INS475 Midterm True or False Questions

अब Quizwiz के साथ अपने होमवर्क और परीक्षाओं को एस करें!

The importance of stakeholders' needs and expectations is limited to the beginning of a project.

. False

Questions about how a team will track schedule performance is related to a project's scope

False

Responsibility assignment matrices and project organizational charts are examples of tools used in procurement management

False

Start-to-finish relationships are the most frequently used dependencies between activities

False

The burndown chart is a Scrum created artifact that provides a list of features prioritized by business value

False

The kick-off meeting is always held before the business case and project charter are completed.

False

The only responsibility of a project manager is to meet the specific scope, time, and cost goals of a project

False

The output of the stakeholder management strategy results is a project charter.

False

The project organizational structure is the most efficient choice for most IT projects.

False

The team members of a virtual team are all of the same nationality

False

To be a successful manager, the only skills an IT project manager needs to possess are excellent technical skills.

False

Network diagrams are the preferred technique for showing activity sequencing

True

Project managers in matrix organizations have staff from various functional areas working on their projects

True

Some organizations initiate projects using a contract in place of a project charter

True

Standards and guidelines to follow when performing project management must be devised by top management

True

The introduction of new software makes basic tools, such as Gantt charts and network diagrams, inexpensive and easy to create

True

Project managers should lead projects in isolation in order to truly serve the needs of the organization.

False

Project scope statements must include the project boundaries, constraints, and assumptions

False

A disadvantage of using Gantt charts is that they do not provide a standard format for displaying planned project schedule information.

False

Agile methods are used when deliverables have a low degree of change

False

Corrective actions reduce the probability of negative consequences associated with project risks, while preventive actions should result in improvements in project performance

False

Decisions and actions taken in one knowledge area at a certain time rarely affect other knowledge areas

False

In a Gantt chart, thick black bars represent milestones achieved in a project

False

In order to be realistic, a project manager should always set discrete goals instead of a range of objectives.

False

Individual projects always address strategic goals whereas portfolio management addresses tactical goals

False

It is much more expensive to make major changes to a project during the earlier phases.

False

Milestones are easy to achieve and are always achieved through one main activity.

False

. Change requests are always made in writing.

True

A schedule management plan includes information which describes the format and frequency of schedule reports required for the project

True

A sprint review is a meeting in which the team demonstrates to the product owner what it has completed during the sprint.

True


संबंधित स्टडी सेट्स

Chapter 5-Genomes, Proteomics, and Systems Biology

View Set

spanish 9 test vocab and gramática

View Set

Vascular and MS Study Guide Questions

View Set

Community Health Test 2 (Ch. 9, 11, 14, 15, 19, 20, & 26)

View Set

Chapter 12: The Lymphatic System

View Set

Julius Caesar Act III Study Questions

View Set