Project 2016 Tutorial Video - Updating Project Performance Using MS Project

Pataasin ang iyong marka sa homework at exams ngayon gamit ang Quizwiz!

What is the first thing to do when recording performance in MS Project? a. Find out when the project is scheduled to start b. Find out when the project is scheduled to end c. Update the Status Date d. Update the Project status

c. Update the Status Date

How does the Gantt Chart visually show how much work is completed up to the Status Date? a. A solid dark line appears in the task report b. A solid dark line appears in the duration graph c. A dashed light line appears in the task report d. A dashed light line appears in the duration graph

d. A dashed light line appears in the duration graph

Which button click records that performance is going according to schedule? a. The "On Schedule" button b. The "Inactivate" button c. The "Respect Links" button d. The "Mark On Track" button

d. The "Mark On Track" button

What is a visual cue on the Gantt Chart that a task has been completed? a. A checkmark in the Indicators column b. A red "stick man" in the indicators column c. A calendar icon in the indicators column d. A yellow exclamation point in the indicators column

a. A checkmark in the Indicators column

What is one way to report progress on the Gantt Chart? a. Create a new column for recording performance update text b. Draw a table that shows auto updates performance c. Choose the "Progress Report" option in the Format Tab d. Update the individual Resource Sheet function

a. Create a new column for recording performance update text