Quiz 5

Pataasin ang iyong marka sa homework at exams ngayon gamit ang Quizwiz!

The main disadvantage of ____ is that it can end up lengthening the project schedule, because starting some tasks too soon often increases project risk and results in rework.

fast tracking

Which of the following icons appears when there is a miscalculation resulting in over allocation?

red human

A project schedule network diagram is an output of the ___________ time management planning process.

sequence activites

After defining project activities, the next step in project time management is activity ____.

sequencing

A cost baseline is a(n) ____ budget that project managers use to measure and monitor cost performance.

time-phased

___________ is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost.

crashing


Kaugnay na mga set ng pag-aaral

Practice Exam 1 - integrated business policy/strategy

View Set

A Christmas Carol - Stave Three Study Guide, First Half

View Set

Bus. Law Test 1 - Multiple Choice and True/False

View Set

Chapter 8: The Appendicular Skeleton

View Set

Chapter 6: Formulating Hypotheses

View Set

Physics I Final - Conceptual Questions

View Set