project management ch 7

¡Supera tus tareas y exámenes ahora con Quizwiz!

If a company loses $5 for every $100 in revenue for a certain product, what is the profit margin for that product? a. -5 percent b. 5 percent c. -$5 d. $5

a. -5 percent

You are preparing a cost estimate for a building based on its location, purpose, number of square feet, and other characteristics. What cost-estimating technique are you using? a. parametric b. analogous c. bottom-up d. top-down

a. parametric

If a project is halfway completed, its schedule performance index is 110 percent, and its cost performance index is 95 percent, how is it progressing? a. It is ahead of schedule and under budget. b. It is ahead of schedule and over budget. c. It is behind schedule and under budget. d. It is behind schedule and over budget.

b. It is ahead of schedule and over budget.

Which of the following is not an output of the project cost management process called estimating costs, according to the PMBOK Guide? a. activity cost esimates b. a cost baseline c. basis of estimates d. project documents updates

b. a cost baseline

What is the main goal of project cost management? a. to complete a project for as little cost as possible b. to complete a project within an approved budget c. to provide truthful and accurate cost information on projects d. to ensure that an organization's money is used wisely

b. to complete a project within an approved budget

_____ reserves allow for future situations that are unpredictable. a. Contingency b. Financial c. Management d. Baseline

c. Management

_____ involves allocating the project cost estimate to individual material resources or work items over time. a. Reserve analysis b. Life cycle costing c. Project cost budgeting d. Earned value analysis

c. Project cost budgeting

_____ is a project performance measurement technique that integrates scope, time, and cost data. a. Reserve analysis b. Life cycle costing c. Project cost budgeting d. Earned value analysis

d. Earned value analysis

If the actual cost for a WBS item is $1,500 and its earned value is $2,000, what is its cost variance, and is it under or over budget? a. The cost variance is -$500, which is over budget. b. The cost variance is -$500, which is under budget. c. The cost variance is $500, which is over budget. d. The cost variance is $500, which is under budget.

d. The cost variance is $500, which is under budget.

Accountants usually define _____ as a resource sacrificed or foregone to achieve a specific objective. a. money b. liability c. trade d. cost

d. cost


Conjuntos de estudio relacionados

Question 2- There are several different approaches to representation within a democratic political system

View Set

Marketing 409 - Exam 3 Study Questions

View Set

Chapter 45: Male and Female Hormones PrepU

View Set

Las preguntas y respuestas Capitulo 2

View Set

Chapter 3: Managing Stress & Coping with Life's Challenges

View Set

Pathophysiology / Med-Surg NCLEX

View Set

Chapter 5, 14,15,16 (Mid-Term), Chapter 12 Macro Review Questions, Economics Homework, Macro Test 2, ch 17, Chapter 17 Macroeconomics - Long / Short Run Phillips Curve, ECO 2013 Chapter 26 Homework, Macroeconomics-Ch 25-27, Chapter 12 Review - Econ 1...

View Set