ISQS 4350 - TEST 2**

अब Quizwiz के साथ अपने होमवर्क और परीक्षाओं को एस करें!

Question 10 5 out of 5 points The lowest element in the hierarchical breakdown of the WBS is ________. Answers: a. an object b. a lowest sub deliverable c. a work package d. a cost account e. a work product

c

Question 12 0 out of 4 points ________ is a deterministic scheduling technique while ________ is probabilistic, with ________ being most widely used in commercial software. Answers: a. PERT | CPM | PERT b. PERT | CPM | CPM c. CPM | PERT | CPM d. CPM | CPM | PERT e. CPM | PERT | PERT

c

Question 16 5 out of 5 points Which of the following costs has to do with appraisal? Answers: a. Interviewing costs b. Testing and inspection costs c. Rework costs d. Liability costs e. Training costs

b

Question 7 5 out of 5 points All of the following are part of the Agile Project Management model except ________. Answers: a. embrace change b. self organized project teams c. design up front d. flexibility e. high uncertainty

c

Question 1 5 out of 5 points At the completion of an agile iteration a ________. Answers: a. new, bug-free functionality is developed/deployed to the customer b. a new piece of functionality is developed c. a new phase of the development lifecycle is completed d. All of the functionality associated with a product is developed. e. Only a. and c. are correct.

a

Question 1 5 out of 5 points The best time to do crashing is ________. Answers: a. towards the end of the planning phase b. towards the end of the monitoring phase c. towards the end of the executing phase d. towards the end of the initiating phase e. towards the end of the closing phase

a

Question 10 5 out of 5 points Which of the following is not something that we ordinarily estimate? Answers: a. Quality b. Resources c. Time d. Cost e. Both b. and c. are correct.

a

Question 11 4 out of 4 points In ProjectLibre, by default any link between tasks (activities) is assumed to be ________. Answers: a. Finish-to-Start b. Start-to-Finish c. Start-to-Start d. There is no default setting in ProjectLibre. e. Finish-to-Finish

a

Question 11 5 out of 5 points A ________ is a standard of measurement in quality management. Answers: a. metric b. None of these alternatives is correct. c. merge d. matrix e. milestone

a

Question 15 4 out of 4 points According to Larson and Gray chapter 8, cost estimates are not a budget until ________. Answers: a. budgets have been time-phased b. resources have been assigned c. costs have been determined d. All of these alternatives are correct. e. Only a. and c. are correct.

a

Question 18 5 out of 5 points Suppose you had decided to use a SCRUM methodology to breakup the various components of the software system. Which of the following components which you conduct sprints on first? Answers: a. backbone structure b. minor functional components c. user interfaces d. major functional components e. small details

a

Question 18 5 out of 5 points ________ is the degree to which a system performs its intended function. Answers: a. Functionality b. Validity c. None of these alternatives is correct. d. Maintainability e. Reliability

a

Question 19 5 out of 5 points A big picture view of the cost of a project over its entire existence is ________. Answers: a. life cycle costing b. cost account c. networking view d. WBS e. JAD costing

a

Question 2 5 out of 5 points The ability of 911 emergency systems to identify the caller's phone number and location are considered to be a ________. Answers: a. technical requirement b. project limit c. project deliverable d. milestone e. project exclusion

a

Question 3 5 out of 5 points The ________ backlog represents the amount of work the spring team commits to complete during the next sprint or iteration. Answers: a. sprint b. developer c. product d. iteration e. scrum

a

Question 3 5 out of 5 points The first step in creating the total content and substance of a project is to ________. Answers: a. define the project scope b. establish project priorities c. determine the required completion date d. verify the budget available e. assign team members to work on the project

a

Question 3 5 out of 5 points The purpose of top-down estimation is not for ________. Answers: a. definitive purposes b. budgetary purposes c. planning purposes d. strategic purposes e. accuracy purposes

a

Question 4 5 out of 5 points "To construct a high-quality, custom home with three bedrooms, two baths and a two-car garage within five months at costs not to exceed $250,000" is best classified as ________. Answers: a. an objective b. an exclusion c. a milestone d. a limit e. a deliverable

a

Question 6 5 out of 5 points The ________ process is often associated with the technical tools and techniques of quality management, such as Pareto charts, quality control charts, and statistical sampling. Answers: a. quality control b. quality planning c. quality assurance d. None of these alternatives is correct. e. quality certification

a

Question 6 5 out of 5 points Which of the following lifecycle models is a predictive one? Answers: a. Waterfall b. Agile c. Scrum d. Extreme e. Iterative

a

Question 8 5 out of 5 points A ________ is the tool used to assist in making project trade-offs between schedule, budget, and performance objectives. Answers: a. project priority matrix b. work package c. work breakdown structure d. criterion matrix e. responsibility matrix

a

Question 8 5 out of 5 points Payback occurs when ________. Answers: a. the net cumulative benefits equal the net cumulative costs b. the net cumulative benefits minus costs equal one c. the net costs are lower than the cumulative benefits d. the cumulative benefits are double the cumulative costs e. None of these alternatives is correct.

a

Question 9 5 out of 5 points Which of the following is not something that we ordinarily estimate? Answers: a. Quality b. Resources c. Time d. Cost e. Both b. and c. are correct.

a

Question 9 5 out of 5 points Which of the following is responsible for rapid deployment of the software after each iteration? a. Jenkins b. Project leader c. Product owner d. Release burndown chart e. DevOps

a

Question 18 0 out of 5 points Consider the following table of activities A through G in which A is the start node and G is the stop node. Activity Duration (days) Predecessor A 5 -- B 8 A C 7 A D 6 A E 9 B, C, D F 10 B, C, D G 5 E, F Draw the network above to determine the following. What is the duration of the critical path? What is the late start time for activity E (how late can activity E start?)? a. 28 | 14 b. 28 | 12 c. 29 | 14 d. 29 | 15

a Response Feedback: Incorrect. A path is a sequence of activities that takes you from the start node (activity) through the stop node (activity). All paths through the network have to be completed. There are six paths through this network. The one that takes the longest to complete is the one that determines the duration of the project. The longest path is, by definition, the critical path. All activities on the critical path are called 'critical activities.' All critical activities have zero slack. The duration of the critical path is also the early finish time and late finish time of the stop node. The backward pass determines late finish and late start times for all activities. A backward pass starts with the late finish time (which, by convention, is always equal to the early finish time) of the stop node and works backward. The late finish time for activity E is 23. We subtract the duration of activity E from 23 to arrive at the late start time for activity E, which is 14.

Question 14 5 out of 5 points A project leader's boss has told Jonathan that his project is very important. If the critical path is delayed, he will be given whatever he needs to get the project back on schedule. His project is classified as ________ constrained. Answers: a. time b. cost c. resource d. performance e. quality

a Response Feedback: Correct. A time-constrained project is one that must be completed by an imposed date. If required, resources can be added to ensure the project is completed by a specific date. Although time is the critical factor, resource usage should be no more than is necessary and sufficient.

Question 20 5 out of 5 points Select the most accurate statement with regards to the Critical Path Method (CPM). Answers: a. It assumes that activities are independent of one another, with clearly defined start and finish dates. b. It accounts for the interruptions that may affect an activity between the start and the finish times. c. It allows us to investigate the effects of uncertainty of activity times on project completion times. d. It uses the variance in the critical path activities to evaluate the risks associated with project completion times.

a Response Feedback: Correct. CPM assumes that activities are independent of one another, with clearly defined start and finish dates. Understanding the critical path is vital to managing a project because any delays of activities on the critical path will delay the entire project.

• Question 12 5 out of 5 points Which PMBOK activity is responsible for determining activity resource requirements, and for determining a resource breakdown structure? Answers: a. Estimate activity resources b. Estimate activity durations c. Develop schedule d. Define activities e. Plan schedule management

a Response Feedback: Correct. The process known as Estimate activity resources determines resource requirements, and creates a resource breakdown structure.

Question 3 5 out of 5 points The district magistrate of Arkham City has decided to rebuild the busiest road in the city. She plans to close the street for the duration of the work, causing immense inconvenience to the people who typically use the road. The project has 3 parallel paths defined as the following: Path A-B-C-H will take 16 days. Path A-F-G-H will take 22 days. Path A-D-E-H will take 30 days. Given the information on hand, which of the following statements is true? Answers: a. Path A-D-E-H is the critical path. b. Path A-F-G-H has the largest slack time. c. Path A-F-G-H is the critical path. d. Path A-D-E-H has the largest slack time.

a Response Feedback:Correct. In the given scenario, path A-D-E-H is the critical path. The critical path is the sequence of activities that takes the longest time and defines the total project completion time.

Question 1 5 out of 5 points ________ is a deterministic diagramming technique used to predict total project duration. Answers: a. PERT b. CPM c. A Gantt chart d. EVA e. Crashing

b

Question 10 5 out of 5 points The advantage that a PERT representation of a project schedule over a CPM representation is that a PERT representation ________. Answers: a. is easier to calculate b. calculates probabilities of completing milestones by their completion dates c. gives automatic valuations of ES, EF, LS, LF and SLACK d. enables fast determination of total project duration and the critical path e. All of these alternatives are correct.

b

Question 11 5 out of 5 points As a rule of thumb, the time to design, document and code a module equals ________. Answers: a. the time to analyze it b. the time to test it c. the time to integrate it d. the time to conceptualize it e. None of these alternatives is correct.

b

Question 11 5 out of 5 points If your team's task was to develop an AI pattern recognition engine based on King Sung Fu's formulas/algorithms developed 40 years ago, which model would you likely use? Answers: a. Extreme b. Waterfall c. Iterative d. Scrum e. Agile

b

Question 11 5 out of 5 points Which of the following is false? Answers: a. Only one task in a project should be without a successor. b. Always assign resources to summary tasks c. Only one task in a project should be entered without a predecessor. d. Avoid using too many specific date constraints on tasks e. Avoid creating predecessor/successor task relationships between summary tasks

b

Question 12 5 out of 5 points Estimating processes occur within two knowledge areas. They are: Answers: a. Time, Quality b. Time, Cost c. Procurement, Risk d. Cost, Quality e. Scope, Time

b

Question 12 5 out of 5 points Suppose you had decided to use a SCRUM methodology to breakup the various components of the software system. Which of the following components which you conduct sprints on second? Answers: a. small details b. user interfaces c. major functional components d. backbone structure e. minor functional components

b

Question 12 5 out of 5 points ________ means the project's processes and products meet written specifications. Answers: a. None of these alternatives is correct. b. Conformance to requirements c. Fitness for use d. Project feasibility e. Benchmarking

b

Question 13 5 out of 5 points Which is more expensive and costly to the firm? Answers: a. Over-estimation b. Under-estimation

b

Question 14 4 out of 4 points By default ProjectLibre assumes unspecified task durations are ________. Answers: a. zero duration b. one day in duration, followed by a ? c. one unit in duration, followed by a ? d. simply a ? e. Both a. and d. are correct.

b

Question 15 5 out of 5 points Which of the following is not one of the basic classifications of project priorities? Answers: a. Cost b. Profit c. Time d. Performance e. All of these are basic classifications.

b

Question 15 5 out of 5 points ________ analysis is a method of calculating the expected net monetary gain or loss from a project by discounting all expected future cash inflows and outflows to the present point in time. Answers: a. Cost of capital b. Net present value c. Cash flow d. Payback e. Both c. and d. are correct.

b

Question 16 5 out of 5 points Jackson has just been assigned a project to develop a new advertising campaign for an established product. His first step should be to ________. Answers: a. determine the required completion date b. define the project scope c. establish project priorities d. assign team members to work on the project e. verify the budget available

b

Question 18 4 out of 4 points Which of the following statements is false? Answers: a. Probability distributions for PERT activity durations are represented by use of the Beta distribution. b. The critical path is the series of activities that determine the earliest time by which a project can be started. c. A forward pass through a project network diagram determines the early start and early finish dates for each activity. d. Crashing is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost. e. Both a. and d. are false statements.

b

Question 18 5 out of 5 points Estimation that is performed immediately before execution and often uses a bottom-up technique referred to as ________. Answers: a. budgetary estimation b. definitive estimation c. analogous estimation d. low-level developer estimation e. ubiquitous estimation

b

Question 18 5 out of 5 points If a project criterion indicates that the project must meet a specific date, that criterion is classified as ________. Answers: a. accepted b. constrained c. enhanced d. limited e. fixed

b

Question 19 4 out of 4 points In ProjectLibre, the tool that is used to establish sequencing among the activities is the ________. Answers: a. indent arrow on the task tab b. link tool on the task tab c. assign resources tool on the task tab d. insert tool under the task tab e. Both a. and c. are correct.

b

Question 19 5 out of 5 points Anna has just been given a project that has a specific target date. After discussion with top management she finds that while the date is important the cost is more important and a slip in delivery would be acceptable if required to meet the cost targets. The target date is best classified as ________. Answers: a. enhance b. accept c. optional d. constrain e. limit

b

Question 19 5 out of 5 points Iterations are short time frames ("time boxes") that typically last from ________. Answers: a. 7-12 weeks b. 1-4 weeks c. 4-7 weeks d. 1-2 weeks e. 1-4 days

b

Question 2 5 out of 5 points Which of the following titles in a typical scrum arrangement is the project manager? Answers: a. Scrum developer b. Scrum master c. Scrum methodologist d. Product owner e. Scrum leader

b

Question 20 4 out of 4 points Which of the following processes in project time management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables? Answers: a. Developing the schedule b. Defining activities c. Sequencing activities d. Controlling schedule e. Estimating activity durations

b

Question 21 4 out of 4 points Almost all knowledge areas have a ________ process and a ________ process. Answers: a. plan | schedule b. plan | control c. estimate | control d. plan | estimate e. estimate | schedule

b

Question 22 4 out of 4 points Which of the following is a way to improve quality on the front-end of the development lifecycle? Answers: a. Unit testing b. Walkthroughs c. User acceptance testing d. Integration testing e. Regression testing

b

Question 23 4 out of 4 points In project time management, which of the following processes involve calculating the number of work periods that are needed to complete individual tasks? Answers: a. Controlling schedule b. Estimating activity durations c. Defining activities d. Planning schedule management e. Sequencing activities

b

Question 24 4 out of 4 points If the time units are months, effort is measured in ________ whereas duration is measured in _______. Answers: a. dollars, month-dollars b. man-months, month c. months, man-months d. month-dollars, dollars e. None of the alternatives is correct.

b

Question 3 4 out of 4 points According to Larson and Gray chapter 8, project network times are not a schedule until ________. Answers: a. budgets have been time-phased b. resources have been assigned c. costs have been determined d. All of these alternatives are correct. e. Only a. and c. are correct.

b

Question 3 5 out of 5 points Which of the following statements is false? Answers: a. Probability distributions for PERT activity durations are represented by use of the Beta distribution. b. The critical path is the series of activities that determine the earliest time by which a project can be started. c. A forward pass through a project network diagram determines the early start and early finish dates for each activity. d. Crashing is a technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost. e. Both a. and d. are false statements.

b

Question 4 5 out of 5 points Estimating processes occur within what process group, what lifecycle phase? Answers: a. Initiating b. Planning c. Executing d. Monitoring and controlling e. Closing

b

Question 6 5 out of 5 points The standard deviation of a task whose optimistic time is 31 and whose most likely time is 72 and whose pessimistic time is 123 is ________. Answers: a. 13.33 b. 15.33 c. 14.56 d. 8.50 e. None of these alternatives is correct.

b

Question 7 5 out of 5 points ________ generates ideas for quality improvements by comparing specific project practices or product characteristics to those of other projects or products within or outside the performing organization. Answers: a. Prototyping b. Benchmarking c. None of these alternatives is correct. d. Systems thinking e. Mind mapping

b

Question 8 5 out of 5 points A typical amount to be added to budgets and schedules for such things as holidays, sick days, snow days, company meetings, training days, etc., is ________. Answers: a. 5% b. 10% c. 15% d. 20% e. 25%

b

Question 8 5 out of 5 points Which of the following statements is false? Answers: a. A resource breakdown structure is a hierarchical structure that identifies the project's resources by category and type. b. Duration and effort are synonymous terms. c. A three-point estimate in PERT includes an optimistic, a most likely, and a pessimistic estimate. d. A Gantt chart is a common tool for displaying project schedule information on a timeline. e. Both b. and d. are false statements.

b

Question 9 5 out of 5 points Which of the following estimates is typically used for making decisions two to five years out? Answers: a. Estimation b. Strategic estimation c. Budgetary estimation d. Definitive estimation e. Accommodation of the customer

b

Question 17 5 out of 5 points A backhoe that Susan needs on her project has been scheduled on another project. This is a ________ constraint. Answers: a. information b. equipment c. materials d. people e. working capital

b Response Feedback: Correct. Equipment is usually presented by type, size, and quantity. In some cases equipment can be interchanged to improve schedules, but this is not typical. Equipment is often overlooked as a constraint. The most common oversight is to assume the resource pool is more than adequate for the project.

Question 15 5 out of 5 points Which of the following are discrete tasks which require resources and time, within the context of projects? Answers: a. Processes b. Activities c. Schedules d. Value chains

b Response Feedback: Correct. In the context of projects, activities are discrete tasks that consume resources and time.

Question 16 5 out of 5 points Wayne needs to order memory chips needed to continue his project. The memory chips are needed now bu the supplier won't be able to deliver them until next week. This is an example of a ________ constraint. Answers: a. equipment b. materials c. information d. people e. working capital

b Response Feedback: Correct. Material availability and shortages have been blamed for the delay of many projects. When it is known that a lack of availability of materials is important and probable, materials should be included in the project network plan and schedule.

Question 4 5 out of 5 points The ________ calculates the critical path and determines how long an activity can be delayed without delaying the project. Answers: a. parallel pass b. backward pass c. forward pass d. concurrent pass

b. Response Feedback:Correct. The backward pass determines which activities represent the critical path. The critical path is the longest path in the network which, when delayed, will delay the project and determines how long the activity can be delayed without delaying the project.

Question 12 5 out of 5 points Which of the following rules is part of the crashing heuristic? Answers: a. Crash only non-critical activities b. Pick the un-crashed activity with the largest crash cost per day as the next activity to crash c. Always crash the activity to its minimum duration if there is sufficient budget to do so and if that does not cause the associate path to no longer be critical d. All of these alternatives are legitimate crashing rules. e. Only a. and b. are legitimate crashing rules.

c

Question 13 5 out of 5 points Which of the following is not part of the Agile Alliance manifesto that declared four core values? Answers: a. Responding to change over following a plan. b. Individuals and interactions over processes and tools. c. Creating an end user survey. d. Working software over comprehensive documentation. e. Customer collaboration over contract negotiation.

c

Question 14 5 out of 5 points Analogous estimating amounts to ________. Answers: a. bottom-up estimation b. expert judgment c. use of a past similar project d. All of these alternatives are correct. e. Only b. and c. are correct.

c

Question 14 5 out of 5 points Top management prefers ________ development models over ________ models because they know up front how much cost and time are required. Answers: a. creative | predictive b. static | predictive c. predictive | adaptive d. adaptive | predictive e. adaptive | creative

c

Question 15 5 out of 5 points When marketing promised a new software product to an external client that is called ________. Answers: a. Budgetary estimation b. Strategic estimation c. Accommodation of the customer d. Estimation e. Definitive estimation

c

Question 15 5 out of 5 points Which of the following lifecycle models would you use if the requirements are unknown and/or unstable? Answers: a. Extreme b. Spiral c. Scrum d. Waterfall e. Iterative

c

Question 16 5 out of 5 points Top-down estimation is often also referred to as ________. Answers: a. budgetary estimation b. low-level developer estimation c. analogous estimation d. definitive estimation e. ubiquitous estimation

c

Question 16 5 out of 5 points Which of the following processes involves determining the policies, procedures, and documentation that will be used for planning, executing, and controlling the project schedule? Answers: a. Estimating activity resources b. Quality controlling c. Planning schedule management d. Defining activities e. Activity sequencing

c

Question 17 5 out of 5 points A ________ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project. Answers: a. WBS dictionary b. cost account c. WBS d. work package e. scope statement

c

Question 17 5 out of 5 points Process improvement plan, quality metrics, and quality checklists are the outputs of the ________ process. Answers: a. performing quality assurance b. controlling quality c. planning quality management d. None of these alternatives is correct. e. quality certification

c

Question 17 5 out of 5 points The average duration of a task whose optimistic time is 30 and whose most likely time is 45 and whose pessimistic time is 90 is ________. Answers: a. 30 b. 40 c. 50 d. 60 e. None of these alternatives is correct.

c

Question 18 5 out of 5 points Which of the following estimates is typically done two years before start of execution? Answers: a. Accommodation of the customer b. Definitive estimation c. Budgetary estimation d. Strategic estimation e. Estimation

c

Question 20 5 out of 5 points All of the following are true about work packages except ________. Answers: a. consume resources b. assigned to only one manager c. have medium to long duration d. definitive starts and stops dates e. All of these alternatives are true.

c

Question 20 5 out of 5 points What is the main goal of project cost management? Answers: a. To provide truthful and accurate cost information on projects b. To complete a project for as little cost as possible c. To complete a project within an approved budget d. To ensure that an organization's money used wisely e. All of these alternatives are correct.

c

Question 4 5 out of 5 points How many function points does it take to equal a person-month in terms of effort? Answers: a. 3 b. 4 c. 5 d. 6 e. 7

c

Question 4 5 out of 5 points Scrum, agile methodologies belong to which of the following methodology types? Answers: a. traditional waterfall with low ceremony b. iterative development with high ceremony c. iterative development with low ceremony d. iterative development with high discipline e. traditional waterfall with high ceremony

c

Question 5 5 out of 5 points As discussed in class, the cost to fix a defect ________ over time and becomes exorbitant once the defect ________. Answers: a. decreases linearly | is found b. increases linearly | 'walks out the door' c. increases exponentially | 'walks out the door' d. decreases exponentially | is found e. Both a. and c. are correct.

c

Question 5 5 out of 5 points Which of the following is a good condition for bottom-up estimating? Answers: a. Strategic decision making b. Internal, small project c. Fixed price contract d. High uncertainty e. Both c. and d. are good conditions for bottom-up estimating.

c

Question 6 4 out of 4 points Suppose you wanted to start task BB five days after task AA started. How would you do this in ProjectLibre? Answers: a. This is impossible in ProjectLibre. b. Place task BB in a finish/start relationship with its predecessor AA with a lag of five days. c. Place task BB in a start/start relationship with its predecessor AA with a lag of five days. d. Place task AA in a finish/start relationship with its predecessor BB with a lag of five days. e. Place task AA in a finish/finish relationship with its predecessor BB with a lag of five days.

c

Question 6 5 out of 5 points You cannot start editing a technical report until someone else completes the first draft. What type of dependency does this represent? Answers: a. Start-to-start b. Finish-to finish c. Finish-to-start d. Start-to-finish e. None of these alternatives is correct.

c

Question 7 5 out of 5 points Which of the following is not one of the three purposes for estimation? Answers: a. Far-out Strategic Planning (5 years out) b. Budgetary (2 years out) c. WAG d. Definitive (immediately before execution and used within execution) e. Both b. and c. are not purposes for estimation.

c

Question 9 5 out of 5 points Research shows the most frequently mentioned barrier to project success is ________. Answers: a. poor performance by team members b. political in-fighting c. poorly defined scope or mission d. weak project leadership e. not enough budget resources

c

Question 19 5 out of 5 points Seven activities are to be considered for this problem. Additional information about these activities such as their activity time and immediate predecessors are included in the table that follows. Use this information to figure out the earliest completion time for this project using a Gantt chart. Activity Immediate Predecessor(s) Activity Time(in weeks) A None 1 B None 1 C A 4 D B 5 E C, D 5 F E 3 G F 2 Answers: a. 18 weeks b. 14 weeks c. 16 weeks d. 20 weeks

c Response Feedback: Correct. Below is the early start schedule for the given project represented using a Gantt chart. Activity Immediate Predecessor(s) Activity Time(in weeks) ES EF LS LF A None 1 0 1 1 2 B None 1 0 1 0 1 C A 4 1 5 2 6 D B 5 1 6 1 6 E C, D 5 6 11 6 11 F E 3 11 14 11 14 G F 2 14 16 14 16 Activities A and B can begin at time 0 and have durations of one week each. Activity C cannot begin until activity A is completed, and activity D cannot begin until activity B is completed thus, these activities are scheduled to begin at time 1. Activity C is completed at time 5, but activity E cannot begin until activity D is also complete. Once activity D is complete, activity E can begin at time 6. Activity F can then be scheduled at time 11, and activity G can be scheduled at time 14. Activity G finishes at time 16. Thus, the earliest completion time for the given project is 16 weeks.

Question 10 5 out of 5 points If it becomes necessary to delay one or several late starts to accommodate resource limitations, this is called ________. Answers: a. time-constrained scheduling b. allocation c. resource-constrained scheduling d. splitting e. mandatory leveling

c Response Feedback: Correct. If resources are not adequate to meet peak demands, the late start of some activities must be delayed, and the duration of the project may be increased. This process is called resource-constrained scheduling.

Question 7 5 out of 5 points Renovation of a small compartment in a house boat or camping trailer that is too small for more than one person is an example of a(n) ________ resource constraint. Answers: a. time b. technical c. physical d. resource e. scheduling

c Response Feedback: Correct. Since space allows only one person to work at one time, all tasks have to be performed sequentially this is a physical constraint.

• Question 11 5 out of 5 points For any activity that has one or more predecessors, the ________ time is always the largest early finish of any of its predecessors. If the early finish times of an activity's predecessors were 85, 70 and 55, then this time would be the largest of these three early finish times or 85. Answers: a. early finish b. late start c. early start d. late finish

c Response Feedback: Correct. The early start of a merge activity is always the largest of the early finish times of any of its predecessors. If the early finish times of an activity's predecessors were 85, 70 and 55, then the early start time of the activity in question would be the largest of these three early finish times or 85.

Question 1 5 out of 5 points ________ costs are things like resource hourly rates. Answers: a. Intangible b. Sunk c. Indirect d. Direct e. Tangible

d

Question 10 5 out of 5 points To require lots of documentation, code that is well-commented, and lots of discipline is called ________. Answers: a. low ceremony b. low ceremony waterfall c. low ceremony iterative d. high ceremony e. low ceremony agile

d

Question 11 5 out of 5 points After planning scope management, the first step of project scope definition is to ________. Answers: a. analyze the current budget plan b. analyze the strategic plan c. meet with team members d. define the overall objective to meet the customer's needs e. select team members

d

Question 12 0 out of 5 points The method used to decompose and delineate the work involved in a project is called ________. Answers: a. organization breakdown structure b. work package c. priority matrix d. work breakdown structure e. responsibility matrix

d

Question 13 4 out of 4 points According to PMBOK, the first process involved in project time management is ________. Answers: a. defining activities b. estimating activity durations c. sequencing activities d. planning schedule management e. developing schedule

d

Question 13 5 out of 5 points ________ reserves allow for future situations that are unpredictable (unknown unknowns). Answers: a. Baseline b. Contingency c. Financial d. Management e. None of these alternatives is correct.

d

Question 14 5 out of 5 points The second step in the defining of a project would be to ________. Answers: a. select team members b. analyze the current budget plan c. analyze the strategic plan d. establish project priorities e. define the major objectives to meet the customer's needs

d

Question 15 5 out of 5 points What kind of cash reserves are needed to accommodate holidays, sick days, snow days, company meetings, training days? Answers: a. Management reserves b. Budgetary reserves c. Unproductive days reserves d. Contingency reserves e. None of these alternatives is correct.

d

Question 17 4 out of 4 points As the project manager for a software development project, you are helping to develop the project schedule. You decide that writing code for a system should not start until users sign off on the analysis work. Further, you decide that testing of a module (an object, class) will not commence until the entire module has been coded and compiled. What type of dependency is this? Answers: a. External b. There is no dependency. c. Discretionary d. Mandatory e. Internal

d

Question 17 5 out of 5 points What percent of IT projects should be completed with an adaptive, agile type of methodology? Answers: a. 40% b. 50% c. 60% d. 70% e. 80%

d

Question 17 5 out of 5 points Which of the following is not one of the items that would appear on a project scope checklist? Answers: a. Deliverables b. Technical requirements c. Reviews with customer d. Work breakdown structure e. Objectives

d

Question 2 4 out of 4 points In ProjectLibre, the tool that is used to designate subordination as displayed in the WBS is ________. Answers: a. link tool on the task tab b. assign resources tool on the task tab c. insert tool on the task tab d. indent tool on the task tab e. None of these alternatives is correct.

d

Question 2 5 out of 5 points The purpose of crashing is to ________. Answers: a. Reduce task cost b. Reduce project cost c. Improve product quality d. Reduce project duration, given a crashing budget e. None of the alternatives is correct.

d

Question 20 5 out of 5 points IT Projects that are of high priority and whose requirements are unstable or unknown are best accommodated by Answers: a. co-located teams b. dedicated project teams c. team members are senior level d. all of the above are correct

d

Question 20 5 out of 5 points When marketing informs the software development team that the product was promised to the customer on March 1st, that is a ________. Answers: a. target b. forecast c. due date d. commitment e. None of these alternatives is correct.

d

Question 4 4 out of 4 points By default ProjectLibre makes which of the following assumptions about time? Answers: a. 8-hour days b. No work on Saturdays c. No work on Sundays d. All of the alternatives are correct. e. Only a. and c. are correct.

d

Question 4 5 out of 5 points The implication of the cost of quality taxonomy discussed in class was to ________. Answers: a. spend more money on appraisal so as to incur less in the way of external costs due to bugs and software defects b. spend more money on prevention so as to incur less in the way of internal costs due to bugs and software defects c. spend more money on appraisal so as to incur less in the way of internal costs due to bugs and software defects d. spend more money on prevention so as to incur less in the way of external costs due to bugs and software defects e. All of these alternatives are correct.

d

Question 5 5 out of 5 points Iterative development processes provide which important advantages ________. Answers: a. continuous integration, verification, and validation of the evolving product b. frequent demonstration of progress to increase the likelihood that the end product will satisfy customer needs c. Early detection of defects and problems d. a., b. and c. are correct. e. None of these alternative is correct.

d

Question 5 5 out of 5 points The highest element in the hierarchical breakdown of the WBS is ________. Answers: a. a work package b. a cost account c. major deliverables d. the project e. sub deliverables

d

Question 5 5 out of 5 points Which of the following is not a reason for why estimates are needed? Answers: a. Estimates are needed to determine how long the project should take and its cost. b. Estimates are needed to determine whether the project is worth doing. c. Estimates are needed to support good decisions. d. Estimates are needed to measure and assess quality. e. Estimates are needed to schedule work.

d

Question 6 5 out of 5 points In reviewing the project plan, Sarah learns that the first deliverable is due by October 12. This would be called a ________. Answers: a. critical goal b. project target c. limit item d. milestone e. project objective

d

Question 7 0 out of 5 points When should inexperienced persons be used to estimate? Answers: a. When no one else is available b. When the project is new c. When there is no history database d. Both a. and c. are correct when taken together. e. Inexperienced persons should never be used to estimate.

d

Question 7 4 out of 4 points The total effort for a project is calculated to be 24 person-months. Three capable persons are assigned to the project. There is no mandatory or other sequencing required in the project. What is its total duration likely to be? Answers: a. 12 months b. 6 months c. 3 months d. 8 months e. 24 months

d

Question 8 4 out of 4 points Which of the following statements is false? Answers: a. A resource breakdown structure is a hierarchical structure that identifies the project's resources by category and type. b. A three-point estimate in PERT includes an optimistic, a most likely, and a pessimistic estimate. c. A Gantt chart is a common tool for displaying project schedule information on a timeline. d. Duration and effort are synonymous terms. e. Both b. and d. are false statements.

d

• Question 13 5 out of 5 points When creating a software package, the software must be designed, the code must be written, and then the code must be tested. This is an example of a ________ constraint. Answers: a. physical b. resource c. schedule d. technical e. time

d Response Feedback: Correct. A network for a new software project could place the activities in the network, as a sequence of (1) design, (2) code, and (3) test. In other words, you cannot logically perform activity 2 until 1 is completed, and so on. The project network depicts technical constraints.

Question 5 5 out of 5 points Rose leads the advertising of an innovative product, Teckos, just launched by her company. She has determined the advertising for Teckos is an individual project consisting of 7 activities. Information pertinent to these activities is included in the table that follows. Activity Immediate Predecessor(s) Activity Time(in weeks) A None 2 B None 2 C A 4 D B 5 E C 5 F D 2 G E, F 2 Using a Gantt chart, determine the earliest completion time for the project. Answers: a. 11 weeks b. 10 weeks c. 12 weeks d. 13 weeks

d Response Feedback: Correct. Below is the early start schedule for the advertising project represented using a Gantt chart. Activity Immediate Predecessor(s) Activity Time(in weeks) ES EF LS LF A None 2 0 2 0 2 B None 2 0 2 2 4 C A 4 2 6 2 6 D B 5 2 7 4 9 E C 5 6 11 6 11 F D 2 7 9 9 11 G E, F 2 11 13 11 13 Activities A and B can begin at time 0 and have durations of two weeks each. Activity C cannot begin until activity A is completed, and activity D cannot begin until activity B is completed thus, these activities are scheduled to begin at time 2. Activity E can begin after activity C is complete at time 6, and activity F can begin when activity D is complete at time 7. Activity G can only be scheduled at time 11 after both E and F are complete. Activity G finishes at time 13. Thus, the earliest completion time for the given project is 13 weeks.

Question 2 5 out of 5 points Delaying noncritical activities to lower peak demand and, thus, increase resource utilization is called resource ________. Answers: a. manipulating b. switching c. shifting d. smoothing e. allocation

d Response Feedback:Correct. If resources are adequate but the demand varies widely over the life of the project, it may be desirable to even out resource demand by delaying noncritical activities (using slack) to lower peak demand and, thus, increase resource utilization. This process is called resource smoothing.

Question 6 5 out of 5 points A project engineer has been scheduled to run the product system test at the exact same time he is to build a marketing prototype. This is an example of a ________ constraint. Answers: a. time b. scheduling c. physical d. resource e. technical

d. Resource Response Feedback: Correct. If one person must perform all activities, the resource constraint requires the activities be performed in sequence or series.

Question 1 4 out of 4 points A milestone in ProjectLibre is a task with ________. Answers: a. a finite duration b. a zero duration c. minimal duration/minimal cost d. a diamond icon e. Both b. and d. are correct.

e

Question 1 5 out of 5 points Patrick is reading a document that outlines the specific tasks and subtasks required to complete the writing of a technical support manual. The method that was probably used to develop the document is most likely ________. Answers: a. priority matrix b. work package c. responsibility matrix d. organization breakdown structure e. work breakdown structure

e

Question 10 4 out of 4 points A ________ is a bell-shaped curve that is symmetrical regarding the average value of the population (the data being analyzed) and has infinite tails. Answers: a. Beta distribution b. Exponential distribution c. Poisson distribution d. Rectangular distribution e. Normal distribution

e

Question 10 5 out of 5 points ________ is the ability of a product or service to perform as expected under normal conditions. Answers: a. None of these alternatives is correct. b. Performance c. Maintainability d. Functionality e. Reliability

e

Question 13 To crash the critical path beyond the point where it is no longer critical is ________. Answers: a. to allow another path to become critical b. to waste money c. permissible by the rules d. All of these alternatives are correct. e. Only a. and b. are correct.

e

Question 13 5 out of 5 points All of the following are usually included in a work package except ________. Answers: a. What will be done? b. The time needed to complete the work. c. A single person who is responsible for its completion. d. All the costs for the work package. e. All of these are included in a work package.

e

Question 14 5 out of 5 points The distribution used in a PERT representation of a task duration is ________. Answers: a. the uniform distribution b. the exponential distribution c. the normal distribution d. the Poisson distribution e. the beta distribution

e

Question 14 5 out of 5 points ________ is a planning process that is within the Project Scope Management knowledge area. Answers: a. Cost estimating b. Developing a project management plan c. Schedule development d. Quality planning e. Creating of a WBS

e

Question 16 4 out of 4 points The purpose of placing a PROJECT summary task at the very beginning of the list of tasks in the entry table is to ________. Answers: a. see total project duration and total project cost on the top line of the entry table b. enable a collection of tasks to be predecessors to the PROJECT summary task c. make visible the milestones of the project d. create mini projects within the context of the larger PROJECT e. All of these alternatives are correct.

e

Question 16 5 out of 5 points Daily Scrum meetings are usually ________ and typically last only ________ minutes. Answers: a. action-oriented | 30 b. casual meetings | 30 c. casual and creative | 40 d. creative meetings | 50 e. standup meetings | 15

e

Question 19 5 out of 5 points The purpose of a far-out estimate (five or more years) is to ________. Answers: a. Determine economic feasibility b. Determine priority of the project c. Decide detailed absolute definitive cost and duration numbers d. All of these alternatives are correct. e. Only a. and b. are correct.

e

Question 19 5 out of 5 points Why is it necessary to enumerate every path when crashing a project? Answers: a. So as to determine the length of every path and to determine the critical path b. So as to determine which tasks are not critical c. So as to determine the effects on every path length from crashing a specific task d. So as to determine if the critical path has been crashed beyond the point where it is no longer critical e. Only c. and d. are correct.

e

Question 2 5 out of 5 points Administrative activities, such as archiving project files, closing out contracts, documenting lessons learned, and receiving formal acceptance of the delivered work as part of the phase or project, are often involved in ________ processes. Answers: a. initiating b. planning c. executing d. monitoring and controlling e. closing

e

Question 2 5 out of 5 points ________ costs are costs related to the amount of time and resources allocated to completion of the project, whereas ________ costs are such items as overhead, pension and healthcare plans, etc. Answers: a. Sunk | indirect b. Direct | sunk c. Indirect | junk d. Indirect | direct e. Direct | indirect

e

Question 20 5 out of 5 points If you were trying to estimate the cost of a new project that was five years out from even being started, most likely you would be using ________. Answers: a. Top-down estimation b. Bottom-up estimation c. Analogous estimation d. None of these alternative is correct. e. Only a. and c. are correct.

e

Question 3 5 out of 5 points Which of the following is a typical problem associated with cost estimates? Answers: a. Estimates are done too quickly; estimates are off-the-cuff b. People lack estimating experience c. Human beings are biased toward underestimation d. Management desires accuracy e. All of these alternatives are problems associated with cost estimates.

e

Question 5 4 out of 4 points The best time to write the user acceptance test plan is ________. Answers: a. at the beginning of the planning phase b. at the beginning of the executing phase c. at the beginning of the closing phase d. before you do integration testing e. immediately after completing the requirements document

e

Question 7 5 out of 5 points ________ is a major expected output that is derived from a project. Answers: a. An objective b. A target c. A product d. An end object e. A deliverable

e

Question 8 5 out of 5 points In the Scrum Development Process a specific feature is ________. Answers: a. analysis b. design c. build d. test e. All of these alternatives are correct.

e

Question 9 0 out of 5 points The purpose of top-down estimation is for ________. Answers: a. definitive purposes b. detailed scheduling and budgeting purposes c. accuracy purposes d. schedule purposes e. strategic purposes

e

Question 9 4 out of 4 points ProjectLibre can do its scheduling from ________. Answers: a. the project start date b. the project stop date c. the project initiate date d. All of the alternatives are correct. e. Only a. and b. are correct.

e

Which of the following is a potential future consequence of not considering the impact on the schedule of limited resources? Answers: a. Costly activity delays b. Costly project delays c. Difficulty in taking quick corrective action d. Only a. and b. are correct. e. All a., b. and c. are correct.

e

•Question 25 4 out of 4 points In order to see total project duration and total project cost as well as meta-task durations and costs, it is recommended that you ________. Answers: a. include a project summary task as your first task under which all other tasks are subordinate b. insert a cost column in the Entry table c. replace the Entry table with the Resources view d. All of these alternatives are correct. e. Only a. and b. are correct.

e

• Question 9 5 out of 5 points When the work in an activity is interrupted to work on another activity and is then resumed at a later point in time, it is called ________. Answers: a. overriding b. starting/stopping c. prioritizing d. preempting e. splitting

e Response Feedback: Correct. A planner splits the continuous work included in an activity by interrupting the work and sending the resource to another activity for a period of time and then having the resource resume work on the original activity.

• Question 8 5 out of 5 points Which of the following is not one seven processes that make up the PMBOK knowledge area known as time (schedule) management? Answers: a. Sequence activities b. Plan schedule management c. Define activities d. Control activities e. Monitor activities

e Response Feedback: Correct. The seven processes are plan schedule management, define activities, sequence activities, estimate activity resources, estimate activity durations, develop activity schedule, and control schedule.


संबंधित स्टडी सेट्स

Snow glows white on the mountain tonight Not a footprint to be seen A kingdom of isolation And it looks like I'm the queen The wind is howling like this swirling storm inside Couldn't keep it in, heaven knows I've tried Don't let them in, don't let them s

View Set

Business Management & Administration Test

View Set

BIM Tools and Parametric Modeling-True/False + Vocabulary

View Set

The Point: Chapter 27 Female Genitalia

View Set

Real Estate State Law Practice Exam 4, PRACTICE TEST 1, State Test Prep., Real Estate State Law Practice test 6, National Test, Exam 1, Nevada Real Estate, Real Estate

View Set

Vitamins & Minerals - Functions & Benefits

View Set

Purposive Communication and Four Model of communication

View Set