Unit 2 Exam: Project Management
A _________ activity is one that has more than one activity immediately following it.
Burst
A(n) _________ activity has more than one dependency arrow flowing from it.
Burst
Tom is responsible for ordering hardware for a custom home his company is building. The contractor installing the hardware is scheduled to start in 5 working days, but the hardware is on backorder and will not arrive for another 9 working days. Fortunately, Tom has 10 days of slack; however, he shares this slack with the hardware installer. He will have to let the contractor know that the hardware will be ready 4 days later than expected and that the slack for the installer has been reduced by 4 days. Tom and the installer share 10 days of
Total Slack
The amount of delay within a task that will not delay the overall project is known as a
Total Slack.
The amount of time an activity can be delayed and yet not delay the project is termed
Total slack.
A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000. Which of the following is true?
We can't be sure how the project is going
A Risk Response Matrix contains all of the following EXCEPT
When the risk will occur
Which of the following is true about hammock activities?
Which of the following is true about hammock activities?
The risk assessment form contains all of the following EXCEPT
Who will detect the occurrence of the risk event.
Including the change control system within the ________ is a key to a successful project.
Work Breakdown Structure and Project Baseline
Information to develop a project network is collected from the
Work breakdown structure.
Project budgets are developed by time-phasing which of the following?
Work packages
Refining Estimates may be necessary for a number of reasons. For example, a manager getting further into a project and obtaining a better understanding of what needs to be done to accomplish a project and meet the needs of the customer is an example of
Changes in project scope.
If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?
Check to see which activities are on the critical path.
What is the relationship between organizational culture and estimating?
Cultural norms affect the accuracy of estimates.
All resource leveling techniques involve
Delaying noncritical activities.
Based on the following, which event should you be most concerned about? Risk Event Likelihood Impact Bad weather 2 3 Design flaw 3 5 Accident 1 5 Shipment delay 2 2 Power outage 1 5
Design flaw
Which of the following is NOT true in regard to the level of detail estimates should contain?
Detailed estimates are crucial to project success; therefore, an effort should be made to make estimates as detailed as possible for all projects.
_____________ is a measure of how easy it would be to notice that a risk event was going to occur in time to take mitigating action, that is, how much warning you would have.
Detection difficulty
This is used to compare the cost accounts between organizational units and deliverables.
Direct Labor Budget Rollup
Item50 0/2 points awarded Item Scored References Item 50 Item 50 0 of 2 points awarded Item Scored The salary of the project manager would be an example of what type of cost found in a project?
Direct project overhead
Which of the following will correctly calculate the total slack in an activity?
Either LS - ES or LF - EF
This response is used to increase the potential effect of an identified Opportunity.
Enhance
A special truck that George needs on his project has been scheduled on another project. This is an example of what type of resource constraint?
Equipment
The process of forecasting or approximating the time and cost of completing project deliverables is called
Estimating.
The requirement for a freshly poured foundation to cure before beginning construction is an example of which of the following type of lag?
Finish to Start
One common mistake made early in the risk identification process is to
Focus on consequences and not on the events that could produce consequences.
Which of the following can be used without coordinating with managers of succeeding activities?
Free slack
Accounting would be an example of which of the following costs typically found in a project?
General and administrative overhead
Which of the following does NOT help describe a project network?
Highlights major deliverables and identifies their completion dates
Which of the following is NOT one of the potential responses to a specific risk event?
Ignoring
Which of the following is a good condition for top-down estimating?
Internal, small project
All of the following are benefits of scheduling resources before project implementation EXCEPT
It ensures low network sensitivity.
Why is it necessary to have a time-phased budget baseline?
It shows how much work was accomplished for the money spent.
Which of the following correctly calculates the late start for an activity?
LF - DUR
Learning curves are more likely to be applied in situations where most of the costs are
Labor.
The assumption that all immediate preceding activities must be 100% complete is too restrictive in some situations. When an activity is broken down into smaller segments in order to start the succeeding activity sooner, this is called
Laddering.
The pattern of improvement identified from a worker having performed a task multiple time is known as a
Learning Curve.
Laura is forecasting the time and cost of developing an intranet for a new customer. Her department has completed six such intranets for customers during the last two years. Although the proposed system is about the same size as the others, she estimates that it will take about 10 percent less time and money. Which of the following methods is she using?
Learning curve
Which of the following is NOT one of the bottom-up approaches to estimating project time and cost?
Learning curve
In a resource-constrained project, the first priority in assigning resources is usually given to activities with the
Least slack.
Risks are evaluated in terms of
Likelihood and impact.
A ____________ (responsible for the work package) involved in risk assessment and mitigation will help focus attention on all aspects of risk management.
Line Person
Bill is building a project network that involves testing a prototype. He must design the prototype (activity 1), build the prototype (activity 2), and test the prototype (activity 3). Activity 1 is the predecessor for activity 2 and activity 2 is the predecessor for activity 3. If the prototype fails testing, Bill must redesign the prototype; therefore, activity 3 is a predecessor for activity 1. This is an example of
Looping.
Which of the following is identified to cover major unforeseen risks and, hence, are applied to the total project?
Management reserves
Gene is trying to order the concrete needed to continue his project. However, the supplier will not be able to deliver it until next week. This is an example of what kind of resource constraint?
Materials
An activity that has more than one dependency arrow flowing into it is termed a(n)
Merge activity.
Jan is trying to reallocate resources in a time-constrained project to create smoother resource utilization. She should first identify activities with the
Most slack.
Refining estimates may be necessary for a number of reasons. For example, resource shortages, in the form of people, equipment, or materials, can extend original estimates. This is a good example of
Normal conditions not applying.
_______________ focuses on how to respond to events that have a positive impact on a project
Opportunity management
A _________ activity is one that has more than one activity taking place at the same time.
Parallel
A good starting point for developing time and cost estimates is
Past experience.
A sequence of connected, dependent activities is termed a(n)
Path
Sam, the project engineer, has been scheduled to run the product system test at the same time he is to build a marketing prototype. This is an example of what type of resource constraint?
People
Which of the following would be the best method for projects where the final product is not known and the uncertainty is very large?
Phase estimating
Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test. This is an example of a constraint that could impact the sequence and timing of activities in a project network. What type of constraint is it?
Physical
Richard is collecting estimates for a house that he will have the funding to build in 12 months. Which of the following factors does Richard need to consider in regard to the quality of these estimates?
Planning horizon
________ activities must be completed immediately before a particular activity.
Predecessor
Ed is looking over the actual results of projects and comparing them to what was estimated. He notices that the projects that took six months or longer to complete were noticeably more off the estimates. Which of the following factors is he recognizing?
Project duration
Rob is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to complete. Due to the uncertainty involved he will be making a low, an average and a high estimate. Rob is using which estimating approach
Range estimating
In reviewing the status of her project with top management, Shirley was told that there are only two programmers that she can use for her project. Her project is classified as __________ constrained.
Resource
When there are not enough people, money, and/or equipment available for a project it is known as being
Resource Constrained.
If resources are not adequate to meet peak demands, the resulting reschedule is termed
Resource-constrained scheduling.
The risk associated with the unlikelihood that one of the key members will be struck by lightning would most likely be handled by which of the following?
Retaining
Organizations use __________ in conjunction with work breakdown structures to help management teams identify and eventually analyze risk.
Risk breakdown structures
A list of questions that address traditional areas of uncertainty on a project is termed a
Risk profile.
Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation?
Scope creep
The risk management tool that is divided into three color-coded zones representing major, moderate, and minor risks is the risk
Severity matrix.
This response allocates some or all of the responsibility of realizing the identified Opportunity for the project.
Share
The cost impact of a risk event occurring as a project proceeds through its life cycle tends to
Slowly rise.
Resources are adequate, but demand varies widely over the life of the project. Delaying noncritical activities to lower peak demand on resources is known as resource
Smoothing.
System documentation cannot end until three days after testing has started. This is an example of which kind of lag?
Start to Finish
Concurrent engineering, which has dramatically reduced the development time for new products, relies on what kind of lag?
Start to Start lags
________ activities are to be completed immediately following a particular activity.
Successor
While balancing assignments, a project manager must also balance:
Talent development.
When developing a new software package, logically, the software must be designed before the code is written, and the code must be written before it is tested. These activities are dependent on each other by _________ constraints.
Technical
Technical constraints have been carefully considered when developing a project network. Which of the following is true at this point?
Technical dependencies between activities are known.
Risks that can result in a system or process that will not work are known as
Technical risks.
The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as
Template method.
In a resource-constrained project, which of the following is most likely to be changed?
The completion date
The forward pass in project network calculations determines all of the following EXCEPT
The critical path.
When completing a backward pass, you carry the LS to the next preceding activity to establish the LF, unless the next preceding activity is a burst activity, in which case you select
The smallest LS of all its immediate successor activities to establish the LF.
Which of the following does NOT help describe a bottom-up estimating approach?
They are made by someone who uses experience and/or information from someone else to determine overall project cost and duration.
Regina's boss has told her that her project is very important. If the critical path is delayed, she will be given whatever she needs to get it back on schedule. Her project is classified as ________ constrained.
Time
When considering the sequence and timing of activities, which of the following is NOT one of the types of project network constraints?
Time
Reasons why estimating time and cost are important include all of the following EXCEPT
To help establish a project selection process.
One piece of information that the arrows within the Activity-on-Node network can convey is
how activities are related.
A project network provides the basis for ________________________________ .
scheduling labor and equipment
Resource leveling or smoothing can have all the following results on a project EXCEPT
A longer project duration.
The implications of an identified change need to be assessed by:
A person with expertise related to the change.
A key distinction between a risk response and a contingency plan is
A risk response is part of the actual implementation plan and action is taken before the risk can materialize, while a contingency plan goes into effect only after the risk has transpired
This response is used when an identified Opportunity is not actively pursued.
Accept
Change management systems are designed to accomplish all of the following EXCEPT
All of these are examples of what change management systems are designed to accomplish
Which of the following is NOT included in a Failure Mode and Effects Analysis?
All of these are included.
When deciding which staff to team-up to work on work packages, factors to consider are:
All of these choices are correct.
Typical kinds of costs found in a project include all of the following EXCEPT
All of these choices are examples of costs found in a project
Estimating can be challenged by
All of these choices.
Which of the following groups should NOT be a part of the risk identification process?
All of these groups can be included in the risk identification process.
Tools such as a risk assessment form and a risk severity matrix are used to
Assess risks.
Adopting proven technology instead of experimental technology in order to eliminate technical failure would be an example of which risk response?
Avoiding