66.All of the following are true about the project scope statement EXCEPT: A.It is an output of the Validate Scope process. B.It describes, in detail, the project's deliverables and the work required to create those deliverables. C.It provides a common understanding of the project scope among project stakeholders. D.It may contain explicit scope exclusions that can assist in managing stakeholder expectations.

A

67.Which of the following statements is true about the work breakdown structure (WBS)? A.The WBS is a hierarchical decomposition of the total scope of work to be carried out by the project team to accomplish the project objectives and create the required deliverables. B.The WBS is a simple list of project activities in chart form. C.The WBS is the same as the organizational breakdown structure (OBS). D.The WBS is the bill of materials (BOM) needed to accomplish the project objectives and create the required deliverables.

A

68.The following is an example of a constraint associated with the project scope that limits the team's options in scope definition: A.A predefined budget or any imposed dates or schedule milestones that are issued by the customer or performing organization. B.The threat of a strike by a subcontractor. C.Existing relationships with sellers, suppliers, or others in the supply chain. D.The method used to measure project performance.

A

70.What is the WBS typically used for? A.To organize and define the total scope of the project. B.To identify the logical person to be project sponsor. C.To define the level of reporting that the seller provides the buyer. D.As a record of when work elements are assigned to individuals.

A

72.Which of the following is true about the Validate Scope process? A.It is the process of formalizing acceptance of the completed project deliverables. B.It is not necessary if the project completes on time and within budget. C.It occurs primarily when revisions or changes are made to project scope. D.Scope validation is primarily concerned with correctness of the deliverables, whereas quality control is primarily concerned with acceptance of the deliverables and meeting the quality requirements specified for the deliverables.

A

69.An input to the Define Scope process is: A.The type of contract detail language. B.Project charter. C.Work breakdown structure (WBS). D.Decomposition.

B

71.The following is true about the WBS: A.The WBS is another term for the bar (Gantt) chart. B.Each descending level of the WBS represents an increasingly detailed definition of the project work. C.Work not in the WBS is usually defined in the scope statement of the project. D.The WBS shows only the critical path activities.

B

73.You are managing a global project that involves stakeholders in several international locations. You are likely to consult the WBS dictionary to find: A.The language translation of technical terms used in the project. B.Detailed deliverable, activity, and scheduling information about each component in the WBS. C.Information relating the legal constraints of relevant international locations to the development of the WBS. D.Strengths, weaknesses, opportunities, and threats (SWOT) of key stakeholders and their impact on the WBS.

B

62.Collect Requirements is the process of determining, documenting, and managing stakeholder needs and requirements to meet project objectives. All of the following are true about this process EXCEPT: A.The project's success is directly influenced by active stakeholder involvement in the discovery and decomposition of needs into requirements and by the care taken in determining, documenting, and managing the requirements of the product, service, or result of the project. B.Requirements become the foundation of the WBS. Cost, schedule, quality planning, and sometimes procurement are all based upon these requirements. C.The development of requirements begins with an analysis of the information contained in the project charter, the risk register, and the stakeholder engagement plan. D.Requirements need to be elicited, analyzed, and recorded in enough detail to be included in the scope baseline and to be measured once project execution begins.

C

65.An output of the Define Scope process is: A.Work breakdown structure (WBS). B.Resource breakdown structure (RBS). C.Project scope statement. D.Scope and schedule delays control plan.

C

75.All of the following are true about the Control Scope process EXCEPT: A.Control Scope is the process of monitoring the status of the project and product scope and managing changes to the scope baseline. B.Control Scope is used to manage the actual changes when they occur and is integrated with the other control processes. C.Scope changes can be avoided by developing clear and concise specifications and enforcing strict adherence to them. D.Controlling the project scope ensures that all requested changes and recommended corrective or preventive actions are processed through the Perform Integrated Change Control process.

C

77.Agile scope planning is especially useful when: A.Solution requirements are emerging all the time. B.Quality requirements are not stable. C.Business requirements are not stable. D.Scope is well understood at the beginning.

C

61.All of the following are true about the project scope management plan EXCEPT: A.It enables the creation of the WBS from the detailed project scope statement. B.It describes how the scope will be defined, developed, monitored, controlled, and validated. C.It can be formal or informal, broadly framed or highly detailed, based on the needs of the project. D.It is not related to the project management plan.

D

63.You are involved in collecting requirements for your project. You are likely to use the stakeholder register for all of the following EXCEPT: A.Identifying stakeholders who can provide information on the requirements. B.Capturing major requirements that stakeholders may have for the project. C.Capturing main expectations that stakeholders may have for the project. D.Evaluating the product breakdown structure (PBS) associated with each of the key stakeholders.

D

64.You are developing a document that links product requirements from their origin to the deliverables that satisfy them to help ensure that each requirement adds business value and to manage changes to the product scope. This is known as the: A.Configuration management system. B.Business case. C.New product development matrix. D.Requirements traceability matrix.

D

74.Which of the following is NOT an output of the Control Scope process? A.Work performance information. B.Change requests. C.Project documents updates. D.Accepted deliverables.

D

76.____________ describe capabilities that are temporary and are no longer needed after the new product/service/result is ready. A.Business requirements B.Solution requirements C.Quality requirements D.Transition requirements

D


Kaugnay na mga set ng pag-aaral

Earth and Space Science Midterm 1 and 2

View Set

MGMT 320 Chapter 11 Connect Learnsmart

View Set

Human Nutrition Ch. 5 + 6 Study Guide

View Set

Stimulus Based questions AP Euro Final

View Set

Managerial Accounting- Variances Review

View Set

LAWS1100 3: SOURCES OF LAW (Common Law)

View Set

Ch. 8 Principles of Managerial Accounting

View Set