managing risk chapter 7
where are time buffers typically applied
1. activities with severe risks 2. merge activities that are prone to delays 3. noncritical activities to reduce the likelihood that they create another critical path 4. activities that require scarce resources
what happens in the third step of the risk identification process: risk response development
1. develop a strategy to reduce possible damage 2. develop contingency plans
most change managment systems are designed to accomplish____________________________
1. identify proposed changes 2. list expected effects on schedule and budget 3. review, evaluate, and approve/disapprove changes 4. negotiate and resolve conflicts of change 5. communicte changes 6. assign responsibility for implementing change 7. adjust master schedule and budget 8. track all changes
what happens in the fourth step of the risk identification process: risk response control
1. implement risk strategy 2. monitor and adjust plan for new risks 3 change management
how are responses to risks classified
1. mitigating 2. avoiding 3. transferring 4. sharing 5. retaining
in a scenario analysis, team members assess the significance of each risk event in terms of
1. probability of the event 2. impact of the event
these techniques takes a more macro perspective of analyzing risk by looking at overall cost and schedule risks
1. program evaluation and review technique (PERT) 2. PERT simulation
what are the two strategies for mitigaing risk
1. reduce the likelihood that the event will occur 2. reduce the impact that the adverse event would have on the project
what are the steps in the risk management process
1. risk identification 2. risk assessment 3. risk response development 4. risk response control
The risk assessment form contains all of the following except
A) Likelihood of the risk event occurring B) Potential impact of the risk event C) Who will detect the occurrence of the risk event. D) Difficulty of detecting the occurrence of the risk event E) When the risk event may occur C) who will detect the occurrence of the risk event
Change management systems are designed to accomplish all of the following except:
A) Track all changes that are to be implemented B) Review, evaluates, and approve/disapprove proposed changes formally C) Identify expected effects of proposed changes on schedule and budget D) Reflect scope changes in baseline and performance measures E) All of the above are correct E) all of the above
Which of the following is not one of the steps in the risk management process?
A)Risk response development B) Risk assessment C) Risk identification D) Risk tracking E) Risk response control D)risk tracking
All of the following are included in the risk identification process except
Competitors
this analysis extends the risk severity matrix by including ease of detection in an equation
Failure Mode and Effects Analysis (FMEA)
One common mistake made early in the risk identification process is
Focus on objectives and not on the events that could produce consequences.
A risk profile is a list of questions that address traditional areas of uncertainty on a project that answers developed from:
From previous, similar projects
The easiest and most commonly used technique for analyzing risks is _____ analysis.
Impact
The 1999 NASA Mars Climate Orbiter is an example of
Mismanaged risk control
The demolition of the Seattle Kingdome (Snapshot from Practice) is an example of which of the following?
Mitigating
Technical risks are:
Often the kind that can cause the project to be shut down. Problematic
A list of questions that address traditional areas of uncertainty on a project is termed a risk
Profile
Which of the following is not one of the probability analysis tools?
Ratio/range analysis
Detailing all identified risks, including descriptions, category, and probability of occurring, impact, responses, contingency plans, owners and current status is called:
Risk register
what is the difference between a risk response and a contingency plan
a response is part of the actual implementation plan and action is taken before the risk can materialize, while a contingency plan is not part of the initial implementation plan and only goes into effect after the risk is recognized
this response to an opportunity is being willing to take advantage of it if it occures, but not taking action to pursue it
accept
when are management reserves established
after budget reserves are identified and funds established
what happens in the first step of the risk identification process: risk identification
analyze the project to identify sources of risk
what happens in the second step of the risk identification process: risk assessment
assess risks in terms of: 1. severity of impact 2. likelihood of occurring 3. controllability
changing the project plan to eliminate the risk or condition is classifed as which response category
avoiding risk
what are the reserves identified for specific work packages or segments of a project found in the baseline budget or work breakdown structure
budget reserves
this involves reporting, controlling, and recording changes to the project baseline
change management system
represents actions that will reduce or mitigate the negative impact of the risk event
contingency plan
what is an alternative plan that will be used if a possible foreseen risk event becomes a reality
contingency plan
what should a contingency plan include
cost estimate identify the source of funding
does the chance of risk increase or decrease as the project progresses
decreases
when are the chances of a risk event occuring the highest
early stages of project
this response tactic to an opportunity takes action to increase the probability and or the positive impact of an opportunity
enhance
how can managers ensure risk response control
establish an environment in which participants feel comfortable raising concerns and admitting mistakes document responsiblity
this response tactic to an opportunity seeks to eliminate the uncertainty associated with an opportunity to ensure that will definitely happen
exploit
what are the different responses to an opportunity
exploit share enhance accept
what is a classic example of transferring risk
fixed-price contracts that transfer risk from an owner to a contractor insurance
what is the purpose of risk management
identifies as many risk events as possible minimizes their impact manages responses to those events that do materialize provides contingency funds to cover risk events that arize
what is the formula for the failure mode and effects analysis (FMEA)
impact x probability x detection = risk value
examples of threats
inflation market acceptance exchange rates government regulations
how are price risks evaluated on cost sensitive projects
item by item
which projects need some contingency for price changes
long duration projects
what are the reserves needed to cover major unforeseen risks and, hence, are applied to the total project
management reserves
an event that can have a positive impact on project objectives
opportunity
when does the PM initiate the risk management process
planning phase
when the project owner assumes the risk because the chance of such an event occurring is slim refers to which risk response category
retaining risk
An uncertain event or condition that, if it occurs, has a positive or negative effect on a project objectives is termed.
risk
what is a hierarchial depiction of the identifed project risks arranged by risk category and subcategory that identifies the various areas and causes of potential risks
risk breakdown structure (RBS)
what is the list of questions that address traditional areas of uncertainty of a project
risk profile
what details all identified risks, including descriptions, category, and the probability of occurring, impact, responses, contingency plans, owners, and current status
risk register
this provides a basis for prioritizing which risks to address based on their position in the grid
risk severity matrix
what is the easiest and most commonly used technique for analyzing risks
scenario analysis
this response tactic to an opportunity involves allocating some or all of the ownership of an opportunity to another party who is best able to capture said opportunity for the benefit of the project
share
how do PM's crash or reduce the project duration
shortening ore or more activities on the critical path
The cost impact of a risk event occurring as a project proceeds through its life cycle tends to
slowly rise
what types of risks does the risk profile address
technical and managerial
what kind of risks often cause the project to be shut down
technical risks
sources external to the organization are considered
threats
what do managers use to cushion agains potential delays in the project
time buffers
what is one common mistake made early in the risk identification process
to focus on objectives and not on the events that could produce consequences
when is the cost impact the greatest on a project
towards the end
passing risk to another party is classified as which risk response category
transferring risk