class
Which of the following statement is(are) true in ROP analysis?
All statements are true
In Theory of Constraints, which of the following is represented by "drum"?
Bottleneck resource
The Theory of Constraints (TOC) approach is also referred to as
Drum - Buffer - Rope
The prime objective of PAC is:
Executing MPC plans
As the service level increases, the probability of not running out of stock during a cycle decreases.
False
Dispatching involves the use of logic that guides the prioritizing of jobs at a workstation. These rules are referred to as lot-sizing rules.
False
In MRP, the only source of uncertainty is supply.
False
In a TOC system, inventory buffers before bottleneck resources are eliminated
False
In a single machine job shop, the makespan depends on the rule used for scheduling.
False
Johnson's rule when applied in a two-machine case will provide minimum average lateness.
False
PAC stands for Process Activity Control
False
The EOQ is based on the assumption of lumpy demand,
False
The use of the lot-for-lot procedure tends to increase the lumpiness of the gross requirements of items further down in the BOM.
False
Which of the following three strategies can be useful in reducing MRP system nervousness? I- Using Time fences II- Using Firm Planned Orders III- Careful use of Lot-Sizing procedures
I, II, III
Which of the following statement(s) is (are) TRUE?
In a one machine system, the EDD rule for sequencing the order of jobs will result in minimizing average lateness
Which of the below lot-sizing procedures provide an optimal solution in MRP lot-sizing?
KBB
Which one of the following lot-sizing rules guarantees an optimal solution in a general MRP environment?
KBB
The total time to process an entire set of jobs at a work center is referred to as
Make-span
Which one of the following is not an assumption of the basic EOQ model?
Quantity discounts can be taken advantage of for large lot sizes.
Practical application of the Theory of Constraints involves the implementation of all of the following steps except
Reduce the capacity at the bottleneck(s).
A negative SPO (Slack per remaining operations) of a job implies that the job is already late
True
Demand for raw materials and component items is derived demand, calculated exactly once a firm has the MPS. Therefore, items contained in manufacturing inventories is called dependent demand inventory.
True
Everything else remaining the same, if EOQ increases, Time Between Orders (TBO) will increase.
True
MRP lot-sizing procedures are designed specifically for the discrete demand case.
True
Order point methods are used to determine appropriate order quantities and timing for individual independent-demand product items that are characterized by random customer demand.
True
Sequencing rules simply prioritize jobs at work centers without reference to the capacity.
True
The Theory of Constraints scheduling is also referred to as the drum-buffer-rope.
True
The Theory of Constraints scheduling loads work centers to full capacity by using finite scheduling.
True
The process with the least capacity is called a bottleneck
True
To provide satisfactory levels of customer service while keeping inventory costs within reasonable bounds, two fundamental decisions must be made about inventory: when to order and how much to order.
True
When ordering costs are relatively small compared to inventory carrying costs, LFL will yield favorable results
True
An inventory system answers two important questions: when to order and how much to order. Which of the following statements correctly explains how a Q,R system (continuous review system) answers these questions?
Under a Q,R rule, a fixed quantity Q is ordered when the inventory position reaches the order point R.
When several jobs arrive at a work center, there is a need for
a system of scheduling and prioritizing
The need for safety stocks can be reduced by an operations strategy which
all of the options are incorrect
Which of the following statements is correct about complete enumeration?
all possible alternatives are evaluated and compared to pick the best solution
Safety stock and safety lead-time are mechanisms to cope with
all the options are valid
Using the Theory of Constraints scheduling logic in simulation mode can help
negotiate achievable delivery dates and meet customer service goals
In Theory of Constraints, which of the following is represented by "rope"?
pull scheduling at the non-bottleneck work centers
Examining realistic, multiple-machine, dynamic scheduling situations is possible by using
simulation
The Stock-out probability is:
the probability that inventory will not be sufficient to meet demand during the cycle