate policies, which might affect how products or services are produced. a. True b. False

True

The project scope statement, stakeholder requirements documentation, and organizational process assets are the primary inputs for creating a WBS. a. True b. False

True

The scope management plan can be informal and broad or formal and detailed, based on the needs of the project. a. True b. False

True

You can only enter duration estimates for work packages.

True

48. _____ is a process for identifying and modeling business events, who initiated them, and how the system should respond to them.

Use case modeling

72. _____ is a process for identifying and modeling business events, who initiated them, and how the system should respond to them.

Use case modeling

____ is a process for identifying and modeling business events, who initiated them, and how the system should respond to them. a. Prototyping c. RAD b. JAD d. Use case modeling

Use case modeling

28. _____ involves formalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables.

Validating scope

46. _____ refers to the difference between planned and actual performance.

Variance

70. _____ is the difference between planned and actual performance.

Variance

____________________ is the difference between planned and actual performance.

Variance

____ involves formalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables during this process. a. Planning scope c. Controlling scope b. Defining scope d. Verifying scope

Verifying scope

57. A(n) _____ is a deliverable-oriented grouping of the work involved in a project that defines its total scope.

WBS

Creating the ____________________ involves subdividing the major project deliverables into smaller, more manageable components.

WBS - work breakdown structure - work breakdown structure (WBS)

Some project management experts believe that work should not be done on a project if it is not included in the ____________________.

WBS - work breakdown structure - work breakdown structure (WBS)

66. A(n) _____ is a document that describes detailed information about each WBS item.

WBS dictionary

A(n) ____________________ is a document that describes detailed information about each WBS item.

WBS dictionary

A unit of work should appear at only one place in the WBS.

Which of the following is recommended for the creation of a good WBS?

Scope validation

_____ involves formal acceptance of the completed project scope by the stakeholders.

Validating scope

_____ involves formalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables.

Defining scope

_____ involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved.

Use case modeling

_____ is a process for identifying and modeling business events, who initiated them, and how the system should respond to them.

Variance

_____ refers to the difference between planned and actual performance.

37. In the _____approach for constructing a WBS, you use a similar project's WBS as a starting point.

analogy

In the ____, you use a similar project's WBS as a starting point. a. top-down approach c. mind-mapping approach b. bottom-up approach d. analogy approach

analogy approach

31. Generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization is known as _____.

benchmarking

41. In the _____ approach, team members first identify as many specific tasks related to the project as possible and then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS.

bottom-up

64. In the _____ approach to creating a WBS, team members first identify as many specific tasks related to the project as possible.

bottom-up

In the ____________________ approach, team members first identify as many specific tasks related to the project as possible.

bottom-up

Project managers often use the ____ approach for projects that represent entirely new systems or approaches to doing a job, or to help create buy-in and synergy with a project team. a. analogy c. top-down b. bottom-up d. mind mapping

bottom-up

The ____ approach involves refining the work into greater and greater levels of detail. a. analogy c. top-down b. bottom-up d. mind mapping

bottom-up

34. The main technique used in creating a WBS is _____, which involves subdividing project deliverables into smaller pieces.

decomposition

58. Subdividing the project deliverables into smaller pieces is known as _____.

decomposition

24. The term ______ describes a product produced as part of a project.

deliverable

The term ____ describes a product produced as part of a project. a. end-product c. deliverable b. scope d. outcome

deliverable

The ____ tasks vary the most from project to project. a. closing c. planning b. monitoring and controlling d. executing

executing

There are ____ main processes involved in project scope management. a. three c. five b. four d. six

five

68. The main tool for performing scope validation is _____ and group decision making techniques.

inspection

The main tool for performing scope verification is ____________________.

inspection

62. A work package is a task at the _____ level of the WBS.

lowest

40. The _____ technique for creating a WBS uses branches radiating from a core idea to structure thoughts and ideas instead of writing down tasks in a list or immediately trying to create a structure for tasks.

mind mapping

29. Creating the WBS is a subprocess associated with the _____ process in project scope management.

planning

Key inputs for preparing the project scope statement include the ____________________, requirements documentation, and organizational process assets such as policies and procedures related to scope statements as well as project files and lessons learned from previous, similar projects.

project charter

Factors such as user involvement, clear business objectives, a minimized or clearly defined scope, and firm basic requirements, are elements of ____________________.

project scope management

56. The main outputs of scope definition are the _____ and project document updates.

project scope statement

An up-to-date ____ is an important document for developing and confirming a common understanding of the project scope. a. scope management plan c. WBS b. project scope statement d. decomposition

project scope statement

The main outputs of scope definition are the ____________________ and project document updates.

project scope statement

30. The ______ documents how project needs will be analyzed, documented, and managed.

requirements management plan

32. A(n) _____ is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed.

requirements traceability matrix

55. A(n) _____ is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed.

requirements traceability matrix (RTM)

Of the following constraints, it is most difficult to describe, agree upon, and meet the ____ goal of many projects. a. scope c. cost b. time d. technical

scope

59. The _____ includes the approved project scope statement and its associated WBS and WBS dictionary.

scope baseline

The approved project scope statement and its associated WBS and WBS dictionary form the ____________________.

scope baseline

The goal of ____ is to influence the factors that cause scope changes, assure changes are processed according to procedures developed as part of integrated change control, and manage changes when they occur. a. scope verification c. scope planning b. scope control d. scope definition

scope control

52. The main outputs of _____are the project scope statement and updates to project documents.

scope definition

Good ____ is very important to project success because it helps improve the accuracy of time, cost, and resource estimates, it defines a baseline for performance measurement and project control, and it aides in communicating clear work responsibilities. a. scope planning c. scope definition b. scope management d. scope verification

scope definition

The main outputs of ____________________ are the project scope statement and updates to project documents.

scope definition

36. The _____ should list and describe all of the deliverables required for the project.

scope statement

The ____ should list and describe all of the deliverables required for the project. a. project charter c. WBS b. scope statement d. Gantt chart

scope statement

60. Tasks in a WBS that are decomposed into smaller tasks are called _____ tasks.

summary

The project scope statement should reference ____________________, such as product specifications that will affect what products are produced or purchased, or corporate policies, which might affect how products or services are produced.

supporting documents

61. PMI uses the term "_____" to describe each level of work in the WBS.

task

PMI uses the term "___________________" to describe each level of work in the WBS.

task

44. Scope creep refers to:

the tendency for project scope to keep getting bigger and bigger.

42. Mind mapping can be used for developing WBSs using

the top-down or bottom-up approach

25. Scope refers to:

the work involved in creating the products and the processes used to create them.

38. The _____ approach for constructing a WBS involves refining the work into greater and greater levels of detail.

top-down

39. The _____ approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items.

top-down

A(n) ____________________ project scope statement is an important document for developing and confirming a common understanding of the project scope.

up-to-date - up to date -

The main outputs of ____ are accepted deliverables and change requests. a. planning scope c. defining scope b. controlling scope d. verifying scope

verifying scope

53. Creating the _____ involves subdividing the major project deliverables into smaller, more manageable components.

work breakdown structure (WBS)

35. A(n) ____ is a task at the lowest level of the WBS.

work package

A(n) ____________________ is a task at the lowest level of the WBS.

work package

Collecting requirements

_____ involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them.

Prototyping

_____ refers to the process of developing a working replica of the system or some aspect of the system.

JAD

_____ uses highly organized and intensive workshops to bring together project stakeholders—the sponsor, users, business analysts, programmers, and so on—to jointly define and design information systems.

The format of the WBS dictionary should be the same from project to project.

False

mind mapping

The _____ technique for creating a WBS uses branches radiating from a core idea to structure thoughts and ideas instead of writing down tasks in a list or immediately trying to create a structure for tasks.

requirements management plan

The ______ documents how project needs will be analyzed, documented, and managed.

Scope refers to all the work involved in creating the products of the project and the processes used to create them.

True

The project scope statement should reference supporting documents, such as product specifications that will affect what products are produced or purchased, or corporate policies, which might affect how products or services are produced.

True

The project scope statement, stakeholder requirements documentation, and organizational process assets are the primary inputs for creating a WBS.

True

The tasks in a WBS do not have to be developed as a sequential list of steps.

True

The ____ approach is best suited to project managers who have vast technical insight and a big-picture perspective. a. analogy c. top-down b. bottom-up d. mind mapping

bottom-up

After discovering WBS items and structure using the ____ technique, you could then translate the information into chart or tabular form. a. analogy c. top-down b. bottom-up d. mind mapping

mind mapping

Many people confuse tasks on a WBS with ____. a. goals c. responsibilities b. objectives d. specifications

specifications

If ____________________ for developing a WBS exist, it is very important to follow them.

guidelines

77. What are some of the suggestions for improving the requirements process?

1. Develop and follow a requirements management process that includes procedures for initial requirements determination. 2. Employ techniques such as prototyping, use case modeling, and Joint Application Design to understand user requirements thoroughly. Prototyping involves developing a working replica of the system or some aspect of the system. These working replicas may be throwaways or an incremental component of the deliverable system. Prototyping is an effective tool for gaining an understanding of requirements, determining the feasibility of requirements, and resolving user interface uncertainties. Use case modeling is a process for identifying and modeling business events, who initiated them, and how the system should respond to them. It is an effective tool for understanding requirements for information systems. Joint Application Design (JAD) uses highly organized and intensive workshops to bring together project stakeholders—the sponsor, users, business analysts, programmers, and so on—to jointly define and design information systems. These techniques also help users become more active in defining system requirements. 3. Put all requirements in writing and keep them current and readily available. Several tools are available to automate this function. For example, a type of software called a requirements management tool aids in capturing and maintaining requirements information, provides immediate access to the information, and assists in establishing necessary relationships between requirements and information created by other tools. 4. Create a requirements management database for documenting and controlling requirements. Computer Aided Software Engineering (CASE) tools or other technologies can assist in maintaining a repository for project data. A CASE tool's database can also be used to document and control requirements. 5. Provide adequate testing to verify that the project's products perform as expected. Conduct testing throughout the project life cycle. 6. Use a process for reviewing requested requirements changes from a systems perspective. 7. Emphasize completion dates. 8. Allocate resources specifically for handling change requests.


Conjuntos de estudio relacionados

Java Quiz 7 - Classes & Functions

View Set

Industrial Economics questions- Everything

View Set

KIV/ZI 1. ročník FEK, Teorie ke zkoušce ze ZI

View Set

ECO - Ch.18 - Open-Economy Macroeconomics: Basic Concepts

View Set