Chapter 4 Project management

Pataasin ang iyong marka sa homework at exams ngayon gamit ang Quizwiz!

Which of the following is not true regarding bottom-up budgeting?

The method tends to be inaccurate in the detailed tasks.

A task is expected to take 20 hours of labor at $25 per hour. The required material cost is $500 and the organization charges 30% of direct labor for overhead. The total task cost is

$1,150

There is a 30 percent chance that a new product development project will result in sales of $500,000 and a 70 percent chance that the project will result in sales of $100,000. What is the expected value of this project?

$220,000

The first unit required 6 hours. If the industry uses a 90 percent learning rate, how long should the fourth unit take

4.86 hours

The first unit requires 10 hours to complete. If the industry uses an 80 percent learning rate, how long should the third unit take?

7.02 hours

Reason for cost uncertainty in projects include

All of the following

Activity budgets show expenses by task and expected time period of the expenditure.

False

As a project unfolds, the cost uncertainty increases as the project moves towards completion.

False

Because project budgeting is for a special case and the organization's budgeting process is for routine work, the project manager need not be familiar with the organization's accounting system.

False

Bottom-up budgets are usually more accurate in the detailed tasks

False

By very careful planning, a project manager can do away with cost uncertainty

False

Contingency planning is generally begun at that point in time when an organization finds itself in serious financial trouble

False

For projects with S-shaped life cycles, top-down budgeting is most likely unacceptable.

False

Learning curve theory states that performance of labor per unit will improve by a percentage each time production increases by the same percentage.

False

Mechanical tasks typically have higher learning rates than more mental tasks.

False

Organizational tradition has little or no impact on the firm's project budgeting.

False

Overhead and indirect charges should not be assigned to a project

False

Qualitative risk analysis is not as important to a project's planning because there are not many qualitative concerns in project management.

False

Scenario analysis is not a popular technique for identifying risks

False

The PMI does not devote much coverage to risk management in the PMBOK

False

The project manager recognizes an expense when an invoice is actually paid.

False

Which of the following is not true regarding top-down budgeting?

The overall budget cost is generally not very accurate.

A budget is a plan for allocating resources

True

A budget is a plan for allocating resources to project activities

True

A disaster is an event that may have an extraordinarily high cost if it occurs, but has a very low probability of occurring

True

A key advantage of top-down budgeting is that the overall budget costs can be estimated quite accurately

True

Budget cuts are usually disastrous to an exponential life-cycle project

True

Budgeting a project is often more difficult than budgeting routine activities.

True

A problem with bottom-up budgeting is

individual team members overstate their budget needs

A requirement of top-down budgeting is:

none of the above

The name given to the budget process that aggregates income and expenditures across projects is:

program-oriented budget

The best approach to handling change in projects is to accept the negative change and take a loss on the project

False

The project's budget is merely the sum of its resource costs.

False

The result of game theory analysis is a Risk Priority Number

False

There is no way other than guessing to estimate the impact of learning on a project's task

False

Top-down budgeting typically results in better acceptance of the budget

False

Traditional organizational budgets are task-oriented, rather than activity-oriented.

False

With top-down budgeting, overlooking a small but important task can often cause a serious budgetary problem.

False

Calculating the Tracking Signal can not only reveal if estimates are biased, it can also tell how severe the bias is

True

Expected value is a tool for risk analysis.

True

Individual elements of project budgets are generally more accurate in bottom-up budgeting

True

Learning curve theory states that performance of labor per unit will improve by a fixed percentage each time production doubles

True

Learning curves can be used to help improve cost estimates

True

Most organizations use top-down budgeting

True

Organizations can use both top-down and bottom-up budgeting

True

Project budget is nothing more than the project plan, based on the WBS, expressed in monetary terms

True

Random errors will tend to cancel out.

True

The project budget acts as a project control

True

Tracking signals can be used to identify bias in your estimates

True

After major risk are identified which of the following data should NOT be obtained for analysis

the person responsible for each outcome

Which of the following statements is not true about a firm and its project accounting?

the project manager must rely on the accounting department to make special allowances for his/her project

Why is it necessary to consider the learning curve of resources on a project?

to estimate labor costs properly

The budgeting approach based on the collective judgments of top and middle managers is called:

top-down budgeting


Kaugnay na mga set ng pag-aaral

Anatomy and Physiology I - Chapter 10 Learnsmart

View Set