Blueprints III

Pataasin ang iyong marka sa homework at exams ngayon gamit ang Quizwiz!

In the manufacturing plant's high pressure water rinses area, Panelboard MSB2, Circuit 16 supplies a high pressure rinse pump rated at ? .

125 hp (E6)

On Sheet E7, there is a reference note indicating a remote emergency generator panel. This panel is located in Room ? .

13.9 (A2)

There are ? 5-horsepower motors located in the cooling tower.

2 (E23)

The motor size and voltage for AHU 3 is ? .

25 HP, 3-phase 480 V (E14)

You receive a notice that the panels for the basement electrical room (Room 1.3) are back ordered. The contractor wants to enclose the room now. Consequently, you determine the two door sizes for this room both need to ? .

3'0" × 7'0" × 1 3/4" (A8)

What are the voltage requirements of EF-5?

3-phase 480 V 60 Hz (M17)

The general lighting used in the catwalk area (excluding emergency lighting) is a ? bare lamp strip, ? mounted Lithonia No. CS240, ? fixture.

4' / pendant- / 277 V (E15)

The HVAC ductwork from AHU 4, located on Column Line 3 just below Column Line C, measures ? wide by ? high.

46" X 46" (M2)

Between which two parallel column lines do the 10 main mechanical piping lines run in Work Area A-D 1-3 of the manufacturing plant?

Between C and D at 1, 2, and 3 (M5)

The schedules on M17 give an overview of the project's HVAC equipment. On which drawing would one find the necessary pipe and wire size information to be run to each of Air Handling Units 1 through 11?

E14

The schedules on M17 give an overview of the project's HVAC equipment. On which drawing would one find the necessary panelboard circuit information to run to each of Air Handling Units 1 through 11?

E18

AHU3 is supplied by Panelboard ? , Circuit ? .

EE / 3. (E18)

Select the three best reasons why the Electrical Worker should consult the control diagram for AHU 3. I. Attempt to combine conduits II. Determine the material necessary for hookup III. Determine which control devices operate various motors IV. Identify the components V. Understand the sequence of operations VI. Verify the total connected electrical load

III, IV, V. (M21)

In the manufacturing plant's high pressure water rinses area, Panelboard MSB2, Circuit 15 will supply an existing large high pressure rinse pump control/starter/disconnect unit. What is the name of this room?

Inspection and Packing Room (A1)

The control diagram for Air Handler Unit 3 (AHU 3) is located on Sheet

M21

AHU 3 is located on the ? level.

Mezzanine (E14)

In Etch Room 4.1, what type of conduit is used for all exposed raceways?

PVC (E6)

On Mechanical Sheet M2, what does the square with one line drawn diagonally through it and labeled EF-5 symbolize?

Return/exhaust grille for Exhaust Fan 5. (M1)

AHU 3 is located just ? of Column C.

South (E13)

The symbol used on the HVAC prints to indicate a damper motor is best described as a ? with an upper case letter ? within it.

Square/M (M1)

On Sheet M8, what is located in the area shown as "Electrical Space?"

The Main Switchboards (E23)

Including both normal and emergency luminaries, what type and how many area type lights are used on the mezzanine level?

Type "E" / 32 (E13)

On the mezzanine power plan, each air handling unit has two devices symbolized by a "DD" placed in a rectangle. This symbol represents ? that are connected to the ? .

duct-mounted smoke detectors / fire alarm system (E16)

In Lab 15.1, there are three separate countertop areas. The outlets supplying these countertops consist of ? mounted approximately ? .

multi-outlet assemblies using 120-V 20-A outlets / 8" above the countertop (E7)

On Drawing E9, at Column Line D and 4, there is a reference made to a post indicator valve connection. The PIV is located ? building wall in line with Column ? .

outside the north / 4 (E1)


Kaugnay na mga set ng pag-aaral

ME 383 Exam 2 - CH 19: Bulk Deformation Process in Metal

View Set

Brave New World Questions chapters 1-3

View Set

Psychology Ch 6 Quiz answers and vocabulary

View Set

Chapter 6: Values, Ethics, and Advocacy

View Set

Earth and Environmental Science Final

View Set