IT 364 Quiz 3

Pataasin ang iyong marka sa homework at exams ngayon gamit ang Quizwiz!

In which process group should you spend the most time and money? ______________ process

Executing

Key outcomes of the executing process group are formal acceptance of the work and creation of closing documents. True False

False

The kick-off meeting is always held before the business case and project charter are completed. True False

False

Initiating processes take place during each phase of a project. True False

True

The WBS provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance. True False

True

The planning process group activities require all 10 knowledge area of project managers. True False

True

The five project management process groups include _______________________________. a .analyzing b. testing c. closing d. planning e .initiating f. monitoring/controlling g .maintaining h. analyzing

executing closing planning initiating monitoring/controlling

The key outputs of planning process include the followings: A.project scope statement B.WBS C.project schedule D.risk register E.project charter F.stakeholder register

project scope statement WBS project schedule risk register project scope statement


Kaugnay na mga set ng pag-aaral

CSE 643 - Computer Security - SQL Injection

View Set

Saunders Unit II Issues in Nursing Q 13-25

View Set

Educational Psychology Final Study Guide

View Set

Fundamentals of Nursing - Ch 23 Legal Implications in Nursing Practice

View Set

CMT Ch. 13 The endocrine system (Pituitary Gland)

View Set