Project Cost Management - Ch 7 (True/False)
Budgetary estimates are made even before a project is officially started.
False
Contingency reserves are also known as unknown unknowns.
False
If cost variance is a positive number, it means that performing the work costs more than planned.
False
If the cost performance index (CPI) is less than 100 percent, the project is under budget.
False
Intangible costs can be easily measured in monetary terms.
False
It is important for project managers to focus on indirect costs because they can be easily controlled.
False
A schedule performance index of one means that the project is on schedule.
True
If an important supplier goes out of business, management reserves can be set aside to cover the resulting costs.
True
In a bottom up estimate, the size of the individual work items is one of the factors that drives the accuracy of the estimates.
True
It is important for project managers to understand that every cost estimate is unique.
True
One of the reasons why project cost estimates are inaccurate is because human beings are biased toward underestimation.
True
A budgetary estimate is the most accurate of the three types of estimates.
False
A negative schedule variance means that it took lesser than planned to perform the work.
False
Analogous estimates are called activity based costing.
False
Analogous estimates are the most accurate technique to estimate costs.
False
The primary output of the planning cost management process is a change request.
False
A cost management plan can include organizational procedures links, control thresholds, and process descriptions.
True
Definitive estimates are made one year or less prior to project completion.
True
Determining the budget involves allocating the project cost estimate to individual work items over time.
True
Estimates should become more accurate as time progresses.
True
IT project managers must be able to present and discuss project information both in financial and technical terms.
True
Supporting details for an estimate include the ground rules and assumptions used in creating the estimate.
True
The formulas for variances and indexes start with EV, the earned value.
True
When deciding what projects to invest in or continue, one should include sunk costs.
False
In an earned value chart, when the actual cost line is right on or above the earned value line, it indicates that costs are less than planned.
False
Overrun is the additional percentage amount by which estimates exceed actual costs.
False
Project managers must conduct cash flow analysis to determine net present value.
True
Spreadsheets are a common tool for cost estimating, cost budgeting, and cost control.
True
The project management plan and project funding requirements are inputs of the process of controlling costs.
True
Parametric models are reliable when the models are flexible in terms of the project's size.
True