23. Which of the following is one of the main outputs of estimating activity resources process? a. Project documents update c. Work breakdown structure b. Milestone list d. Activity duration estimate

A

30. _____ is the amount of time an activity can be delayed from its early start without delaying the planned project finish date. a. Total slack c. Backward pass b. Free float d. Forward pass

A

39. Which of the following is an output of schedule control? a. Lessons-learned reports c. Resource requirements b. Activity attributes d. Milestones list

A

13. In project time management, the next step after defining project activities is: a. planning schedule management. c. controlling the schedule. b. determining their dependencies. d. estimating activity duration.

B

27. Which of the following is a network diagramming technique used primarily to predict total project duration? a. Gantt chart c. Resource breakdown structure b. Critical path analysis d. Arrow diagramming method

B

3. In project time management, which of the following processes generate the main outputs of an activity list, activity attributes, and a milestone list? a. Sequencing activities c. Resource estimating activities b. Defining activities d. Estimating activity durations

B

40. A draft schedule for a project is most likely to be found in a _____. a. project buffer c. resource breakdown structure b. project charter d. project's dummy activities list

B

6. In project time management, which of the following processes involve analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule? a. Planning schedule management c. Controlling the schedule b. Developing the schedule d. Defining activities

B

1. The first process involved in project time management is _____ . a. defining activities c. planning schedule management b. estimating activity durations d. sequencing activities

C

25. In project time management, the ultimate goal of _____ is to provide a basis for monitoring project progress for the time dimension of the project. a. defining activities c. developing a schedule b. sequencing activities d. estimating activity resources

C

29. The amount of time an activity can be delayed without delaying the early start date of any immediately following activities is known as a _____. a. forward pass c. fast tracking b. backward pass d. free slack

D

37. A difference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM) is that: a. CPM addresses the risk associated with duration estimates whereas PERT does not. c. CPM involves more work than PERT because it requires several duration estimates. b. unlike CPM, PERT estimates only when there is no risk of uncertainty. d. PERT uses different duration estimates whereas CPM uses one specific duration estimate.

D

9. Which of the following documents is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule? a. Resource breakdown structure c. Organizational process assets update b. Milestones list d. Project charter

D

13. In a network diagram, it is mandatory for every item on the WBS to be shown instead of only those activities with dependencies.

F

16. A drawback of the precedence diagramming method is that it cannot be used unless dummy activities are employed.

F

17. In project time management, one should control the scheule before estimating the duration for each activity.

F

18. In a Gantt chart, thick black bars represent milestones achieved in a project.

F

2. In project time management, the primary output of defining activities is a schedule management plan.

F

20. A disadvantage of using Gantt charts is that they do not provide a standard format for displaying planned project schedule information.

F

23. A backward pass through the network diagram determines the early start and early finish dates for each activity.

F

25. The main disadvantage of crashing is that it lengthens the time needed to finish a project.

F

27. Critical chain scheduling assumes that resources multitask and maximizes multitasking.

F

28. One of PERT's main disadvantages is that it does not address the risk associated with duration estimates.

F

29. The final process in project time management is developing the schedule.

F

9. After defining project activities, the next step in project time management is developing the schedule.

F

19. A Tracking Gantt chart is based on the percentage of work completed for project tasks or the actual start and finish dates.

T

26. The technique of fast tracking can result in lengthening the project schedule.

T

4. Project schedules grow out of basic documents such as the project charter.

T


Ensembles d'études connexes

Champions - Promulgated Contract Forms

View Set

Exam #5 (Modules 9 & 10) - NUR415

View Set

Grade 8 Unit 14 Synonyms and Antonyms

View Set

M.A 106: CH 12 Electronic Health Records

View Set

Cardio Pharm Qs - CHF, Diuretics, Anti-anginal, Anti-arrhythmics, Lipid Lowering

View Set

Ch. 12 HW Quiz: Social Psychology

View Set