IT 364 Quiz 3
In which process group should you spend the most time and money? ______________ process
Executing
Key outcomes of the executing process group are formal acceptance of the work and creation of closing documents. True False
False
The kick-off meeting is always held before the business case and project charter are completed. True False
False
Initiating processes take place during each phase of a project. True False
True
The WBS provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance. True False
True
The planning process group activities require all 10 knowledge area of project managers. True False
True
The five project management process groups include _______________________________. a .analyzing b. testing c. closing d. planning e .initiating f. monitoring/controlling g .maintaining h. analyzing
executing closing planning initiating monitoring/controlling
The key outputs of planning process include the followings: A.project scope statement B.WBS C.project schedule D.risk register E.project charter F.stakeholder register
project scope statement WBS project schedule risk register project scope statement