Project management
Which of the following represents an activity on an activity-on-node (AON) project network
A node
When deciding which staff to team-up to work on work packages, factors to consider are:
Both work habits and practical experience.
In which stage of the project life cycle is the product of the project delivered to the customer and resources are released from the project?
Closing
Any project life cycle is made up of stages. The project's schedule and budget will be determined in the ___________ stage of the project life cycle
Defining
The establishment of project goals, specifications, and responsibilities usually occurs in the ________ stage of project life cycle.
Defining
________ slack is the amount of time an activity can be delayed without delaying any immediately following (successor) activity can never be negative.
Free
Accounting would be an example of which of the following costs typically found in a project?
General and administrative overhead
The critical path in a project network is the
Longest path through the network
Which of the following is a good example of a Process Breakdown Structure?
New software program
Which of the following is least likely to be included in a work package?
Overhead expenses
Which of the following would be the best method for projects where the final product is not known and the uncertainty is very large?
Phase estimating
In which stage of the project life cycle is the project's schedule and budget determined?
Planning
A project manager is looking over the actual results of projects and comparing them to what was estimated. She notices that the projects that took six months or longer to complete were noticeably more off the estimates. Which of the following factors is she recognizing?
Planning horizon
________ activities must be completed immediately before a particular activity.
Predecessor
The WBS is best suited for projects that have a tangible outcome. Which of the following is used when the final outcome of the project is less tangible or is a product of a series of steps or phases?
Process breakdown structure
Which of the choices listed below is NOT considered a project?
Production of automobile tires
If a project is small and does not require an elaborate system to assign tasks, which of the following is a good choice?
Responsibility matrix
Which dimension of project management centers on creating a temporary social system within a larger organizational environment that combines the talents of a divergent set of professionals working to complete the project?
Sociocultural
While balancing assignments, a project manager must also balance
Talent development
What's consensus method?
Uses pooled experience of senior and/or middle managers to estimate the total project duration and cost
A "Dissemination Mode" is
What defines how project communication is to occur
What is a project?
a project is done only once; a new product or service exists when the project is completed. (its not a routine)
The last element of a project scope statement or checklist ensures an understanding and agreement of expectations. This is known as ____________.
acceptance criteria
In making project trade-offs, a criterion that is allowed not to meet the original target, for example, allowing the schedule to slip, is classified as ___________.
accepted
A key aspect to communication plans are that they allow the project manager and the project team to
actively control the flow of information.
All leveling techniques delay noncritical activities by using ________ to reduce peak demand
additional slack
When the project scope and/or technology are not fully known or stable, the best choice of method for such projects is
agile-driven project management
When work package estimates are made by individuals most knowledgeable about the work being performed and these estimates are then "rolled up" to find estimated costs for major deliverables and the project itself, ____________ estimating is being used
bottom-up
Training the customer, releasing staff and resources occurs in the ________ stage of project life cycle.
closing
The type of information that will need to be collected during a project and who will receive this information can be found in the project __________ plan
communication
A robust ______________ can go a long way to reducing project problems over the life of the project and will establish how, when and to whom information must be supplied.
communications plan
The top-down method of estimating when the pooled experience of senior and/or middle managers are used to estimate the total project duration and cost is the _________ method
consensus
In regard to project priorities, if a project parameter such as the completion date or the cost of a project is fixed and must be met, it is considered ____________.
constrained
The delaying of any activity on the __________ will delay the completion of the project by the same amount
critical path
customer tastes and feature preferences vary from customer to customer. Increased competition has placed a premium on customer satisfaction and the development of __________ products and services.
customized
Taking advantage of opportunities to reduce costs or accelerate the schedule are examples of project criteria classified as ___________
enhanced
If three copiers are needed to produce a final report on time and only two are available, the project is facing a(n) ________ type of resource constraint.
equipment
In which stage of the project life cycle are you more likely to find status reports, changes, and the creation of forecasts?
executing
In which stage of the project life cycle is a major portion of the actual project work performed?
executing
When a project is classified as resource-constrained, a resource constraint exists, and positive slack is insufficient, then the project duration is typically __________.
extended
A(n) _____________ calculates project duration
forward pass
In scheduling resource-constrained projects, _________ are typically used rather than optimum mathematical solutions
heuristics
What are the stages of project life cyle?
identifying, defining ,planning, executing and closing
The best way to __________________ is to collect and archive data on past projects
improve estimates
Agile project management involves ____ whereas traditional project management involves _______.
iterative and incremental delivery, upfront planning with high predictability
An increase in the complexity of projects, because projects typically include the latest advances, can be the result of a growth in new __________.
knowledge
Learning curves are more likely to be applied in situations where most of the costs are
labor
The assumption that all immediately preceding activities must be 100% complete is too restrictive in some situations. When an activity is broken down into smaller segments in order to start the succeeding activity sooner, this is called
laddering
When an activity with a long duration is broken into smaller segments so that the following activities can begin sooner it is called __________
laddering
The top-down method of estimating project time and costs that is useful for projects requiring the same task, group of tasks, or product repeated several times, especially if it is labor intensive, is the ______________.
learning curves
In a resource-constrained project, the first, or primary, priority in assigning resources is usually given to activities with the
least slack.
The agreement that training will be the responsibility of the customer and not the team is an example of a project ________.
limits and exclusions
The project scope statement indicates that the client is responsible for training the people who will be using the equipment and that the project team will train the client's trainers. This is an example o
limits and exclusions.
In a project network, recycling through a set of activities or __________ is not permitted
looping
The shortage of memory chips to produce a printed circuit motherboard is an example of a(n) ________ type of resource constraint
material
An activity that has more than one dependency arrow flowing into it is termed a(n
merge activity
In reviewing the project plan, a project professional sees that the first prototype must be completed by October 12. This would be best classified as a
milestone.
Significant events in a project that occur at a specific point in time, are natural control points, and are easily recognized by project participants are known as ___________.
milestones
A project scheduler is trying to reallocate resources in a time-constrained project to create smoother resource utilization. The scheduler should first identify activities with the
most slack
In reality resource allocation generally occurs in a(n) ___________ environment where the demands of one project have to be reconciled with the needs of other projects
multiproject
When translated into a project network, a work package will become
one or more activities
The integration of the lowest level of the WBS with the organizational units responsible for performing the work is known as
organization breakdown structure.
The estimating factor that considers the prevailing belief in some firms that detailed estimating takes too much time and is not worth the effort is an example of the ___________ factor.
organizational culture
The approach to estimating project time and cost that begins with an overall estimate for the project and then refines estimates for various stages of the project as it is implemented is known as ____________.
phase estimating method
The estimating approach that is best to use on projects where there is an unusual amount of uncertainty surrounding the project and when it is impractical to estimate times and costs for the entire project is known as ___________.
phase estimating method
A Process Breakdown Structure can provide a reasonable alternative to a Work Breakdown structure for an extensive development project if
phase exit criteria are firmly established.
Traditional project management focuses on thorough planning up front. Such planning requires ____.
predictability
One of the primary jobs of a project manager is to manage the trade-offs among time, cost, and performance. To do so, the project manager must define and understand the ___________ of the project.
priorities
A document that is issued by upper management and provides the project manager with written authority to use organizational resources for project activities is called a(n) __________.
project charter
Arrows on an activity-on-node (AON) project network represent
project flow and dependency
A technique that clearly establishes priorities with customers and top management so as to create shared expectations and avoid misunderstandings is developing a(n) ___________.
project priority matrix
Once the __________ has been established, it is the basis for making trade-off decisions later in the project
project priority matrix
Agile PM is appropriate when _______.
project scope is unknown or unstable
The definition of the end result or mission of your project, or what you expect to deliver to your customer when the project is complete is the project ___________
scope
Scope creep can be reduced by carefully writing a(n) __________.
scope statement
The likelihood the original critical path(s) will change once the project is initiated is referred to as
sensitivity.
In a resource-constrained project the second priority in assigning resources is usually given to activities with the
smallest duration
When the work in an activity is interrupted to work on another activity and is then resumed at a later point in time, it is called _________.
splitting
When using the _______ scheduling technique, startup and shutdown costs are major considerations.
splitting
When developing a new software package, logically, the software must be designed before the code is written, and the code must be written before it is tested. These activities are dependent on each other by _________ constraints
technical
A(n) ________ constraint addresses the sequence in which project activities must occur even after considering resource constraints.
technical or logic
Projects with high predictability are said to have
the best circumstances for use of traditional project management
Iterative and incremental delivery means ______.
the components or features of the project product or service are delivered one at a time throughout the duration of the project
The forward pass in project network calculations determines all of the following EXCEPT
the critical path
The preferred method for situations involving strategic decision making, projects with a high degree of uncertainty, and projects with an unstable scope is the ___________ approach to estimating project time and costs
top-down
Project managers typically use ________, also called analogous estimating or the ______ method when there is a past history of similar projects and rough-cut estimates are needed for strategic purposes two-to-five years out because, as estimating methods go, it is faster and less expensive.
top-down, apportion
A selective outline of the project that ensures the identification of all tasks and an understanding of what is to be done is called a(n) ____________
work breakdown structure
Information to develop a project network is collected from the
work breakdown structure
The information necessary to conduct a bottom-up estimate of project time and cost starts with the ___________.
work package