The term ______ describes a product produced as part of a project.

.deliverable

_____ is a process for identifying and modeling business events, who initiated them, and how the system should respond to them.

Use case modeling

_____ involves formalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables.

Validating scope

_____ refers to the difference between planned and actual performance.

Variance

Which of the following is recommended for the creation of a good WBS?

A unit of work should appear at only one place in the WBS.

_____ involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them.

Collecting requirements

_____ involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved.

Defining scope

_____ uses highly organized and intensive workshops to bring together project stakeholders—the sponsor, users, business analysts, programmers, and so on—to jointly define and design information systems.

JAD

_____ refers to the process of developing a working replica of the system or some aspect of the system.

Prototyping

_____ involves formal acceptance of the completed project scope by the stakeholders.

Scope validation

In the _____approach for constructing a WBS, you use a similar project's WBS as a starting point.

analogy

Generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization is known as _____.

benchmarking

In the _____ approach, team members first identify as many specific tasks related to the project as possible and then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS.

bottom-up

The main technique used in creating a WBS is _____, which involves subdividing project deliverables into smaller pieces.

decomposition

The _____ technique for creating a WBS uses branches radiating from a core idea to structure thoughts and ideas instead of writing down tasks in a list or immediately trying to create a structure for tasks.

mind mapping

Creating the WBS is a subprocess associated with the _____ process in project scope management.

planning

The ______ documents how project needs will be analyzed, documented, and managed.

requirements management plan

A(n) _____ is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed.

requirements traceability matrix

The _____ should list and describe all of the deliverables required for the project.

scope statement

Scope creep refers to:

the tendency for project scope to keep getting bigger and bigger.

Scope refers to:

the work involved in creating the products and the processes used to create them.

The _____ approach for constructing a WBS involves refining the work into greater and greater levels of detail.

top-down

The _____ approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items.

top-down

A(n) _____ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project.

work breakdown structure

A(n) ____ is a task at the lowest level of the WBS.

work package


Kaugnay na mga set ng pag-aaral

Integrated Business Policy & Strategy: Chapter 1, 2, 3, & 4

View Set

ATI - Fluid and Electrolytes Practice Questions

View Set

Chapter 47--Intestinal and Rectal Disorders

View Set

Medical Billing, Coding, and Insurance Chapter 2

View Set

Abeka 9th grade Science: Matter and Energy Test 4 (ch. 6-7)

View Set