late start date
The ____ for an activity is the latest possible time an activity might begin without delaying the project finish date.
PDM
The ____ is a network diagramming technique in which boxes represent activities
External
____ dependencies involve relationships between project and non-project activities
feeding buffers
Critical chain scheduling protects tasks on the critical chain from being delayed by using ____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.
Bursts
____ occur when two or more activities follow a single node
red
Project management software highlights the critical path in ____ on a network diagram
finish-to-finish
In a ____ relationship, one task cannot finish before another finishes
resource breakdown structure
A ____ is a hierarchical structure that identifies the project's resources by category and type.
start-to-start
In a ____ relationship, the "from" activity cannot start until the "to" activity is started
finish-to-start
In a ____ relationship, the "from" activity must finish before the "to" activity can start
right
On a network diagram, all arrowheads should face toward the ____.
duration estimates
The activity list, activity attributes, activity resource requirements, resource calendars, project scope statement, enterprise environmental factors, and organizational process assets all include information that affect ____.
7
There are ____ main processes involved in project time management
Mandatory
____ dependencies are inherent in the nature of the work being performed on a project
Discretionary
____ dependencies are sometimes referred to as soft logic and should be used with care since they may limit later scheduling options
Developing the schedule
____ involves analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule
Controlling the schedule
____ involves controlling and managing changes to the project schedule
Fast tracking
____ involves doing activities in parallel that you would normally do in sequence
Estimating activity durations
____ involves estimating the number of work periods that are needed to complete individual activities
Sequencing activities
____ involves evaluating the reasons for dependencies and the different types of dependencies.
Sequencing activities
____ involves identifying and documenting the relationships between project activities
Defining activities
____ involves identifying the specific activities that the project team members and stakeholders must perform to produce the project deliverables
Critical chain scheduling
____ is a method of scheduling that considers limited resources when creating a project schedule and includes buffers to protect the project completion date
Critical path analysis
____ is a network diagramming technique used to predict total project duration
Crashing
____ is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost
Total slack
____ is the amount of time an activity can be delayed from its early start without delaying the planned project finish date
Free slack
____ is the amount of time an activity can be delayed without delaying the early start date of any immediately following activities
PERT
____ use(s) probabilistic time estimates—duration estimates based on using optimistic, most likely, and pessimistic estimates of activity durations—instead of one specific or discrete duration estimate.
Tracking Gantt chart
Project managers often illustrate progress with a ____ showing key deliverables and activities.
Parkinson's Law
____ states that work expands to fill the time allowed
Defining activities
____ results in supporting detail to document important product information as well as assumptions and constraints related to specific activities
project schedules
Project managers must use discipline to control ____.
controlling the schedule
Outputs from ____ include work performance measurements, organizational process assets updates, change requests, project management plan updates, and project document updates
activity attributes
The ____ provide(s) schedule-related information about each activity, such as predecessors, successors, logical relationships, leads and lags, resource requirements, constraints, imposed dates, and assumptions
longest; shortest
The critical path is the ____ path through a network diagram, and it represents the ____ time it takes to complete a project
defining activities
The goal of ____ is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work
schedule control
The goal of ____ is to know the status of the schedule, influence the factors that cause schedule changes, determine that the schedule has changed, and manage changes when they occur
defining activities
The main outputs of the ____ process are an activity list, activity attributes, and milestone list.
developing the schedule
The ultimate goal of ____ is to create a realistic project schedule that provides a basis for monitoring project progress for the time dimension of the project
Gantt charts
____ provide(s) a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format