Exam 1 - MAN6581
win ratio
# won / # submitted
expected time (t) (PERT)
(a+4m+b)/6
project planning process
1. Establish project objective 2. Define scope 3. Create WBS 4. Assign responsibility 5. Define specific activities and sequences 6. Estimate activity & duration of resources 7. Develop project schedule 8. Estimate activity costs & determine budget
start and finish
The schedule for a project specifies when each task should _______.
True
True or false? Network diagrams do not cycle because projects do not cycle. They go from beginning to end.
baseline plan
What needs to be done - scope & deliverable; How it'll get done - activities & sequence; Who will do it - resources & responsibilities; durations, schedule, budget, risk
Before (the RFP is prepared)
When should you begin developing a relationship with potential sponsors?
variance of time (v) (PERT)
[(b-a)/6]^2
performing
accomplish project objectives; increase pace as resources are added; monitor & control progress & changes with sponsor approval; take corrective action as needed; achieve customer satisfactory with acceptance of deliverable
project
an endeavor to accomplish a specific & clear objective through a unique set of interrelated tasks and the effective utilization of resources; -one-time, has a sponsor/customer, and has some degree of uncertainty
responsibility assignment matrix
assigns responsibility to individuals; p = primary (can only be one per work item) s = support (can be multiple per work item)
(contract) terms & conditions
client right to approve/refuse subcontractors; misrepresentation of cost (overruns/schedule delays); customer-furnished equipment; patents; disclosure of proprietary information; international considerations; termination; terms of payment
closing
collect & make final payments; recognize & evaluate staff (bonuses); post-project evaluation & lessons learned - record & document; archive project documents
activities (network diagramming)
consume time & are described by a verb in network diagrams
bid/no-bid (a.k.a. go/no-go)
decision-making method where the potential contractor decides if it wants to create a proposal or take on a project. Factors include: competition, risk, company mission, capabilities, reputation, customer funds, & resources
project scope
defines in detail what needs to be done & establishes a common scope understanding with stakeholders; includes, customer requirements, deliverables, WBS, statement of work, & acceptance criteria
cost-reimbursement (types of contracts)
low risk contract for contractor, higher-risk contract for sponsor; price for actual costs
fixed price (types of contracts)
low-risk contract for customer, higher-risk contract for contractor; used for well-defined, low-risk projects
change control system
mentioned in the project scope, this is put in place to avoid scope creep
most likely (m) (PERT)
most likely time an activity can be completed in a PERT chart
contract(s)
must be signed before starting work, established communication, agreement of deliverables for a certain price
laddering
network diagram method that allows for the shortest possible time & best use of people
PERT (program evaluation & review techniques)
network diagram that shows activities as boxes and arrows to show relationships and to sequence work items
CPM (critical path method)
network diagram that shows activities as boxes with early start & finish times and late start & finish times, finds the path with no slack, and shows length of each activity
soliciting proposals
notify potential contractors, maintain competitiveness (equal info to all bidders), communication methods (formal? verbal?)
project identification
occurs during the initiation phase; recognize the need/problem/opportunity & determine if it's worth pursuing
elements of project charter
project manager, sponsor designee, approval signature, title, purpose, description/objective; major deliverables/risks; constraints
(project) constraints
resources, risk, customer satisfaction, scope, quality, schedule, budget
planning
show how project scope will be accomplished, plan the work & work the plan, develop the baseline plan, have actual resources help with this phase
project variance ((SDp)^2) (PERT)
sum of all variances of the critical path activities
(project) objective
tangible end-product, often stated in the RFP or charter, that establishes what is to be accomplished; clear definition of what is to be accomplished including the end-product (a.k.a. deliverable), schedule, & budget, agreed upon by the customer
(3) sections of a proposal
technical, management, cost
best and final offer
BAFO
(4 phases of) project life cycle
Initiating, Planning, Performing, Closing
network diagram (types)
PERT, CPM, PDM (presence diagramming method)
IS PDLC (IS project development life cycle)
Plan, Execute, Control: Define, analyze, design, develop, test, implement
technical (section of a proposal)
understand need, propose approach/solution, benefits to customer
total money value
value won / value submitted
success measures
win ratio & total money value
execution
1. Perform the work 2. Monitor & control progress 3. Control changes
WBS (work breakdown structure)
deliverable-oriented hierarchical decomposition that organizes work & deliverables; graphic chart or indentured list; creates logical work groupings and subdivides them into manageable components
management (section of a proposal)
description of work tasks, deliverables, project schedule & organization, related experiences, equipment & facilities
project charter
document that formally authorizes a project; provides sponsor approval; commits funds; summarize key conditions & parameters; establishes framework to develop base plan
optimistic time (a) (PERT)
earliest time an activity can be completed in a PERT chart
types of contracts
fixed price or cost-reimbursement
RFP (request for proposal)
formal or informal document describing project requirements in detail for contractors to create bid proposals; includes need, problem, or opportunity description
project selection
identify needs, costs, benefits & determine which of those should move forward as a project to be implemented; develop a graded criteria, list assumptions, gather data, evaluate each opportunity, combine gut feeling with evidence
initiating
identifying the need/problem, determine & select the project, develop a project charter, decide if a RFP is needed
business development
in project management, idea that developing a relationship with potential customers/clients is an internal cost to the contractor (project team) and not the potential sponsor. This is in hopes that the developed relationship leads to unsolicited & uncompetitive contracts.
cost (section of a proposal)
labor (breakdown of man hours needed), materials (equipment, facilities, subcontractors), travel, documentation, overhead, escalation, contingency, fee/profit
pessimistic time (b) (PERT)
latest time an activity can be completed in a PERT chart
critical path
longest path through the network, showing the shortest time in which the project can be completed; any delay here will delay the project; activities on this path have no slack