CIS 4375 Chapter 4

Réussis tes devoirs et examens dès maintenant avec Quizwiz!

As projects progress, the organization must reevaluate the need, funding, and will for each project to determine if the project should be continued, redefined, or terminated. a. True b. False

True

Organizational process asset updates are an important output of the closing process of a project. a. True b. False

True

Payback period is the amount of time it will take to recoup, in the form of net cash inflows, the total dollars invested in a project. a. True b. False

True

Some organizations initiate projects using a contract in place of a project charter. a. True b. False

True

An organization's information technology project selection process should guide the strategic plan. a. True b. False

False

Corrective actions reduce the probability of negative consequences associated with project risks, while preventive actions should result in improvements in project performance. a. True b. False

False

Interface management involves identifying and managing the points of interaction between various elements of a project. a. True b. False

False

It is necessary that IT project managers have prior technical experience in creating and managing IT products. a. True b. False

False

Project integration management must occur just within the context of a particular project. a. True b. False

False

Projects that address broad organizational needs are likely to fail. a. True b. False

False

The number of interfaces in a single project is limited, and does not depend on the number of people involved in the project. a. True b. False

False

An annual discount factor is a multiplier for each year based on the discount rate and year. a. True b. False

True

NPV analysis is a method for making equal comparisons between cash flows for multi-year projects. a. True b. False

True

Which section of the project management plan describes specific methodologies a project might use and explains how to document information? a. management objectives b. project controls c. risk management d. technical processes

d

Which term is used for a formal, documented process that describes when and how official project documents may be modified, the people authorized to make modifications, and the paperwork required for these changes? a. WBS b. project charter c. performance report d. change control system

d

Which process involves working with stakeholders to create the document that formally authorizes a project? a. Developing the project charter b. Developing the preliminary project scope statement c. Developing the project management plan d. Performing integrated change control

A

. A project's internal rate of return can be determined by finding what discount rate results in an NPV of what value for the project? a. zero b. one c. a hundred percent d. fifty percent

a

What actions result in improvements in project performance? a. Corrective b. Defective c. Preventive d. Acceptance plan

a

What document used to coordinate all project planning documents and help guide a project's execution and control? a. project management plan b. statement of work c. scope statement d. business case

a

What is the majority of time on a project is usually spent on? a. execution b. planning c. closing d. monitoring and controlling

a

Which information is included in a business case? a. business need for the project b. relevant government or industry standards c. project objective, high-level requirements, and time and cost goals d. policies, procedures, guidelines, and systems that influence a project's success

c

Which process involves selecting information technology projects and assigning resources? a. project planning b. business area analysis c. resource allocation d. information technology strategy planning

c

Which process involves working with stakeholders to create the document that formally authorizes a project? a. Developing the project charter b. Developing the preliminary project scope statement c. Developing the project management plan d. Developing the organizational process assets updates

c

What term is used for benefits minus costs? a. cost of capital b. cash flow c. discount factor d. opportunity cost of capital

b

Many projects fail because of unclear requirements and expectations, so starting with a payback analysis makes a lot of sense. a. True b. False

False

Opportunities and directives are essentially the same thing. a. True b. False

False

The organization should complete low-priority projects before high-priority ones, if the low-priority ones take less time.

False

Change requests are always made in writing. a. True b. False

True

Information systems can help an organization support a strategy of being a low-cost producer. a. True b. False

True

Projects that arise as a result of problems and directives must be resolved quickly to avoid hurting an organization's business. a. True b. False

True

What is the first step in determining the NPV? a. determine the estimated costs and benefits for the life of the project and the products it produces b. determine the discount rate c. calculate the net present value d. determine the cash flow

a

What is the first step in the planning process? a. tie the information technology strategic plan to the organization's overall strategic plan b. perform a business area analysis c. start defining potential IT projects in terms of their scope, benefits, and constraints d. choose which projects to do and assigning resources to work on them

a

What statement is true regarding a return on investment or ROI? a. It is always a percentage. b. It is always a positive number. c. It is the result of adding the project costs to the profits. d. The lower it is, the better.

a

Which is an example of an organizational process asset? a. Management systems b. The organization's infrastructure c. Government standards d. Marketplace conditions

a

Which process includes defining project scope, benefits, and constraints? a. project planning b. business area analysis c. resource allocation d. information technology strategy planning

a

Which section of the project plan lists the planned dates for completing key deliverables? a. schedule b. closing c. budget d. objectives

a

What type of analysis involves calculating the expected net monetary gain or loss from a project by discounting all expected future cash inflows and outflows to the present point in time? a. Cost of capital b. Net present value c. Cash flow d. Payback

b

When does payback occur? a. When the net cumulative benefits minus costs equal one b. When the net cumulative benefits equal the net cumulative costs c. When the net costs are lower than the cumulative benefits d. When the cumulative benefits are double the cumulative costs

b

Which process is undertaken to reduce the probability of negative consequences associated with project risks? a. Performance reports b. Preventive actions c. Defect repairs d. Corrective actions

b

Which section of the project management plan provides the planned cost of deliverables? a. objectives b. budget c. risk d. technical

b

In a weighted scoring model, what percent must the sum of the weights of all the criteria total? a. 10 b. 50 c. 100 d. 150

c

What process involves identifying and controlling the functional and physical design characteristics of products and their support documentation, and ensures that the descriptions of the project's products are correct and complete? a. NPV analysis b. Project management information systems c. Configuration management d. Project time management

c

An IT company revises its process parameters in response to complaints from vendors that products were not ready on time. Which is this an example of? a. cost forecasting b. a preventive action c. defect repairs d. a corrective action

d

The outputs of which process include change request status updates, project management plan updates, and project document updates? a. initiating b. planning c. executing d. monitoring and controlling

d

What are new requirements imposed by management, government, or some external influence referred to as? a. Opportunities b. Charters c. Problems d. Directives

d

A Gantt chart is the same as a project management plan. a. True b. False

False

A SWOT analysis, being a linear process, cannot be performed using the nonlinear mind mapping technique. a. True b. False

False

A project charter typically does not authorize the project manager to use organizational resources to complete the project. a. True b. False

False

An organization should consider only projects with a negative NPV if financial value is a key criterion for project selection.

False

The ROI is always positive. a. True b. False

False

A summary of the planned approach for managing the project should describe stakeholder needs and expectations, important assumptions, and constraints. a. True b. False

True

In project integration management, directing and managing project execution involves carrying out the project management plan by performing the activities included in it. a. True b. False

True

Which stage of information technology planning outlines business processes that are central to achieving strategic goals and helps determine which ones could most benefit from information technology? a. project planning b. business area analysis c. resource allocation d. information technology strategy planning

b

Which section of the project management plan includes external interfaces, internal structure, as well as roles and responsibilities? a. overview b. technical processes c. project organization d. supporting processes

c

What term is used for the minimum acceptable rate of return on an investment? a. capitalization rate b. internal rate of return c. discount rate d. required rate of return

d

Which document recognizes the existence of a project and provides direction on the project's objectives and management? a. stakeholder register b. risk register c. directive d. project charter

d


Ensembles d'études connexes

ACT English Section Practice: Semicolons, Dashes, and Commas

View Set

Ultimate Glossary of Social Media Terms

View Set

Differential Diagnosis: Nervous System

View Set

Sinners in the Hands of an Angry God Study Guide/Worksheet

View Set