Accounting changes and errors
How do you report a change in accounting principles only?
Cumulative-effect adjustment to retained earnings, which is treated retrospectivley
Prospectivly=
Estimate changes
Inventory valuation method change is (change in estimate, principle, error)
Principle (not like dep)
Prior period adjustments are limited to corrections of errors affecting
prior-year net income
if retrospective then report adjustment to
retained earnings
The asset retirement obligation is recorded as a debit to
the natural resources account (depletion base) and a credit to a liability.
Accretion Expense =
ARO balance x the interest rate at INITIAL measurement (at the credit-adjusted risk-free rate)
If a question is asking about changing the beginning retained earnings, what is it talking about
An Error to a prior period. Make sure to look at the options and select the one that is original in relation to Errors or a change in accounting Principles.
Cumulative effect of a change=
Change in Accounting Principle
Prior Period AJE=
Error Correction
How should a company report its decision to change from a cash-basis to an accrual-basis of accounting? (estimate, accounting principle, fix error)
Fix error (As a Prior period adjustment (net of tax), by adjusting the beginning balance of retained earnings.)
Choose the best description of accretion expense associated with an asset retirement obligation. (Interest expense, Finance Charge, Growth in Asset Retirement Obligation, Depletion Expense)
Growth in Asset Retirement Obligation
If a Depreciation Error has occured in the prior period how is it fixed
It is fixed in the retained earnings but does not affect the depreciation Expense
If an error is found in yr 1 financials and carries forward to yr 2 but it is not found till year 3 what needs to happen to fix the financials
The financial statements for years 1 and 2 should be restated; the cumulative effect of the error on years 1 and 2 should be reflected in the carrying amounts of assets and liabilities as of the beginning of year 3.
Accretion Expense is
This Increases ARO(Asset Retirement Obligation), it is the retirement and disposal of assets like a mine, nuclear power plant or other type of environmental impact causing assets. The expense is considered an operating expense NOT INTEREST EXPENSE
When an accounting principle change cannot be distinguished from an estimate change, it is accounted for as
an estimate change. Changes in accounting estimate are accounted for currently and prospectively and are reported in income from continuing operations. The relevant accounts affected by the change are adjusted for the current and future years. The change is not retroactively applied.
Change in Depreciation is classified as (estimate change, change in error, or change in accounting principles)
estimate change
change in estimate is usually
prospective, you cannot go back into prior years because the knowledge was not known
A change in depreciation method is treated as a change in estimate with the remaining book value at the beginning of the year of change being subject to the new method for the remainder of the asset's life. No cumulative effect is reported.
so if it asks what is the cumulative effect of this change, it is still 0 because it is prospective.