supply chain exam 2

¡Supera tus tareas y exámenes ahora con Quizwiz!

You have just determined the actual number of workstations that will be used on an assembly line to be 6 using the assembly-line balancing procedure. The cycle time of the line is 5 minutes and the sum of all that tasks required on the line is 25 minutes. Which of the following is the correct value for the resulting line's efficiency?

.833 [25/(6 x 5)] = 0.833

Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the eight tasks that make up the job are 7, 4, 7, 8, 9, 4, 3 and 6 minutes, and the cycle time is 8 minutes?

6 (7 + 4 + 7 + 8 + 9 + 4 + 3 + 6)/8 = 6.

Using the assembly-line balancing procedure, which of the following is the required cycle time in minutes per unit if the daily production time is 480 minutes and the required daily output is 50 units?

9.6 480/50= 9.6

Some of the advantages of a functional project where the project is housed in a functional division include which of the following?

A team member can work on several projects

Which of these expressions is Little's Law?

A) Throughput Rate/Inventory = 1/Flow Time B) Inventory = Throughput rate × Flow time C) Inventory/Throughput Rate = Flow time D) Inventory/Flow time = Throughput rate

A firm will work with a customer to design the product, and then make it from purchased materials, parts, and components. This firm is called:

An engineer to order firm

Which of the following basic types of process structures is one which similar equipment 19) or functions are grouped together?

Assembly line

In conducting aggregate operations planning there are a number of required inputs. Which of the following are inputs considered external to the firm?

Competitor behavior and economic conditions

An advantage of a pure project where self-contained teams work full time on a project is which of the following?

Lines of communication are shortened

Which of the following is not a suggestion for managing queues presented in the textbook?

Periodically close the service channel to temporarily disperse the line

Which of the following is not a basic type of process structure?

Product-process matrix

PERT is an abbreviation for which of the following methodologies?

Program Evaluation and Review Technique

Which of the following is an example of a finite population in a queuing system?

The departmental faculty in line at the copy machine.

In a project analysis using three time estimates with more than one critical path existing, 1) how does the project manager decide which variances to use in arriving at the probability of meeting the project due date?

The project manager uses the largest variances in order to understate the probability of on-time completion

In essence, a queuing system includes several major components. Which of the following is not one of them?

The queue discipline

For an activity in a CPM analysis, the Early Start time is 8 and the Late Start time is 10. Which of the following statements is true?

The slack for this activity is 2 (10-8=2)

Which of the following is a basic type of process structure?

Work center

The main purpose of aggregate operations planning is to specify the optimal combination of which of the following?

Workforce levels and inventory on hand

In an overview of the major operations planning activities in a typical service organization, which of the following activities follows aggregate sales and operations planning?

Workforce scheduling

You have just performed a CPM analysis and have found that more than one path through the project network has zero slack values. What can you conclude?

You have multiple critical paths

Earned Value Management

a technique for measuring project progress objectively.

Matching the production rate to the order rate by hiring and laying off employees as the order rate varies is which of the following pure production planning strategies?

chase

Which of the following is a production planning strategy presented in the textbook?

level

You have just been assigned to oversee a series of projects. Functional areas will loan you personnel for each project and separate project managers will be responsible for separate projects. These project managers will report to you. Which project management structure is being used?

matrix

According to Little's Law, which of the following ratios is used to find throughput rate?

Cycle time/Process time

Which of the following is not one of the "number of interesting issues that arise in yield management?"

Designing yield management programs that cannot be imitated by a competitor

What does "EVM" stand for?

Earned Value Management

From an operational perspective yield management is most effective under which of the following circumstances?

Inventory is perishable

In the service-system design matrix, a mail contact service encounter is expected to have which of the following?

Low sales opportunity

A firm fills its customer's orders from finished goods inventory. It is a:

Make to stock firm

Machine breakdown and repair in a twelve machine factory having one repair mechanic would develop which type of queuing system line structure concerning machine breakdowns?

Multichannel, single phase

In CPM analysis it is generally expected that the relationship between activity direct costs and project indirect costs will be which of the following?

Negatively related

Which following queue discipline is discussed in the textbook?

Newest customer first

You have been placed in charge of a large project. Shortened communication lines are required to ensure quick resolution of problems as they arise. You recognize that the project is going to take a lot of time and require a lot of team pride, motivation, and commitment by all members. Which project management structure should you use in this situation?

Pure Project

Which of the following is a suggestion for managing queues that is mentioned in the textbook?

Segment the customers

Which of the following is a characteristic that can be used to guide the design of service systems?

Services cannot be inventoried

When balancing an assembly line, which of the following is not a way to reduce the longest task time below the required workstation cycle time?

Speed up the assembly line transfer mechanism

The major goal of Critical Path analysis is to:

To determine when each activity in the project should be scheduled

Which of the following is not a suggestion for managing queues presented in the textbook?

Train your servers to be friendly


Conjuntos de estudio relacionados

AP Language and Composition Mock Exam 2

View Set

Definitions/Techniques - Prototypes

View Set

Entrepreneurial Small Business Chapter 5

View Set

Exam 3 Ambulation using crutches

View Set