Construction Management Final Review

Réussis tes devoirs et examens dès maintenant avec Quizwiz!

There are now ___ standard divisions divided into ____ subgroups in the 2004 CSI master format system

49/5

The document that adds work to or deletes work from a contract is called ____

A change order

What is a characteristic of a critical path schedule

A critical path schedule has zero days of float on the path

Taxes, overhead, and profit in a estimate are commonly described by what term

Add-ons

Value engineering has what affect on a construction project

Alternate materials or means and methods are employed that saves the owner money without lowering the value of the project

What is the best way to describe a bid bond instrument

An instrument to protect the owner from having to pay extra to get the work done if the bidder with the lowest bid decides not to do the project

The ____ summarizes the actual payment amounts and provides the official approvals required before the payment can be released

Application for payment

Which set of forms is needed for progress payments

Application or certification for payment and continuation sheet

Which of the following are Three Levels of skill developed in the middle ages

Apprentice, Journeyman, Master

In contract documents, who approves the submittals that describe the products and equipment to be used during construction

Architect

When does a comprehensive quality management plan need to be in place

Before ground is broken on the project

What does the acronym BIM mean

Building Information Modeling

Which of the following mathematical skills may not be necessary for doing the tasks of estimating a construction project

Calculus

The method of implementing BIM such that project information can be loaded into one database is called ____

Central Repository

What is the process for identifying untended material or system interference in a construction project

Clash detection

The majority of projects a construction company will work on will come from?

Competing with other contractors

Mobilization occurs in which stage of a construction project

Construction

What is not part of the procedures during the project closeout

Correction period

Which three primary elements are associated with tracking the performance of a project

Cost, Quality, and Time

Noncompliance to standards and codes is what type of risk

Design

The owner on a construction project is accountable for which of the following

Developing the program to outline the needs of the end users

Identify the two main parts of contract documents

Drawings and the project manual

What is not a construction management job description

Electrical Subcontractor

What specific type of risk challenge are posed by wetlands

Environmental

A query is a list of items that the contractor wants to substitute as part of value engineering

False

Coordination of inspection and agency approvals are a minor issue in managing construction operations

False

Gantt charts, or bar charts show the start and finish of activities along with the task interrelationships

False

General conditions are also called job overhead because these are direct costs associated with any construction project

False

Historically, the construction industry has been looked on as incredibly efficient, safe and time saving.

False

If an estimate is equal to or greater than the actual cost, the contractor will lose money on the job

False

If certain trees or natural vegetation have to be maintained or preserved on the site - it will be the owners responsibility to make sure this is taken care of

False

If you spend time and effort to request an increase in time for the project due to a delay and you dont get it, it is a total waste of time

False

In Construction a program is a set of instruction telling the contractor how to build the building

False

In a deliver has something wrong with it, the person receiving it should log it and immediately call the supplier about the discrepancy

False

In a joint venture, one of the partners will be a majority partner assuming the major risks and preparing all of the estimates

False

In a lump sum contract if the project finishes under budget the owner does not need to release the full amount of the contract to the owner

False

Noise and dust control are issues that are covered in the general conditions of the contract

False

Political/legal/regulatory risks are so unpredictable and pretty much impossible for the contractor to anticipate so it is basically a waste of the contractors time to try and predict them

False

Retainage is a percentage of the money owed to the contractor that is held back due to the contractors inability to complete the project within budget

False

Second level players in the construction industry exercise great influence on a project through direct contracts with the owner, designer and contractor

False

Security measures and arrangements will be required by the contract but it is up to the owner to decide what measures are to be taken

False

Subcontractors typically contract directly with the owner for special or trade specific work

False

The actual forms that the contractor will fill out and submit are made available to the bidders upon request

False

The assistant superintendent is solely responsible for pursuing quality control on a project

False

The contract administration assists the project manager and the superintendent with construction details

False

The design intent model is prepared by a contractor to communicate design information

False

The general provisions of the contract include the duties of the architect in administering the contract will be located in the section along with responsibilities for visiting the site and inspections

False

The goal of an estimate is to be equal to or less than the actual cost

False

The goal of the construction team to construct the project with no complaints, defects or failures

False

The industrial revolution better defined the roles of various professions involved in construction wherein contractors took on greater responsibility for technical coordination

False

The main difference between construction and manufacturing is that construction takes place in controlled environments

False

The only risk that need to be identified for risk management purposes are those that deal with cost and delays to the schedule

False

The open bid process is required in both public and private bids to ensure transparency and fairness

False

Through their use of stone and stonemasons, the Greeks pioneered the development of Arches and Domes

False

When an owner contracts with a architect to design a project and then places the contract out for contractors to bid on. This is the Design-Build delivery system

False

When making the comparisons between the various items actual costs versus their estimated costs, its important for each item to come in within budget

False

With design/bid/build, value engineering always takes place during the pre-construction stage

False

With summary schedules major work tasks are broken down into smaller tasks in order to analyze them in greater detail

False

Price and reputation are the two criteria that will determine who wins the competition for a construction project

Fasle

Which of the following is not a type of estimate mentioned in the book

Final Estimate

What is not considered a construction management function

Funding the Project

Since spring of 2012, ____ are the information sheets that deal with pertinent chemical composition and other data that impact the safety of the user

GHS

The job overhead section of an estimate is made up of which of the following

General conditions

In a tight economy, the competition for construction projects will be ___ and contractors will be willing to take jobs at ____

Higher/Lower Profits

What is the contractor responsible for providing?

Labor, material, equipment, and expertise

Which of the following is the area on a site designated for the stored of large orders of material or equipment for easy identification

Laydown area

What describes the money assessed to the contractor upon failure to meet the specific contract completion date

Liquidated damages

What groups represent the bid selection criteria used to evaluate project bids

Low bid, best-value, qualification bid

With ____ the contractors are basing their bids on their own unique strategies for completing for completing the work

Low-bids

What is not an example of special purpose schedule

Material schedules

Activity-on-node and activity-on-arrow are examples of ____

Network diagram

Should an estimate be prepared before visiting the site

No

Construction safety standards in the United States are defined by which of the following organization

OSHA

Aside from aesthetics, appearance and durability what else is impacted by quality

Performance

What is used to monitor the safety of a project

Potential Risk Indemnification

The two main goals of a safety plan are ____ and _____

Prevent hazards/mitigate hazards

What is not a primary objective for the quality management plan

Processing documentation in a timely manner

Which of the following is not a function of direct labor cost in a construction project

Profit the owner makes

Who is the player in charge of the project from beginning to end?

Project Manager

The ____ follows the first steps outlined with the best value approach but price is not a factor

QBS

Plans and specifications are used to control which primary tracking element in a construction project

Quality

What do you call quality management addressed at the project level that deals with conformance to plan and specifications

Quality Control

Which of the following forms is used to seek information on contract documents

RFI

Which are two process tools used by contract administrator to track complex information

RFIs and Submittals

Which of the following is not a primary focus of a construction coordination meetings

Review the owners proposed budget

Risk allocation is an example of

Risk mitigation

Which tool is used to track project time

Schedule

What is not considered a source of feedback from the field used for project control

Shop drawings and submittals

What is used to monitor the quality of a project

Specifications and Drawings

What is used to monitor the cost of the project

The Estimate

What is used to monitor the scope of a project

The Project program

A certificate of occupancy will be issued after what

The certificate of substantial completion is issued

The project control cycle begins with ____ and ends with ____

The development of a project plan/ reporting and evaluation

Ultimately who will establish the level of quality for a construction project

The owner

The ____ is held to establish the rules by which the project is going to be governed and to clarify the lines of authority and communication

The preconstruction conference

The estimating process is best described by which of the following

The process of determining the project bid price

The term Takeoff is best described by which of the following

The process of quantifying materials, labor, and equipment

Which of the following is not included in the advertisement for bid

The project estimate

What is used to monitor the Time of the project

The schedule

Who is responsible for the overall safety of their workers and all of the equipment and materials they will be handling?

The superintendent/ The project manager

Which of the following are considered third level Players?

Trade Associations, Local, State and Federal Gov.

What is not considered direct cost

Trash and debris removal

A basic characteristic of a successful construction manager is the ability to anticipate and ward off potential project disruptions

True

A comprehensive quality plan will utilize several administrative and physical checks to monitor the quality of the project from start to finish

True

A method of sending the message to everyone that quality is important for the company is to create incentives and rewards for quality work that are a part of the quality assurance plan

True

A project team uses crashing to accelerate activities to offset the effects of a delayed schedule

True

A purchase order is an agreement between a vendor and a customer for products that meet a specific price and specification

True

A state required storm water pollution prevention plan will be instituted at the start of the project and maintained throughout the duration of the construction

True

A well-defined project scope is a key element in the successful completion of a construction project

True

Actual costs are what establishes the estimating database and the productivity rates of a construction project

True

Although third level players do not have direct links to the primary players, they still exercise a great deal of influence on a construction project.

True

As long as a new facility is under construction, it is a liability for the owner

True

BIM has the capability to integrate project-related data such as time and cost with a typical 3D model

True

Back charges refer to the money the general contractor charges for the work performed due to the failure of a subcontractor

True

Construction management at risk requires the construction manager to make design inputs as well as construct the project as a general contractor

True

Cost codes are used to track the work items contributing to teh overall project costs - and all job information having to do with cost will be tracked using these codes

True

If a contractor finds a project to be too risky it always has the option to not bid on it.

True

In construction a finite time frame associated with a completion date is one of the prime characteristics of a project.

True

In environmental Construction a contractor will probably be collaborating with ecologists, chemists, biologists, and other scientists

True

In most cases, it will be the superintendents responsibility to make sure that the workforce is prepared and motivated

True

In the construction information flow, the contractor will return the submitter to the subcontractor after the architect approves it

True

It is a good practice to involve subcontractors and major suppliers in the risk evaluation process

True

Knowing that a particular owner is difficult to work with or slow in making decisions is part of project management

True

Meeting or exceeding the requirements as set by the design documents defines quality in a construction project

True

Network logic helps determine the sequence of activities in a project and identify activities that can occur simultaneously

True

One of the most costly red flag clauses is for liquidated damages

True

Planning is the most important activity during the pre-construction phase

True

Poor contract administration will get a project into trouble faster than anything - if the project goes to court. The most organized managerial procedures will win the majority of the time.

True

Productivity depends on the construction managers ability to see that the job conditions support the maximum efficiency

True

Quantity surveyors are responsible for counting up and calculating all of the quantities of materials, labor and equipment necessary to build the construction project

True

Safety is something that cannot be compromised for any reason - it needs to be core value for the construction company - something that does not shift or change depending on the market or any other influences

True

Since personal safety of individuals of individuals is a goal of the safety plan the super has to enforce stringent rules regarding the requirements for PPE - and they have to be furnished for every worker according to what is needed for the job

True

Subcontractors are independent operators with their own schedules and other project besides yours - construction manager needs to be aware of this when preparing or altering a schedule

True

The contractor can assess risks before it even bids on the project by reviewing the contract requirements among other items

True

The first task of the contract administrator is to make a contact list with every single person associated with the project

True

The invitation to bid will be in letter form and will be sent to contractors with whom the owner has already worked or contractors who have a good reputation for the project type

True

The prime contractor on a construction project is the contractor that has a contract directly with the owner

True

The sheets in the set will be divided into the various disciplines like civil, architectural, structural, mechanical, etc. - Typically these drawings will be arranged according to the work represented on the sheets usually in the order that the work will be performed

True

The superintendent is responsible for coordinating all of the construction activities on-site and keeping the project on schedule

True

The time between bidding and starting construction, and the time between starting construction and completing the project are stretches of time that an estimator has to consider for labor price fluctuations and availability

True

There are primarily three types of architects designers, project architects, and specification writers

True

There are three foundations steps common to all risk management approaches risk identification, risk quantification, and risk mitigation

True

When plugging in unit costs for each material, labor, equipment and general conditions, the estimators is primarily concerned with where the costs are coming from and whether or not they are reliable

True

Maintaining a relationship with upper management is one of the attributes of leadership abilities

Yes

Who on the construction staff has been most involved up to the beginning of the pre-construction stage

estimator

What is not necessarily a characteristic needed for an estimator

is adept at operating construction equipment

With what is the financial officer primarily concerned

the creation of the budget


Ensembles d'études connexes

Chapter 9 Motivating Employees Vocabulary

View Set

CompTIA A+ Certification Exam 220-1101 Practice Test 1

View Set

US History Exit Review Chapter 20

View Set