After discovering WBS items and structure using the ____ technique, you could then translate the information into chart or tabular form

mind mapping

A(n) ____ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project

work breakdown structure

In the WBS, the name of the entire project is the top box, called Level ____.

1

In the WBS, the main groupings for the work are listed in Level ____.

2

The main outputs of ____ are accepted deliverables and change requests

verifying scope

____ involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them

Collecting requirements

____ involves controlling changes to project scope throughout the life of the project, which is a challenge on many information technology projects

Controlling scope

____ involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved.

Defining scope

____ uses highly organized and intensive workshops to bring together project stakeholders—the sponsor, users, business analysts, programmers, and so on—to jointly define and design information systems.

JAD

____ involves formal acceptance of the completed project scope by the stakeholders

Scope verification

____ is a process for identifying and modeling business events, who initiated them, and how the system should respond to them

Use case modeling

____ involves formalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables during this process

Verifying scope

In the ____, you use a similar project's WBS as a starting point

analogy approach

Project managers often use the ____ approach for projects that represent entirely new systems or approaches to doing a job, or to help create buy-in and synergy with a project team.

bottom-up

The term ____ describes a product produced as part of a project

deliverable

The ____ tasks vary the most from project to project

executing

There are ____ main processes involved in project scope management.

five

An up-to-date ____ is an important document for developing and confirming a common understanding of the project scope

project scope statement

Of the following constraints, it is most difficult to describe, agree upon, and meet the ____ goal of many projects

scope

The goal of ____ is to influence the factors that cause scope changes, assure changes are processed according to procedures developed as part of integrated change control, and manage changes when they occur.

scope control

Good ____ is very important to project success because it helps improve the accuracy of time, cost, and resource estimates, it defines a baseline for performance measurement and project control, and it aids in communicating clear work responsibilities

scope definition

The ____ should list and describe all of the deliverables required for the project

scope statement

Many people confuse tasks on a WBS with ____.

specifications

The ____ approach involves refining the work into greater and greater levels of detail

top-down

The ____ approach is best suited to project managers who have vast technical insight and a big-picture perspective

top-down


Kaugnay na mga set ng pag-aaral

Ch. 15 Clinical Psychology Multiple Choice

View Set

Evolve: Endo, Endocrine NCLEX, Endocrine Disorder chapter 50 NCLEX Questions, Endocrine NCLEX Practice Questions, Chapter 63 Care of Patients with Problems of the Thyroid Parathyroid Glands, Endocrine NCLEX Questions, NCLEX practice: endocrine, Chapt...

View Set

(NUR 100) Prep U CH 40 fluid, electrolyte and acid-base balance

View Set

Pedestrian and emergency vehicles Drivers ed