PM/490: Project Management Capstone Wk 4 - Practice: Week 4 Quick Check

अब Quizwiz के साथ अपने होमवर्क और परीक्षाओं को एस करें!

In a change request, that is a corrective action?

A planned action that brings the project back into alignment with the project management plan

Lessons learned are not lessons learned until:

Action that has been taken to realize their benefits

When you record a lesson learned, what else should you record along with it? (Select all that apply.)

Actions recommendations

What information may be included in the issue log?

All of the above

besides the standard project documents, what else may be an input to the direct and manage work process?

All of the above

What is the primary purpose of the lessons learned register?

As a reference document for future projects that are similar

What should be submitted when an issue arises that requires modification to the project?

Change request

How often are issues addressed in project management?

Daily

What kind of knowledge and information can be shared through a lessons learned register?

Explicit knowledge

Preforming project work requires:

Integration with various activities and project plans

Baseline tracking helps to answer which of the following questions? (Select all that apply)

Is the project on schedule? Is the project on budget?

How does maintaining a lessons learned register improve the project?

It helps the team learn from past events so as not to repeat mistakes.

Information or knowledge that can be codified becomes a(n) _______.

Organizational process asset

Which of the following is an example of tacit knowledge?

Personal experience with design skills

Which of the following documents is an input to Baseline Tracking?

Project schedule

Which type of knowledge can only be shared through mentoring, conversation, and job interactions?

Tacit knowledge

Who approves change requests?

The change control board

When should a project manager start filling the lessons learned register?

Throughout the project

What is the purpose of the status report?

To show the status of the project at any point in the project

What is the purpose of baselining?

To track actual project results against the plan


संबंधित स्टडी सेट्स

Chapter 29: Management of Patients with Nonmalignant Hematologic Disorders

View Set

Module 9 Digital Forensics Analysis and Validation

View Set

AP U.S. Gov/Politics Chapter 10 - Interest Groups

View Set

IO Psych Chapter 5 Performance Measurement

View Set

The Committee of Public Safety and the Terror (1793-94)

View Set