Scrum2
True or False: It is mandatory that the product Increment be released to production at the end of each Sprint. True False
False
True or False: Scrum has a role called "project manager." True False
False
When should a Developer on a Scrum Team be replaced? (Choose the best answer) A. As needed, while taking into account a short-term reduction in productivity. B. Every Sprint to promote shared learning. C.As needed, with no special allowance for changes in productivity. D. Never, it reduces productivity.
A. As needed, while taking into account a short-term reduction in productivity.
Who creates the Definition of Done? (Choose the best answer) A. If it is not an organizational standard, the Scrum Team must create a Definition of Done appropriate for the product. B. The Scrum Master since they are responsible for the productivity of the Developers. C. The Scrum Team, in a collaborative effort where the result is the common denominator of all members' definitions. D. The Product Owner since they are responsible for the product's success.
A. If it is not an organizational standard, the Scrum Team must create a Definition of Done appropriate for the product.
Who is on the Scrum Team? (Choose the best three answers) A. The Product Owner. B. Project Manager. C. Developers. D. The Scrum Master.
A. The Product Owner C. Developers. D. The Scrum Master.
During a Sprint, a Developer determines that the Scrum Team will not be able to complete the items in their forecast. Who should be present to review and adjust the Product Backlog items selected? (Choose the best answer) A. The Product Owner and the Developers. B. The Scrum Master, the project manager, and the Developers C. The Product Owner and all stakeholders. D. The Developers.
A. The Product Owner and the Developers.
When does the next Sprint begin? (Choose the best answer) A. Next Monday. B. Immediately after the conclusion of the previous Sprint. C. Immediately following the next Sprint Planning. D. When the Product Owner is ready.
B. Immediately after the conclusion of the previous Sprint.
Which Scrum events are timeboxed? (choose the best three answers) A. Release Testing. B. Sprint Retrospective. D. Sprint Planning. E. Sprint Testing. F. Sprint Review G. Release Retrospective.
B. Sprint Retrospective. D. Sprint Planning. E. Sprint Review.
Who has the final say on the order of the Product Backlog? (Choose the best answer) A. The Stakeholders. B. The Product Owner. C. The Developers. D. The Scrum Master. E. The CEO.
B. The Product Owner.
When does a Sprint conclude? (Choose the best answer) A. When the Product Owner decides enough has been delivered to meet the Sprint Goal. B. When the Sprint Retrospective is complete. C. When all the tasks are completed by the Developers. D. When all Product Backlog items meet their Definition of Done.
B. When the Sprint Retrospective is complete.
The timebox for a Daily Scrum is?(choose the best answer) A.The same time of day every day. A. The same time of day every day. B.15 minutes. B. 15 minutes. C.Two minutes per person. C. Two minutes per person. D.4 hours. D. 4 hours. E.15 minutes for a 4-week sprint. For shorter Sprints it is usually shorter. E. 15 minutes for a 4-week sprint. For shorter Sprints it is usually shorter.
B.15 minutes.
The three pillars of empiricism are:(choose the best answer) A. Planning, Demonstration, Retrospective. B. Planning, Inspection, Adaptation. C. Inspection, Transparency, Adaptation. D. Respect For People, Kaizen, Eliminating Waste. E. Transparency, Eliminating Waste, Kaizen. .
C. Inspection, Transparency, Adaptation.
The length of a Sprint should be:(choose the best answer) A. Short enough to keep the business risk acceptable to the Product Owner. B. Short enough to be able to synchronize the development work with other business events. C. One month or less. D. All of the above.
D. All of the above
How much work must the Developers complete for each Product Backlog item they select for a Sprint? (Choose the best answer) A. Analysis, design, programming, testing and documentation. B. All development work and at least some testing. C.As much as it can fit into the Sprint. D. Enough so that each Product Backlog item they select meets the Definition of Done.
D. Enough so that each Product Backlog item they select meets the Definition of Done.
The Product Backlog is ordered by:(choose the best answer) A. Least valuable items at the top to most valuable at the bottom. B. Items are randomly arranged. C. Size, where small items are at the top and large items are at the bottom. D. Risk, where safer items are at the top, and riskier items are at the bottom. E. Whatever is deemed most appropriate by the Product Owner.
E. Whatever is deemed most appropriate by the Product Owner.