Ch. 5
growing grass
What activity was on the critical path for building Disney's Animal Kingdom theme park
nine
What is the PERT weighted average based on an optimistic estimate of six days, a most likely estimate of eight days, and a pessimistic time of sixteen days?
guiding project execution
What is the first step in planning a project schedule?
finish-to-start
What is the most common type of dependency between activities?
parametric modeling
Which cost estimating technique would you be using if you estimate the cost of materials based on the number of square feet?
optimistic time
Which number should be shortest when creating a three-point estimate?
time-phased
A cost baseline is a(n) ____ budget that project managers use to measure and monitor cost performance
sequence activities
A project schedule network diagram is an output of the ___________ time management planning process.
optimistic
A three-point estimate is an estimate that includes a(n) ____, most likely, and pessimistic estimate, such as three weeks, four weeks, and five weeks, respectively
critical
A(n) ____ path for a project is the series of activities that determine the earliest time by which the project can be completed.
attributes
Activity ____ provide schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity
true
Activity sequencing involves reviewing the activity list and attributes, project scope statement, and milestone list to determine the relationships or dependencies between activities
true
After you determine the reason for a dependency between activities, you must determine the type of dependency (TF)
budgeting
Cost ____ involves allocating the overall cost estimate to individual tasks over time to establish a baseline for measuring performance
buffers
Critical chain scheduling considers limited resources when creating a project schedule and includes _________ to protect the project completion date.
true
Discretionary dependencies are defined by the project team
true
Duration relates to the time estimate, not the effort estimate
false
Every item on a WBS needs to be on the network diagram (TF)
30 weeks
If you have only two paths through a project network diagram where path 1 has a length of 20 weeks and path 2 has a length of 30 weeks, what is the estimated duration of the project?
bursts
In an AOA network diagram, ____ occur when two or more activities follow a single node.
merge
In an AOA network diagram, a(n) ____ occurs when two or more nodes precede a single node
false
It is poor practice to use more than one approach for creating a cost estimate
true
Lag time is a gap in time, such as waiting. (TF)
false
Most project teams use the most pessimistic time to estimate activity durations. (TF)
milestone list
Project teams often create a ____________ to ensure that all major activities are accounted for.
float
Slack or ____ is the amount of time an activity may be delayed without delaying a succeeding activity or the project finish date
true
The WBS is a required input to the cost budgeting process
WBS 100%
The _________ rule is that all work required for a deliverable is included in its sub-deliverables when defining activities
WBS
The ___________ must be the basis for a project cost estimate if you plan to create a cost baseline and use earned value management as part of monitoring and controlling costs
critical path
The ____________ method is a network diagramming technique used to predict total project duration
false
The critical path is the shortest path through the network diagram (TF)
fast tracking
The main disadvantage of ____ is that it can end up lengthening the project schedule, because starting some tasks too soon often increases project risk and results in rework.
schedule
The project team begins to develop a ____ by first clearly defining all the activities it needs to perform
true
There can be more than one critical path on a project
true
There is usually no cost or duration associated with a milestone (TF)
madatory
____ dependencies are inherent in the nature of the work being performed on a project.
analogous
____ estimates, also called top-down estimates, use the actual cost of a previous, similar project as the basis for estimating the cost of the current project
duration
____ includes the actual amount of time spent working on an activity plus elapsed time.
crashing
____ is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost