chapter 9,10,11 finance exam

Réussis tes devoirs et examens dès maintenant avec Quizwiz!

disadvantages of the payback period

-Ignores the time value of money -Requires an arbitrary cutoff point -Ignores cash flows beyond the cutoff date -Biased against long-term projects, such as research and development, and new projects

advantages of IRR

-Preferred by executives -Intuitively appealing -Easy to communicate the value of a project -If the IRR is high enough, may not need to estimate a required return -Considers all cash flows -Considers time value of money -Provides indication of risk

disadvantages of IRR

-can produce multiple answers -cannot rank mutually exclusive projects -reinvestment assumption flawed

Accept project if NPV _____ 0

>

What are non-conventional cash flows?

A combination of cash outflows and inflows.

Decision rule

Accept if the payback period is less than some preset limit

What is the first step in the Net Present Value (NPV) process?

Estimate the future cash flows.

According the video, one of the biggest challenges for the Net Present Value method is:

Identifying the appropriate discount rate to use.

Whenever there is a conflict between NPV and another decision rule always use the

NPV

profitability index decision rule

P1 > 1.0 then accept

Which type of analysis identifies the variable, or variables, that are most critical to the success of a particular project?

Sensitivity

When reviewing a graph of data from sensitivity analysis, the ____________ the line, the ____________ the sensitivity of the estimated Net Present Value.

Steeper, greater.

The Payback Period Rule states that a company will accept a project if:

The calculated payback is less than a pre-specified number of years.

The Internal Rate of Return (IRR) represents which of the following

The discount rate that makes the net present value equal to zero.

All of the following are useful for understanding Profitability Index, except:

The initial investment is included when calculating the present value of the future cash flows

Which one of the following will be used in the computation of the best-case analysis of a proposed project?

The lowest variable cost per unit that can reasonably be expected

All of the following are disadvantages of the Payback Period, except:

The method incorporates the time value of money.

simulation analysis

a combination of scenario and sensitivity analysis

simulation analysis

an expanded sensitivity and scenario analysis

Fixed costs:

are constant over the short-run regardless of the quantity of output produced.

the greater the volatility in NPV in relation to a specific variable, the larger the forecasting risk

associated with that variable

the payback period is a

break even type measure

sensitivity analysis

change one variable at a time

NPV= PV inflows-

cost

Sensitivity analysis determines the:

degree to which the net present value reacts to changes in a single variable

The main focus of sensitivity analysis is to:

determine the one variable that has the highest level of risk.

Advantaged of Payback period

easy to understand, biased towards liquidity

best-case scenario

high revenues, low costs

forecasting risk

how sensitive is our NPV to changes in the cash flow estimates; the more sensitive, the greater the forecasting risk

Forecasting risk is defined as the possibility that:

incorrect decisions will be made due to erroneous cash flow projections.

The base case values used in scenario analysis are the values considered to be the most:

likely to occur.

worst-case scenario

low revenues, high costs

base case

most likely event

NPV=

net gain in shareholder wealth

what happens when we change

one variable at a time

if the NPV is __________ accept the project

positive

Monte Carlo simulation can estimate thousands of

possible outcomes based on conditional probability distributions and constraints for each the variables

The acceptance of one project ___________ accepting the other.

precludes

Profitability Index Formula

present value of net cash inflows / initial investment

Based upon the following graph, which variable should Simmons Corporation be most concerned about?

price (highest)

NPV=0 means

projects inflows are exactly sufficient to repay the invested capital and provide the required rate of return

For IRR accept the project if the IRR is greater than the

required return

An analysis of the change in a project's NPV when a single variable is changed is called _____ analysis.

sensitivity

Combining scenario analysis with sensitivity analysis can yield a crude form of _____ analysis.

simulation

The cash flows of one project are ___________ by the acceptance of the other.

unaffected

Variable costs can be defined as the costs that:

vary directly with sales

scenario analysis

what happens to the NPV under different cash flow scenarios

this is a subset of scenario analysis

where we are looking at the effect of specific variables on NPV

scenario analysis

worst, base, best case

When you assign the lowest anticipated sales price and the highest anticipated costs to a project, you are analyzing the project under the condition known as:

worst-case scenario analysis.

The IRR is the discount rate that makes NPV equal to ________________.

zero


Ensembles d'études connexes

Field Service Management Fundamentals

View Set

ATI Learning System Gerontology Final Quiz

View Set

Chapter 6-7 Econ 102 Principles of Microeconomics

View Set

BIO 210 : Chapter 7 Skeletal System

View Set

American Government CLEP - ONLINE PRACTICE TEST 1-3

View Set

Cards, Cars, and Currency Lesson 2 Econ Lowdown

View Set

CIS 156: Python Programming - Strings (Chapter 7)

View Set