A BOM file is often called a product structure file or product tree because it shows how a product is put together.

T

A master production schedule is an input to a material requirements planning (MRP) system.

T

A modular bill of materials is the term for an item that can be produced and stocked as a subassembly.

T

An input to the material requirements planning (MRP) system is an inventory records file.

T

Computing the quantity of each component that goes into a finished product can be done by expanding (or exploding) each item in a product structure file and summing at all levels.

T

In a net change MRP system requirements and schedules are updated whenever a transaction is processed that has an impact on the item.

T

MRP is a logical, easily understandable approach to the problem of determining the number of parts, components, and materials needed to produce each end item.

T

MRP is based on dependent demand.

T

MRP is most valuable where a number of products are made in batches using the same productive equipment.

T

MRP provides the schedule specifying when each part and component of an end item should be ordered or produced.

T

MRP stands for Material Requirements Planning.

T

Manufacturing firms maintain bill of materials (BOM) files, which are simply a sequencing of everything that goes into a final product.

T

Net change MRP systems are "activity" driven.

T

The deeper one looks into the product creation sequence, the more the requirements of dependent demand items tend to become more "lumpy."

T

The master production schedule states the number of items to be produced during specific time periods.

T

A modular bill of materials includes items with fractional options.

F

An input to the material requirements planning (MRP) system is an exception report.

F

An output of MRP is a bill of materials (BOM) file.

F

In a net change MRP system requirements and schedules are considered rigid and never updated.

F

MRP is least valuable in industries where a number of products are made in batches using the same productive equipment.

F

MRP stands for Manufacturing Requirements Planning.

F

The MRP program performs its analysis from the bottom up of the product structure trees, imploding requirements level by level.

F

The deeper one looks into the product creation sequence, the more the requirements of dependent demand items tend to smooth out and become even over time.

F


Ensembles d'études connexes

AMDT 108 Final Exam (Chapters 8-13)

View Set

Exam 1 (Physical Fitness and Wellness, & Body Comp.)

View Set

Chapter 56 Drugs for Psychotic Disorders

View Set