CH 7

अब Quizwiz के साथ अपने होमवर्क और परीक्षाओं को एस करें!

Using simplified percentage complete amounts for a one-year project with weekly reporting and an average task or work packet size of one week, you can expect about a(n) ____ percent error rate

1

Three separate surveys of software project cost overruns found that the average cost overrun for all of the projects in their survey samples (not just unsuccessful projects) were ____ percent

33-34

The Standish Group's CHAOS studies reported an average cost overrun for unsuccessful IT projects ranged from 180 percent in 1994 to ____ percent in 2002.

43

The Standish Group's CHAOS studies reported an average cost overrun for unsuccessful IT projects ranged from 180 percent in 1994 to ____ percent in 2004

56

The ____ is the total direct and indirect costs incurred in accomplishing work on an activity during a given period.

AC

____ use the actual cost of a previous, similar project as the basis for estimating the cost of the current project.

Analogous estimates

____ involve estimating individual work items or activities and summing them to get a project total.

Bottom-up estimate

The ____ is the ratio of earned value to actual cost and can be used to estimate the projected cost of completingthe project

CPI

____ is the earned value minus the actual cost

CV

The ____ is an estimate of what it will cost to complete the project based on performance to date.

EAC

The ____ is an estimate of the value of the physical work actually completed.

EV

Variances are calculated by subtracting the actual cost or planned value from ___

EV

____ involves developing an approximation or estimate of the costs of the resources needed to complete a project.

Estimating costs

t/f A definitive estimate should be the least accurate of the three types of estimates

F

t/f Although information technology projects have a poor track record in meeting project goals, they have a goodtrack record in meeting budget goals

F

t/f Databases are a common tool for cost estimating, cost budgeting, and cost control

F

t/f Direct costs cannot be directly attributed to a certain project.

F

t/f If cost variance is a positive number, it means that performing the work cost more than planned.

F

t/f If the cost performance index is less than one or less than 100 percent, the project is under budget

F

t/f In an earned value chart, when the actual cost line is right on or above the earned value line, costs are less thanor equal to planned

F

t/f Learning curve theory does not apply to the amount of time it takes to complete some tasks.

F

t/f Organizations have a history of spending too much money in the early phases of information technology projects.

F

t/f Parametric models are least reliable when historical information was used to create the model.

F

t/f Preparing cost estimates is a job for accountants

F

t/f The WBS is not a required input when developing a cost estimate.

F

t/f The people who develop software cost estimates often have a great deal of experience with cost estimation

F

t/f There does not need to be a change control system to define procedures for changing the cost baseline

F

t/f When deciding what projects to invest in or continue, you should include sunk costs.

F

t/f When developing an estimate for a large software project, estimates cannot be made before clear systemrequirements have been produced

F

t/f When justifying investments in new information systems and technology, the focus should only be on revenuesor expenses.

F

states that when many items are produced repetitively, the unitcost of those items decreases in a regular pattern as more units are produced

Learning curve theory

allows you to see a big-picture view of the cost of a projectthroughout its life cycle.

Life cycle costing

considers the total cost of ownership, or development plus supportcosts, for a project.

Life cycle costing

The ____ is that portion of the approved total cost estimate planned to be spent on an activity during a given period

PV

uses project characteristics in a mathematical model to estimate project costs

Parametric modeling

The ____ is the ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity.

RP

The ____ is the ratio of actual work completed to the percentage of work planned to have been completed at anygiven time during the life of the project or activity.

RP

The ____ is the ratio of earned value to planned value and can be used to estimate the projected time to completethe project.

SPI

___ is the earned value minus the planned value

SV

t/f A large percentage of total project costs are often labor costs

T

t/f Any new technology or business process is untested and has inherent risks

T

t/f Cost budgeting provides information for project funding requirements.

T

t/f Estimates are usually done at various stages of a project and should become more accurate as time progresses

T

t/f Every cost estimate is unique

T

t/f If a project manager gets sick for two weeks or an important supplier goes out of business, management reservecould be set aside to cover the resulting costs

T

t/f Many projects that are started never finish because of cost management problems.

T

t/f Many projects, particularly information technology projects, do not have good planning information, sotracking performance against a plan might produce misleading information

T

t/f Most organizations have a well-established process for preparing budgets

T

t/f Project managers must conduct cash flow analysis to determine net present value

T

t/f ROM estimates can be referred to as a ballpark estimate, a guesstimate, a swag, or a broad gauge

T

t/f The cost management plan is part of the overall project management plan

T

t/f The formulas for variances and indexes start with EV, the earned value.

T

_________ ____________ and SPI less than one or less than 100 percentindicate problems.

_Cost performance index (CPI)

costs are often much higher for contractors

_________Labor___________

In practice, many people find that using a combination or hybrid approach involving analogous, bottom up,and/or parametric modeling provides the best

_cost estimates

After you total the EV, AC, and PV data for all activities on a project, you can use the CPI and ______________ __________________ to project how much it will costand how long it will take to finish the project based on performance to date.

_schedule performance index (SPI)__

is the original project plan plus approved changes.

baseline

____ is used to allocate money into an organization's budget

budgetary estimate

____ is a method for determining the estimated annual costs and benefits for a project and the resulting annualcash flow.

cash flow analysis

____ allow for future situations that may be partially planned for

contingency reserves

The project management plan, project funding requirements, work performance data, and organizational process assets are inputs for the process of ____

controlling costs

A ____ is a time-phased budget that project managers use to measure and monitor cost performance

cost baseline

In addition to providing input for budgetary estimates, cost budgeting provides a(n) _______ __________

cost baseline

The main goal of the ____ process is to produce a cost baseline for measuring project performance and projectfunding requirements.

cost budgeting

The main outputs of the __________ __________ process are a cost performance baseline, project funding requirements, and project document updates

cost budgeting

____ involves allocating the overall cost estimate to individual work items to establish a baseline for measuring performance

cost budgeting

The main outputs of the __________ __________ process are work performance measurements, budget forecasts, organizational process asset updates, change requests, project management plan updates, and project document updates.

cost control

The main outputs of the ___________________ process are activity cost estimates, basis of estimates, and project document updates

cost estimating_

Using good __________ ___________ can change the false perception that costs growand failures are to be expected

cost management ____

is a document that describes how the organization willmanage cost variances on the projec

cost management plan

A ____ is used for making many purchasing decisions for which accurate estimates are required and for estimating final project costs

definitive estimate

If the cost estimate will be the basis for contract awards and performance reporting, it should be a ____ and asaccurate as possible

definitive estimate

____ involves allocating the overall cost estimate to individual work items to establish a baseline for measuring performance

determining the budget

14. Project managers should focus on ____, since they can control them.

direct costs

Project managers should focus on ____, since they can control them

direct costs

It's important for the team to _________ ___________ assumptions they made when developing thecost baseline and have several experts review it.

document

Since organizations depend on reliable information technology, there are also huge costs associated with ___

downtime

____ is a project performance measurement technique that integrates scope, time, and cost data.

earned value management

The cost performance index can be used to calculate the

estimate at completion(EAC)

7. The WBS is not a required input to the cost budgeting process.

false

Databases are a common tool for cost estimating, cost budgeting, and cost control.

false

If the cost performance index is less than one or less than 100 percent, the project is under budget.

false

Learning curve theory does not apply to the amount of time it takes to complete some tasks.

false

Preparing cost estimates is a job for accountants.

false

Information technology project managers need to be able to present and discuss project information in ________ ____________ terms as well as in technical terms

financial

Tom DeMarco, a well-known author on software development, suggests ____ reasons for the inaccuracies of many information technology project cost estimates and some ways to overcome them.

four

____ are costs that are not directly related to the products or services of the project, but are indirectly related to performing the project.

indirect costs

costs or benefits are costs or benefits that are difficult to measure inmonetary terms

intangible

___ helps you develop an accurate projection of a project's financial costs and benefits.

life cycle costing

____ allow for future situations that are unpredictable

management reserves

has many cost management features to help you enter budgeted costs, set a baseline, enter actuals, calculate variances, and run various cost reports.

microsoft project

In general, ________ ____________ numbers for cost and schedule variance indicate problems in thoseareas

negative

A(n) ____ might provide an estimate of $50 per line of code for a software development project based on the programming language the project is using, the level of expertise of the programmers, the size and complexityof the data involved, and so on

parametric model

Many organizations now collect and control an entire suite of projects or investments as one set of interrelatedactivities in one place, called a(n

portfolio

____ is the ratio of revenues to profits

profit margin

__ are revenues minus expenditures.

profits

____ includes the processes required to ensure that a project team completes a project within an approved budget

project cost management

____, with assistance from financial experts in their organizations, should create estimates of the costs and benefits of the project for its entire life cycle

project managers

A ____ is done very early in a project or even before a project is officially started

rough order of magnitude estimate

A ____ provides an estimate of what a project will cost.

rough order of magnitude estimate

____ is done very early in a project or even before a project is officially started

rough order of magnitude estimate

____ provides an estimate of what a project will cost

rough order of magnitude estimate

cost is money that has been spent in the past

sunk

____ should be forgotten.

sunk costs

13. ____ are those costs that an organization can easily measure in dollars.

tangible costs

____ are those costs that an organization can easily measure in dollars

tangible costs

6. The cost management plan is part of the overall project management plan.

true

Any new technology or business process is untested and has inherent risks

true

Project managers must conduct cash flow analysis to determine net present value

true

ROM estimates can be referred to as a ballpark estimate, a guesstimate, a swag, or a broad gauge

true

t is helpful to analyze the total dollar value as well as the percentage of the total amount for each major __________ ___________________ category.

work breakdown structure (WBS)_


संबंधित स्टडी सेट्स

Chapter 1 Understanding Healthcare Settings

View Set

Chapter 15: Respiratory Emergencies

View Set

Ch 41: Management of Patients with Musculoskeletal Disorders (3)

View Set

expert session chapter 8 email marketing in the digital age

View Set

Health Assessment EAQ's (JG Orig)

View Set

Chapter 12 Spirituality and Religious Practices

View Set

Chapter 49: Endocrine Problems Lewis: Medical-Surgical Nursing, 10th Edition

View Set

Ch. 8 Microbiology Assignment Questions

View Set