Chapter 5 Project Management

Réussis tes devoirs et examens dès maintenant avec Quizwiz!

What is the standard deviation of a task with optimistic, most likely, and pessimistic times of 3, 4, and 7 days respectively assuming the estimates were made at the 99% plus level?

.667

What is it a milestone?

a significant event in the project

Which of the following terms is most closely associated with a task required by the project?

activity

An identifiable state resulting from the completion of one or more activities is called?

an event

Which of the following is NOT an element of the Gantt chart?

variance of the critical path

A Gantt chart can not depict a critical path, only a PERT/CPM chart can

False

A disadvantage of Gantt charts is that they are hard to draw

False

A disadvantage of using beta distribution to approximate activity times is that it is generally less flexible than the normal distribution.

False

A start-to-finish linkage is the most common way of linking to successive task

False

An event is a series of connected activities

False

Another name for total slack is free slack.

False

If task duration estimates are carefully made, the project manager needs to only examine the critical path when conducting a risk analysis.

False

It is easiest to see lead and lag time in a project task on a PERT/CPM networks

False

Milestones are not depended upon the predecessor activities in the project plan.

False

Milestones cannot be identified on a Gantt Chart.

False

Networks are usually drawn with a "Start" node to the right and a "Finish" node to the left.

False

Technical dependencies are generally easier to see on a Gantt chart than on PERT/CPM networks

False

The difference between EST and LFT is called slack

False

The difference between LST and LFT is called slack.

False

The movement from left to right through the network beginning with the start node that calculates the LS and LF for each activity is known as "FORWARD PASS"

False

The start-to-finish linkage is used in situations where is it desirable for two or more activities to finish at the same time.

False

The tasks of project planning, project budgeting, and project scheduling are largely separable from one another

False

To manage a project successfully, the project manager need only pay close attention to tasks on the critical path

False

When it was originally developed, PERT used certain (deterministic) methods to estimate activity duration

False

What is the expected time to complete a task with an optimistic, most likely, and pessimistic times of 3, 4, and 7 days respectively?

4.3

Slack is calculated as?

LFT - EFT

Technical dependencies on a project plan are easiest to see on a:

PERT/CPM chart

A Term not used in the discussion of PERT/CPM analysis is

Sensitivity path

What is project slack?

The amount of time the critical path of a project can be delayed without making the project late

"Merger" is a term used to describe the situation in which two or more paths in a network join together.

True

A big advantage of AON networks is that they are easier to draw

True

A diagram of nodes connected by directional arcs that defines the project and illustrates the technical of all activities is referred to as a network.

True

A project schedule is a project action plan converted into a timetable

True

A situation where two or more activities have the same starting and finishing nodes or where a single activity connects to two or more nodes is called a dummy task

True

AON and AOA networks can both be used to depict any project network

True

Critical path tasks always have zero slack.

True

Events in a project consume no resources or time.

True

Float refers to the amount of time a noncritical task can be delayed without causing a delay in the entire project.

True

Standard Pert/CPM networks can be used to resolve probabilistic concerns

True

Technical dependencies are often harder to see on a Gantt chart than on a PERT/CPM network.

True

The actual project duration will be known with certainty after the project is completed

True

The amount of time an activity can be delayed without affecting the start time of any successor activity is known as free slack.

True

The difference between LFT and EFT is called slack

True

The difference between the LST and EST is called slack

True

The formula for the expected time of an activity in a network assumes that the optimistic, pessimistic, and most likely time estimates have a Beta distribution.

True

The shortest time to complete a network is equal to the duration of the longest path through the network.

True

The simulation approach is generally preferred over the statistical method.

True

Which of the following is typically used as the best estimate of task duration?

expected time

PERT was originally used for what type of project?

military

The amount of time a noncritical task can be delayed without delaying the project is called?

slack

Which of the following linkages is used to start two or more activities at the same time?

start-to-start

For which purpose is simulation NOT used with regard to project scheduling?

to verify the accuracy of the optimistic, pessimistic and most likely time estimates


Ensembles d'études connexes

MODULE 10: HEALTH, AGING, & THE ELDERLY

View Set

EXAM 3 : Chapter 22 (Nursing Management: Patients With Oral and Esophageal Disorders and Patients Receiving Gastrointestinal Intubation, Enteral, and Parenteral Nutrition)

View Set

Florida Statutes, Rules, & Regulations Common to All Lines

View Set

Medical Term. Chapter 10 Practice

View Set

Alcohol and Other Drug Abuse Exam 2

View Set

Chapter 4.2: Observational Study vs Experiment

View Set

PALS - Team Response Scenario: Sara Hoffman

View Set

Sherpath lesson ch 5 and 6 questions

View Set