AIC
Given an account with 6,000lbs of rebar an installation rate of 0.02 work hours per pound, and a labor budget of $ 2400. What is the cost per hour?
$20.00
Five Contractors are bidding part of a job with storm sewer, sanitary sewer, and water distribution. Their bids are: Contractor 1 will do storm and water for $2000. Contractor 2 will do storm for $1000.Contractor 3 will do sanitary and water for $12,000. Contractor 4 will do sanitary for $7,000 Contractor 5 will do water for $7,000 What is the lowest price for the complete job?
$9,000
What is the actual size (thickness and Width) of a 2x8 board?
1-1/2" thick by 7-1/2" wide
Using the round-trip time of 0.67 hours for one truck, what is the number of theoretical round-trips per hour that one truck can make?
1.49
A piece of equipment has a book value of $10,000, a salvage value of $1,000, and an estimated life of 5 years. What is the depreciation in the beginning of the second year using the depreciation is used?
10,000 - 1,000 / 5 = 1,800
'place concrete' activity requires the placement of 2080 cubic yards. If the individual production rate is 2 cubic yards per work hour per person, with a 10-person crew and 8 hour workday, how many days are needed to complete this activity?
13
An 8% grade is equivalent to what slope?
1:12.5
The term "2/10 net 30" represents
2% discount can be deducted if paid within 10 days of receipt of goods or full payment due in 30 days
Concrete to be poured for 10 footings are 5 feet wide by 5 feet long by 2 feet deep. How many cubic yards of concrete should the estimate be for this pour, using a 10%waste factor.
20.3
For a gable roof, how many Squares of shingles are required for a building that is 24' by 80' with 5/12 slope and a 2' overhang on all sides?
23.5
OSHA's rule in an opening trench excavation what is the maximum allowable distance of travel to an exit ladder?
25ft
A portable ladder is being set up. The distance between the ground and the first floor is 16ft. according to OSHA, what is the minimum ladder extension required above the area?
3ft
What is the MAXIMUM allowable spacing of the walls in inches?
48
A project schedule has been updated. The activity placement of spread footing concrete was originally scheduled to begin as early as day 10. The activity duration is 4 days. The actual start day was day 12. The original schedule had calculated total float of 7 days for this activity. The recalculated total float for the activity, when updated, would be
5 days
What is the allowable Maximum height of an open sided floor before fall protection measures must be provided for workers?
6ft
What is a "Schedule of Values"?
A breakdown of the contract amount into pay items
What is an addendum?
A change or addition to the contract documents before bids are due.
A progress payment application from a subcontractor should also include
A conditional waiver of lien
Which of the following is an activity that has little total float?
A near critical activity
In the bid documents, the owner requests an HVAC system that meets all local codes and maintains 72° C cooling and 68° C heating, No other information is located in the bid documents. This is an example of
A performance specification
Which of the following projects have the highest potential profit for the contractor?
A project which includes responsibility for the design, building, fencing, and leasing of a new office building.
What information must be gathered to update the progress of a schedule
Actual Start/Finish dates and percent complete
The mechanical subcontractor on a project discovers a dimensional conflict between the mechanical and structural drawings and submits a request for information (RFI) to the general contractor. What action should be taken by then general contractor?
Advise the architect of the conflict and request a decision
What MUST an OSHA compliance officer do at the closing conference of an inspection?
Advise the contractor of apparent violations
Under an agency construction manager agreement. Which party holds the contracts with the trade contractors?
Agency construction manager
If concrete is allowed to drop freely for more than 4 feet into place, which of the following is most likely to occur?
Aggregate separates from cement-water paste
Assume the elevated slab is designed for 100psf. The pipe subcontractor requests permission of the site superintend to use a mobile scissor lift on a elevated slab. The lift has a contact area of 30"X60". It weighs 1,100lbs and has a load capacity of 500lbs. what action should the site superintendent take?
Allow use of the lift
The owners representative has the authority to
Approve changes and/or clarify the work
Under construction management agreement, scopes of work are typically defined by the.
Architect Owner???
A contractor has received a low bid from a new subcontractor. In consideration of work on the project, the owner has a strong safety program for contractors and subcontractors. Which of the following methods represents the best way obtain information about the subcontractors safety record?
Ask for qualification statement and look for an experience modification rate less than 1.0
Which of the following financial reports includes both accounts receivable and accounts payable?
Balance sheet
The bid bond covers the period from the time of
Bid submission until the signing of the agreement
What are the rating requirements for a door opening in a rated wall?
Both the door and the frame must be rated
During Construction, high winds cause a masonry wall to collapse. What type of insurance coverage protects against physical damage to the in-place construction of the wall?
Builders Risk
Which of the following has the highest priority after a discovery on a Monday morning that the job site has been vandalized and the magazine cases have been emptied of explosives?
Call the police to initiate an investigation
What does a "10B" rating for a fire extinguisher indicates?
Capability to extinguish 10 square feet of flammable liquid spill.
What is the term for a change order issued by the owner of a project that is outside of the contractor's scope of work and therefore the contractor can a refuse to perform the work?
Cardinal change
The horizontal roof drain conductors installed above finished ceiling require insulation to prevent damage to the
Ceiling caused by condensation
When engaged in heavy grinding of concrete where sever exposure occurs, using a diamond tip blade, which of the following would be proper protection for the face and eyes?
Chipping goggles and a face shield
The invert of a sanitary sewer line coming into a manhole is found in the
Civil drawings
A request for information form is used by the contractors to request
Clarification of an issue from the architect
Shallow foundations in the form of square spread footings are generally used to support?
Columns
Which of the following is the most useful information in the preparation of a conceptual estimate for a building?
Comparable cost for similar types of buildings
What is the first step in the subcontract bid analysis process?
Comparing the scope of inclusions and exclusions
The purpose of retainage is to encourage the general contractor to?
Complete project per contract
Which of the following is required for an employee to operate a powder operated tool?
Completed training card
The location of reinforcing steel used in a concrete member should be placed where?
Concrete is in tension
During pre-bid review of documents prepared by an engineer from another state, a bidding contractor who suspects that the design provided does not meet the state building code should.
Confirm design meets local code
Which of the following is considered a project closeout document?
Consent of surety
What is fast-track construction?
Construction that starts before the design
A topographical map is a drawing showing?
Contour lines and elevations
If the contractor is making a claim under the different site conditions (DSC) clause, which of the following must be proven?
Contractor visited the site
Which of the following can be identified from the initial schedule of values?
Contractors proposed breakdown of the project cost
What type of joint primarily accommodates shrinkage of concrete slabs to prevent irregular cracks?
Control
Which of the following is the most effective way to eliminate days out of the projects duration?
Crash critical path activities
If a schedule is accelerated, which of the following activities must be focused on first?
Critical activities
What is the standard unit of measurement for excavation and backfill?
Cubic yard
Unpaid invoices from subcontractors working on a company's project would be included in the financial statements under
Current liabilities
Where is the best place to document material deliveries received on site?
Daily report sent to the contractors accounting office
The payment of a liability will
Decrease both assets and liabilities
In which of the following project phases would value engineering be implemented in the most cost effective way?
Design
Who is responsible for inspecting for safety risks on a project prior to operation?
Designated competent person
The MAIN reason for establishing an effective project cost control system for labor and equipment
Develop information for forecasting cost of completion.
When is the best time in the construction project cycle to start developing a plan for project staffing requirements?
During the bid proposal process
When fabricated reinforcing bars are delivered to the project site, a project representative should cross-check each item
During unloading and storing
How is free float calculated for an activity?
Earliest start of the next activity minus early finish of the current activity
Which of the following are calculated by the "forward pass" through the CPM network?
Early start early finish
When a series of red flags or a red line is placed on the ground using spray paint, what does the line symbolize?
Electric line below
The OSHA "General Duty Clause" obligates
Employers to provide a workplace free of known hazards
According to the Constructor Code of Conduct, which of the following situations is considered Primarily under the code rather than in the legal system?
Engaging in any deceptive practice that creates unfair disadvantage
Who is responsible for verification of all materials, field measurements, and field construction criteria on the shop drawings?
Engineer
Which of the following best describes a caisson falling basket?
Enlarges the bottom of caisson
A light fixture slides of the electrical subcontractors scaffolding in the lobby of a new bank building. The result is several hundred dollars in damage to the floor finish. Workers below could have been hit by the falling fixture. Which of the following is the best course of action to take?
Ensure presence of OSHA approved railing, toeboarding and netting on all scaffolds
Which of the following is an estimated amount placed in the budget to cover future price increases in labor and materials on a long-term project?
Escalation
On a project estimate, which of the following items is included in a project overhead expense?
Estimating cost
A concrete wall is 16" thick, 20' high, and 108' long. The rate of placement is 3 vertical ft per hour. Concrete is delivered in 8 cubic yard trucks. How frequently should the trucks arrive assuming no problems arise?
Every 30 Minutes
Material was appropriately ordered with sufficient lead time to be available on the site when needed; however, the vendor delivered the material three weeks late. Which of the following activities was poorly practiced by the contractor?
Expediting
Which of the following incorporates the tracking, confirming, and accelerating of delivery of an item that has been purchased?
Expediting
Which of the following insulation material has the highest R value for the same thickness of material?
Fiberglass
On unit price contracts, approval of payment requests to the owner for progress payments is based upon
Field measured quantities
When the start of one activity depends on the completion of the preceding activity, the relationship on a logic network of the two activities is a
Finish to Start
Which of the following authorities are involved with the issuance and signing of the Certificate of Occupancy?
Fire Marshal, electrical inspector, and building inspector
Building codes typically account for the fact that light wood framing is highly combustible by requiring
Fire walls and fire stops
What is the typical sequence for construction of a conventionally reinforced elevated slab?
Form, reinforce, pour, reshore, strip, cure
What document should the prime contractor require from all of the subcontractors at the end of a project?
Full unconditional release
If an accident occurs on site because a masonry subcontractor employee is not abiding by the safety regulations, who is ultimately responsible?
GC
According to CSI, which of the following is in the project manual?
General requirements
Which of the following provides the highest strength to dimensional lumber?
Grain orientation
The architect has approved the rerouting of an HVAC through concrete slabs in a building. To insure that activities are coordinated, a meeting should be called by the field supervisor and the
HVAC subcontractor and all other affected subcontractors
To conduct an effective team meeting, it is best to
Hand out an agenda and see the team member has it prior to the meeting so they can come prepared
In creating a schedule, which of the following occurs first?
Identify the activities
The Primary purpose for identifying the critical path on the logic network is to
Identify the longest continuous path with the minimum amount of time for over all completion
Which of the following best describes lag in precedence scheduling?
Imposed duration on the relationship between two activities.
When reviewing subcontractors financials, which of the following information would be found on the income statement?
Income and expenses for the fiscal year
Air entrainment is used in concrete to
Increase concrete's resistance to freeze-thaw damage.
Soil compacted at its "optimum moisture" content will result in?
Increased compaction effort, the greatest weight per volume ratio, and reduced settlement
Which of the following clauses states that "the contractor will protect the owner and designer from claims, even if the owner or designer is wholly responsible for the loss"?
Indemnification
Which of the following are the horizontal floor members in platform framing?
Joists
Which of the following techniques would best assist project managers in improving production and process controls?
Lean construction
When completing a certificate of substantial completion list, which of the following must be attached to the form?
List of uncompleted work
If there is a conflict escalating between two field engineers working on alternate shifts, the project managers best approach would be to
Listen to both sides of the issue and then make a decision
Which of the following is the most expensive option when resolving disputes?
Litigation
Which of the following graphic arrangements identifies tasks, their interrelationships, and sequence of activities?
Logic diagram
In the competitive bidding process, which type of contract results in the most risk to the contractor?
Lump Sum
What is the best source of worker safety information to use when bricks are to be washed down with acid?
MSDS file
What format is based on the CSI conceptual estimating system?
Master format
According to OSHA's regulatory posting standard, which safety information must be posted at the site on the employees bulletin board?
Material safety data sheet location and safety and health protection on the job
The uniform construction code is an area of
Material suppliers
Which Soil test measures the moisture-density relationship of soils?
Modified proctor
In the traditional design-bid-build approach, the contractor.
Must report to the design professional team any building code nonconformity in the contract documents.
As required by safety codes, the type and rating of doors installed in a multi-tenant office building are determined by the
National Fire Protection Agency
The owner's rep observed substandard drywall patches on a general contractor's renovation project. Which of the following should be the representative's first course of action?
Notify general contractors superintend of problem
Which of the following time of completion measures is likely to be MOST equitable for both parties in the Owner-Contractor agreement regarding the impact of weather conditions?
Number of workable days
Which of the following are legal elements of the contract?
Offer, acceptance, meeting of the minds, and consideration
The national labor relations board (NLRB) is authorized to develop what types of disputes?
Organized workers-contractor
In a construction management contract. The construction management firm typically has contractual relationship with the
Owner only
A contractor submits a bid for $1,277,610 with the appropriate forms and bid bond and receives a letter indicating the bid has been selected. If the contractor then decides not to accept the contract, what is the maximum the contractor will lose?
Penal sum of the bid bond
What method is used to calculate activity duration?
Plan quantity divided by daily production rate
What stage of the management process has the greatest impact on the success of a project?
Planning
The construction contract requires the contractor to submit a complete schedule. This draft so far includes work activities, their duration, and milestones. Which of the following other information is necessary to develop this schedule?
Procurement of long lead times
Which of the following best describes schedules, performance charts, or literature that must be submitted to illustrate the properties of a material for the specified work?
Product data
The "value analysis" is a systematic evaluation of a
Product design to identify cheaper materials and methods of construction
Who is responsible for overall construction project, planning, scheduling, and cost controls?
Project manager
Which of the following protects a prime contractor from a subcontractor who is not honouring the original bid price before a formal contract has been executed?
Promissory estoppel
Which of the following specifications identifies a single brand name, model number, or other specific manufacturer information?
Proprietary
According to OSHA, what action MUST a contractor take to is to instruct employees about hazards that cannot be eliminated?
Provide instructions about recognition and handling of unsafe conditions
Which of the following is used to determine the dew point at varying temperatures?
Psychometric chart
A supplier who provides only materials to a project normally expects what type of agreement?
Purchase order
An ethical dilemma is present as a vendors representative offers to
Reduce the unit price if the superintendent hires the representatives child as a summer worker
Which of the following is placed by a rodbuster?
Reinforcing steel
Subcontractor "A" submits shop drawings to the GC which include materials that do not comply with the contract documents. The GC as well as the architect stamps all of them "reviewed". The materials are then shipped to the job site. During an off-loading inspection, the GC notices the noncompliance. What action should the GC take concerning the matter?
Reject the shipment and require compliance with the contract documents
According to Osha record keeping guidelines, which of the following is a recordable job-related incident?
Removal of foreign bodies embedded in the eye
The primary purpose of using admixture in a concrete mix is to
Resolve concrete placement conditions
The contract documents specify 18 gage studs 16in on center. The framing contractor is submitting product data and shop drawings for 16 gage studs at 24inch on center. What should be done?
Return to the framing contractor and request a compliance submittal
What is the major reason for using tempered glass?
Safely breaks into small pieces
Which of the following best describes the relationship between construction planning and scheduling?
Scheduling of activities cannot begin until after determining the constraints on the project
Which of the following pre-bid information should be gathered for developing a bid proposal?
Schematic design, design development drawings, contract documents, project manual, and bid documents
The GC receives a bulletin from the architect requesting a price on a modification to the work on an ongoing project. What is the most appropriate method for the GC to issue the bulletin to subcontractors?
Send the documents to all subcontractors capable of performing the work
Which of the following is the MAJOR advantage of a design/build contract for the owner?
Single source responsability
Information is used to determine the required contact area of reinforced concrete footing resting in soil
Soil bearing capacity
Who is responsible for preparing the shop drawings?
Subcontractor or vendor
Fire resistance ratings of a building assembly are determined by
Subjecting the assembly to a fire endurance test
During the submittal process, if a contractor is able to procure a superior, nonconforming product of a cheaper cost, the contractor should
Submit a request for substitution
What should be the first step once a project manager believes the project team agrees on a planned schedule?
Submit the schedule to the owner for comments
What is the point in the project when the architect has determined that the facility or a portion of the facility is acceptable for owner use and occupancy?
Substantial completion date
What are the results if the contractor defaults on a bonded construction project?
Surety assumes responsibility for the completion of the project only.
Which of the following documents primary purpose is to describe the materials and quality of workmanship for each construction division?
Technical specifications
According to AIA documents, if a project is delayed due to abnormal weather conditions, which of the following best describes the liability of the contractor?
The contractor is entitled to an extension of time and no additional compensation
A contract for a project contains a liquidated damages clause. The project is under compensable delay for 4 days. In addition, rain caused another 5-day non-compensable delay. How should the delay be handled?
The contractor should request a 5-day time extension due to the rain, and should be compensated for the 4 days compensable delay by the owner
What is Retainage?
The difference between the gross earned and the amount paid to the contract
Which of the following is a primary advantage to a contractor in a joint venture for construction of a project as compared to a legal partnership?
The entities remain seperately controlled for other operations
If a masonry contractor has been given a back charge by a general contractor, what does this mean?
The general contractor is deducting a sum of money from the masonry contractor's contract amount
Rigging is being connected to a piece of equipment that will be lifted to a roof approximately 35ft high. How will slings lifting capacity be affected, using a low-sitting 29o angle instead of 45o angle?
The loading on the sling will increase
If the shop drawing is stamped "approved with noted correction, however, provide record copy" which of the following is the best interpretation?
The vendor or subcontractor can begin delivery or fabrication
When shoring a deep excavation in a congested area, which of the following will allow the greatest freedom of movement within the work area?
Tiebacks
What is the purpose of a fusible-link door closer?
To assist in fire containment
Which of the following is a primary reason that the contract documents require the contractor to submit a project schedule promptly?
To determine contractor's plan and sequence of activities to accomplish the work
What is the value of the project cash flow projection?
To identify the ability to fund the job
What is the purpose of through-wall flashing in brick veneer construction?
To prevent water from infiltrating brick veneer
What is the purpose of the Leadership in Energy and Environmental Design (LEED) Green Building Rating system?
To provide a scoring system to recognize the sustainability of buildings
What is the primary purpose of the national electric code (nec)?
To safeguard persons and property from hazards, arising from the use of electricity.
Which of the following is best to determine the proper tightness of bolts in a structural steel connection?
Torque wrench
On masonry buildings, which of the following could be used to check vertical alignment of structural steel, elevator shafts and walls?
Total station
On multi-story buildings, which of the following could be used to check vertical alignment of structural steel, elevator shafts, or walls?
Total station
A contract that specifies the payment terms in dollars per quantity installed is what type of contract?
Unit price
A contingency fund would be used for?
Unknown conditions
What is the general contractor required to do when material is purchased "FOB job site"?
Unload the material that the supplier delivers to the job site
What is the best action for a contractor to take concerning a project that is one month behind schedule due to incomplete and late architectural drawings?
Updated the schedule and notify the owner of the options and associated costs
A project bid comes in over budget. The architect might request proposal from some, or all of the bidders to suggest ways to reduce costs without degrading the quality of the project. What term describes this accurately?
Value engineering
The baseline schedule or target should be maintained in order to analyse the?
Variance in progress of the project
The "A C" stamped on a plywood panel demonstrates
Veneer grade
Which of the following is MOST important when preparing a bid for site work?
Verifying conditions by means of site visit
The most common type of large scale reinforced brick masonry wall is characterized by
Vertical reinforcing bars grouted into hollow bricks
Which of the following is required by prevailing wage provisions of the Davis-Beacon Act?
Wages paid must not be less than wages prevailing in the locality.
Which of the following is an expressed or implied promise to the owner that the product meets specifications and the contractor will remedy any defects?
Warranty
The most important reason that knowledge and understanding of cash flow is critical to construction company management is to assure
What the company maintains is liquidity
The critical path of a schedule follows activities
With total float values equal to zero
If a project is delayed, how quickly must the contractor give notice to the owner as outlined in the AIA A201 General Conditions?
Within 21 days of the first occurrence
Which of the following provides a framework for organizing the activities that make up a project?
Work breakdown structure
Which of the following must be in evidence for a contractor to be in compliance with OSHA?
Written safety plan
when a person has agreed to perform certain work and, in turn, engages others to perform a portion of the work which is included in the original contract, the agreement with the third party is called a
a subcontract
How should a constructor establish the field staffing for a project?
by utilization of past experience and schedule requirements
A project milestone generally represents
completion of a group of activities
What action should a supervisor take if, during a site walkthrough, the crew supervisor observes an unsecured plastic 5 gallon container containing an unidentified liquid?
investigate and determine its potential hazardous nature, label it, and review hazardous materials communication procedures with the crew
Which of the following is most characteristic of dewatering a construction site?
involves lowering the water table within a construction site
The Uniform Commercial Code (UCC) is an area of law that applies to
material suppliers
The purpose of nail protection installed on wood framing is to
prevent a fastener from penetrating pipe or wiring
The most appropriate equipment for compacting a fill made of clay soil is a
rubber-tired roller