Quiz 6
Which of the following is a difference between an activity list and an activity attribute? a. An activity attribute is a tabulation of activities to be included on a project schedule whereas an activity list is not. b. An activity attribute provides more schedule-related information about each activity than an activity list. c. An activity list provides a more concrete list of milestones for a project than an activity attribute. d. As opposed to an activity attribute, an activity list provides resource requirements and constraints related to activities.
An activity attribute provides more schedule-related information about each activity than an activity list.
In a network diagram, it is mandatory for every item on the WBS to be shown instead of only those activities with dependencies.
False
After working with key stakeholders to define activities and calculate their resources, the next process in project time management is to: a. determine their dependencies. b. estimate the duration of activities. c. control the schedule. d. develop the schedule.
estimate the duration of activities.