Chapter 11
12. _____ are predefined actions that the project team will take if an identified risk event occurs. a. Secondary risks b. Workarounds c. Contingency plans d. Management reserves
c. Contingency plans
26. _____ involves allocating ownership of the risk to another party. a. Risk exploitation b. Risk sharing c. Risk enhancement d. Risk acceptance
b. Risk sharing
17. _____ are/is a qualitative risk analysis tool that maintains an awareness of risks throughout the life of a project in addition to identifying risks. a. SharePoint portal b. Probability/impact matrices or charts c. Expectations management matrix d. Top Ten Risk Item Tracking
d. Top Ten Risk Item Tracking
3. A _____ person achieves a balance between risk and payoff. a. risk-seeking b. risk-averse c. risk-fearing d. risk-neutral
d. risk-neutral
19. _____ analysis simulates a model's outcome many times to provide a statistical distribution of the calculated results. a. Sensitivity b. Systems c. Monte Carlo d. NPV
c. Monte Carlo
27. _____ involves changing the size of the opportunity by identifying and maximizing key drivers of the positive risk. a. Risk exploitation b. Risk sharing c. Risk enhancement d. Risk acceptance
c. Risk enhancement
5. _____ involves determining which risks are likely to affect a project and documenting the characteristics of each. a. Identifying risks b. Planning risk management c. Performing qualitative risk analysis d. Performing quantitative risk analysis
a. Identifying risks
6. _____ involves prioritizing risks based on their probability and impact of occurrence. a. Performing qualitative risk analysis b. Identifying risks c. Planning risk responses d. Performing quantitative risk analysis
a. Performing qualitative risk analysis
4. _____ involves deciding how to approach and plan the risk management activities for the project. a. Identifying risks b. Planning risk management c. Performing qualitative risk analysis d. Performing quantitative risk analysis
b. Planning risk management
8. _____ involves taking steps to enhance opportunities and reduce threats to meeting project objectives. a. Performing quantitative risk analysis b. Planning risk responses c. Controlling risk d. Performing qualitative risk analysis
b. Planning risk responses
28. _____ applies to positive risks when the project team cannot or chooses not to take any actions toward a risk. a. Risk enhancement b. Risk acceptance c. Risk sharing d. Risk exploitation
b. Risk acceptance
15. A(n) _____ represents decision problems by displaying essential elements, including decisions, uncertainties, causality, and objectives, and how they influence each other. a. risk breakdown structure b. influence diagram c. process flow chart d. work breakdown structure
b. influence diagram
1. Risk utility rises at a decreasing rate for a _____ person. a. risk-seeking b. risk-averse c. risk-neutral d. risk-indifferent
b. risk-averse
20. What is the first step in a Monte Carlo analysis? a. Determine the probability distribution of each variable. b. For each variable, such as the time estimate for a task, select a random value based on the probability distribution for the occurrence of the variable. c. Assess the range for the variables being considered. d. Run a deterministic analysis or one pass through the model using the combination of values selected for each one of the variables
c. Assess the range for the variables being considered.
7. _____ involves numerically estimating the effects of risks on project objectives. a. Performing qualitative risk analysis b. Planning risk responses c. Identifying risks d. Performing quantitative risk analysis
d. Performing quantitative risk analysis
24. _____ involves reducing the impact of a risk event by reducing the probability of its occurrence. a. Risk avoidance b. Risk acceptance c. Risk transference d. Risk mitigation
d. Risk mitigation
29. _____ risks refer to those that are direct results of implementing risk responses. a. Architectural b. Primary c. Residual d. Secondary
d. Secondary
22. _____ involves eliminating a specific threat, usually by eliminating its causes. a. Risk avoidance b. Risk acceptance c. Risk transference d. Risk mitigation
a. Risk avoidance
25. _____ involves doing whatever you can to make sure the positive risk happens. a. Risk exploitation b. Risk sharing c. Risk enhancement d. Risk acceptance
a. Risk exploitation
30. _____ are unplanned responses to risk events used when project teams do not have contingency plans in place. a. Workarounds b. Fallback plans c. Contingency plans d. Triggers
a. Workarounds
18. A(n) _____ is a diagramming analysis technique used to help select the best course of action in situations in which future outcomes are uncertain. a. decision tree b. activity-on-arrow c. workaround d. backward pass
a. decision tree
10. Identifying risks is a subprocess of the _____ process of project risk management. a. planning b. executing c. monitoring and controlling d. closing
a. planning
11. Performing qualitative and quantitative risk analyses are subprocesses of the _____ process of project risk management. a. planning b. executing c. monitoring and controlling d. closing
a. planning
2. Those who are _____ have a higher tolerance for risk, and their satisfaction increases when more payoff is at stake. a. risk-seeking b. risk-averse c. risk-neutral d. risk-indifferent
a. risk-seeking
21. A _____ is a technique used to show the effects of changing one or more variables on an outcome. a. sensitivity analysis b. decision tree c. Monte Carlo analysis d. systems analysis
a. sensitivity analysis
9. _____ involves monitoring identified and residual risks, identifying new risks, carrying out risk response plans, and evaluating the effectiveness of risk strategies throughout the life of the project. a. Performing quantitative risk analysis b. Planning risk responses c. Controlling risk d. Performing qualitative risk analysis
c. Controlling risk
23. _____ involves shifting the consequence of a risk and responsibility for its management to a third party. a. Risk avoidance b. Risk acceptance c. Risk transference d. Risk mitigation
c. Risk transference
16. The _____ lists the relative probability of a risk occurring and the relative impact of the risk occurring. a. Top Ten Risk Item Tracking chart b. requirements traceability matrix c. probability/impact matrix d. expectations management matrix
c. probability/impact matrix
13. Unenforceable conditions or contract clauses and adversarial relations are risk conditions associated with the project _____ management knowledge area. a. integration b. quality c. procurement d. human resources
c. procurement
14. _____ is a fact-finding technique that can be used for collecting information in face-to-face, phone, e-mail, or instant-messaging discussions. a. Brainstorming b. Monte Carlo analysis c. The Delphi technique d. Interviewing
d. Interviewing