2-4
Dampers or ____ are placed on a conductor at a given distance ahead of and behind the structure
"Dog bones"
Lightning can have an electrical charge of up to ?
100 million volts
Before another section of a steel tower is placed at least ____ of the bolts must be placed and tightened on the previous section
50%
When backfilling an excavation compaction of ____ to relative density is required for granular soil
70%
Two wires off a main feeder supply current to a transformer several spans away. The voltage of the feeder at the point of take-off is 4180 volts. The resistance of the two wires is two ohms and the transformer draws 40 amperes. What is the line loss?
80v
Maximum EMF is induced when a conductor cuts a magnetic field at ? .
90 degrees
Fault current indicators are used on overhead and underground systems. FCIs trip when
A given current level is reached
An advantage to paralleling lines is ____ can share the load
A lightly loaded line
A portable generator feeding into a utility line does not share the same ___ as the utility line
Ground
To prevent tripping from active downstream components, many FCIs are built with an
High degree of immunity
A ____ fault can be a dead short or partial short circuit, depending on the impedance or resistance between an energized conductor and the object causing the short
Impedance
A ____ sleeve leaves virtually no spaces between the conductor and sleeve or between the conductor strands
Implosive
Voltage drop will ? if the current to the load is increased.
Increase
Which item listed below is not used to help cool transformers?
Insulation
To reverse rotation of a 3-phase motor, you must ___
Interchange any 2 leads
Inductive reactance is measured in
Ohms
What type of fault is a distribution system Exposed to?
Open circuit, over current, over voltage, (all the above)
Which of the following is not a kind of electrical power?
Peak power
One of the most dangerous situations a lineman can face when working on an energized circuit is
Phase to phase fault
If you are working on a downed line, fed from a single phase OCR, you should remove the OCR ___
Primary leads
An OCR control uses a(n) ____ involving the line voltage (kilovolt) and line impedance at key locations to determine the distance to a fault
Program
When joining copper and aluminum conductors always ____
Put aluminum on top
Dampers placed on a transmission line are there to counter
Resonant vibration
When checking conductor sag on an existing line ____ is the best method to use
Return wave
Always test voltage and ___ readings before making any changes to an existing customers 3 phase service
Rotation
the span that is used to calculate inital sag is called the
Ruling span
A hazard associated with applying armor rod to an energized conductor is ____
Unwinding causing cross phasing
Tower footing must be able to counter ____ and ____
Uplift and down thrust
Powder-actuated tool is used to install ___
Wedge connectors
during outages or storm restoration work ? is one of the most dangerous situations an electrical worker can be confronted with
Back feed
Manufacturers use ____ to protect the steel after the tower has been cut and drilled
Dip galvanizing
It takes as little as 50 volts to produce 50 milliamperes which can cause ___
Fibrillation of the heart
Upon what principle does a transformer operate
mutual inductance
A thumper operates by building up a ____ charge and then discharging it through the cable
Capacitive
transformer losses are referred to as ? and copper losses
Core
One method used to ground a transmission steel tower is called ?
Counterpoise
Transformers are normally loaded to ___ of their nameplate rating
125%
A 10-kilovolt ampere transformer can provide ____ for as long as 30 seconds without damage
20kva
The voltage drop per 1,000 feet of 1/0 copper wire (resistance = .122 ohms per 1,000 feet) when 40 amps of current are flowing through the wire is ?
4.88v
Back-feed can occur by electricity being transferred through a connected load and ____
By induction
The power factor is the ratio between____ and ____
Kw peak and kva peak
To protect underground distribution system a ____ class arrestor is typically used in addition to an arrestor located on the dip pole
Light duty
Two things that need to be done before using phasing equipment are to make sure the phasing equipment is working properly and
Make sure the lines are energized
Phase ___ is the order in which voltage waveforms of a polyphase AC generator reaches its respective peaks
Sequence
Voltage regulators must be accounted for and ____ prior to closing in disconnects that will tie in two circuits
Set on neutral position and locked out
Besides the use of socket wrenches ____ are the other tools normally used on steel tower construction
Spud wrenches
The most common method of sagging has been the ____ method
Target
When a helicopter is building a tower in sections ____ are placed on the tower
Temporary brackets
proper grounding and barricading is critical when using a ? to locate a fault
Thumper
The ? number on a residential meter's faceplate refers to watt-hours per turn of the disk
kH