Which of the following is a network diagramming technique used primarily to predict total project duration?

Critical path analysis

A(n) _____ on a project is a significant event that normally has no duration.

milestone

The first process involved in project time management is _____ .

planning schedule management

A draft schedule for a project is most likely to be found in a _____.

project charter

Which of the following is a relationship in which the "from" activity cannot start until the "to" activity is started?

Start-to-start

Which of the following is a similarity between scope control and schedule control?

Both are portions of the integrated change control process under project integration management.

In an AOA network diagram, _____ occur when two or more activities follow a single node.

bursts

_____ provide(s) a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format.

Gantt charts

Which of the following is true of a finsih-to-finish dependency?

It is a dependency in which the "from" activity must be finished before the "to" activity can be finished.

Which of the following is an output of schedule control?

Lessons-learned reports

Which of the following types of dependencies are inherent in the nature of work being performed on a project?

Mandatory

Which of the following is true of dummy activities?

They show logical relationships between activities.

_____ is the amount of time an activity can be delayed from its early start without delaying the planned project finish date.

Total slack

In project time management, the process of_____ primarily involves checking and managing changes to the project schedule.

controlling the schedule

In project time management, the next step after defining project activities is:

determining their dependencies.

In project time management, the ultimate goal of _____ is to provide a basis for monitoring project progress for the time dimension of the project.

developing a schedule

After working with key stakeholders to define activities and calculate their resources, the next process in project time management is to:

estimate the duration of activities.

Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.

feeding buffers

AOA network diagrams use only _____ dependencies.

finish-to-start

The amount of time an activity can be delayed without delaying the early start date of any immediately following activities is known as a _____.

free slack

The _____ for an activity is the latest possible time an activity might begin without delaying the project finish date.

late start date

The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.

longest; shortest

Which of the following is a difference between an activity list and an activity attribute?

An activity attribute provides more schedule-related information about each activity than an activity list.

In project time management, which of the following processes generate the main outputs of an activity list, activity attributes, and a milestone list?

Defining activities

Which of the following processes in project time management involves identifying the specific tasks that the project team members and stakeholders must perform to produce the project deliverables?

Defining activities

In project time management, which of the following processes involve analyzing activity sequences, activity resource estimates, and activity duration estimates to create the project schedule?

Developing the schedule

A similarity between the crashing technique and the fast tracking technique is that:

both can shorten the time needed to finish a project.

_____ dependencies are sometimes referred to as soft logic and should be used with care because they may limit later scheduling options.

Discretionary

In project time management, which of the following processes involve calculating the number of work periods that are needed to complete individual activities?

Estimating activity durations

Which of the following dependencies involve relationships between project and non-project activities?

External

A network diagramming technique in which boxes represent activities is known as a(n) _____.

PDM

A difference between the Program Evaluation and Review Technique (PERT) and critical path method (CPM) is that:

PERT uses different duration estimates whereas CPM uses one specific duration estimate.

_____ states that work expands to fill the time allowed.

Parkinson's Law

Which of the following documents is most likely to include planned project start and end dates which serve as the starting points for a detailed schedule?

Project charter

Which of the following is one of the main outputs of estimating activity resources process?

Project documents update

In project time management, which of the following processes primarily involve identifying and documenting the relationships between project activities?

Sequencing activities

Which of the following techniques involve doing activities in parallel that one would normally do in sequence?

Fast tracking

In project time management, the main goal of _____ is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work.

defining activities

The technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost is known as _____.

crashing

In project time management, a(n) _____ is an output of controlling the schedule

project management plan update


संबंधित स्टडी सेट्स

Lecture 26: DNA Packing & Chromatin Structure

View Set

Chapter 57: Drugs Affecting Gastrointestinal Secretions

View Set

2-20 : Unit 1 : Property & Liability Insurance Concepts

View Set

Chapter 9 & 10 Practice Questions

View Set

Unit 5 Quiz and AP Classroom Questions

View Set

Chapter 6, Section 2 Quiz Review

View Set

Macroeconomie - Piața financiară

View Set

Ch 50 caring for pt with muscle skeletal problems

View Set