work

Pataasin ang iyong marka sa homework at exams ngayon gamit ang Quizwiz!

A common source of waste during the design process is: Errors + Omissions Under-Utilized Talent Over-Designing All of the above

All of the above

Question 5 A common source of waste during the design process is: Errors + Omissions Under-Utilized Talent Over-Designing All of the above

All of the above

Question 3 The high-velocity team will not do the following: Appoint Expert + Assign Blame Capture Knowledge + Reveal Problems Swarm + Solve Problems Share Knowledge

Appoint Expert + Assign Blame

The high-velocity team will not do the following: Appoint Expert + Assign Blame Capture Knowledge + Reveal Problems Swarm + Solve Problems Share Knowledge

Appoint Expert + Assign Blame

Which of the following is the method of pricing in a unit price contract? A stated amount Based on the cost of the contractor's time and materials cost Based on the number of quantifiable work items installed Not to exceed a specific amount

Based on the number of quantifiable work items installed

A bond that is worth 12% of the penal sum is probably a: Completion bond Bid bond Performance bond 12% is too high for any bond

Bid bond

What is the standard procedure to choose a contractor Bidding Choice from previous experience

Bidding

Target Value Design achieves lower construction cost by: Using median values from RSMeans Construction Data Contract requiring architect 'design-to-budget' Collaboratively setting the target cost below market value Reducing the project scope

Collaboratively setting the target cost below market value

DBOM stands for: Design Bond Original Materials Design Build Operate Maintain Dry Binding Offshore Material

Design Build Operate Maintain

Question 2 Which project delivery method is least likely to drive designer-constructor collaboration? Integrated Project Delivery Design-Bid-Build Design Assist

Design-Bid-Build

Which of the following is the right phase order of project development cycle Design-Bid-Build Bid-Design-Build Design-Build-Bid

Design-Bid-Build

Which project delivery method is least likely to drive designer-constructor collaboration? Integrated Project Delivery Design-Bid-Build Design Assist

Design-Bid-Build

Phases of construction need to be considered in which project stage: Conceptual design Inspection Operation and maintenance Detailed design & Planning

Detailed design & Planning

Bonds in construction projects in the USA are obligatory for privately owned projects but not necessary in public works True False

False

Buildings can be an example of mass production manufacturing: True or False

False

The construction industry is Efficient when compared to other industries On par with other industries regarding productivity Has become less productive over the past 50 years

Has become less productive over the past 50 years

Which of the following is not 1 of 3 inter-connected opportunities for improved project delivery? Impeccable Coordination Projects as Collective Enterprise Projects as Production System Integrated Project Delivery

Integrated Project Delivery

Which of the following is true: Integrated project delivery includes operation and maintenance Integrated project delivery is becoming a less-appealing project delivery method Politicians and economists can be considered as key-stakeholders throughout the project life cycle

Integrated project delivery includes operation and maintenance

Why would owners look for PPP solutions Lack of funding Lack of experience in this kind of projects To completely mitigate the risk to another party To decrease the project duration

Lack of funding

The construction industry traditionally has had Lower profit margins significantly below many other industries Has delivered profits on par with the average of the Standard & Poors 500 index companies Has consistently outperformed the S&P 500 index companies

Lower profit margins significantly below many other industries

Pull-Planning reduces project schedules because: Milestones are placed at hand-offs, enabling next steps in the process Gantt Charts are easier to read than CPM method Individual trades only have to focus on delivering their work It works backwards from deadline

Milestones are placed at hand-offs, enabling next steps in the process

Question 7 Pull-Planning reduces project schedules because: Milestones are placed at hand-offs, enabling next steps in the process Gantt Charts are easier to read than CPM method Individual trades only have to focus on delivering their work It works backwards from deadline

Milestones are placed at hand-offs, enabling next steps in the process

Which form of contract is best for the owner on all kinds of projects? Target price Cost reimbursable Unit price None of the above

None of the above

Which of the following is true: Payments in construction are distributed across project life time Payments in manufacturing are distributed across manufacturing life time Payments in construction come after project is handed to client Payments in manufacturing come before product is handed to customer

Payments in construction are distributed across project life time

Question 4 The critical Flow Unit during construction is Material People Ideas WiFi

People

The critical Flow Unit during construction is Material People Ideas WiFi

People

PPC is a measure for the assessment of the efficiency of Pull planning, what does it stand for: Performance Per Cent Percent Promises Completed Pressure-Performance-Completion Practical Planning Criterion

Percent Promises Completed

The PDCA Cycle consists of: Plan Do Cycle Act Perform Do-Over Check Again Plan Do Check Adjust Plan Do Check Act

Plan Do Check Adjust

Which of the following experiences the most risk Project management Construction management Program management

Program management

Which of the following may play the role of the owners advocate in cases of conflict Project management Construction management Program management

Program management

Which of the following is the most involved with contract management: Project management Construction management Program management

Project management

During the 1970's and 1980's, architects generally withdrew from the construction process because: Blue-printing costs became excessive Rising cost and occurrence of litigation The adoption of CAD reduced field time Dept of Justice ruled Architects were not Contractors

Rising cost and occurrence of litigation

The future (next 2 decades) of the construction industry, will likely see Minimal change to the industry Some changes in means and methods Significant change due to high demand and the impact of technology

Significant change due to high demand and the impact of technology

In DBOM projects: The project manager hands over the project to the owner after construction is over The project manager is responsible for operating and maintaining the project The project manager is responsible for the design only, after the design phase the project manager has an advisory role in the project

The project manager is responsible for operating and maintaining the project

Inflation possess serious risk for contractors but surety providers are inflation-risk-safe True False

True

Risk considerations is a major factor in the choice of the delivery method: True False Not in all cases

True


Kaugnay na mga set ng pag-aaral

ACG2071 Chapter 13: Cash Flow from Operations

View Set

Shoulder Muscles (action, origin, insertion, innervation)

View Set

Azure Fundamentals - Cloud Concepts

View Set

Chapter 5 and 6 Practice Review Questions

View Set

Media Studies 111B- Reading Questions

View Set

Nature and the environment, Карп'юк, 9 клас

View Set