SQ#3
Duration formula is:
(O +4ML +P)/6
What is the standard deviation formula?
(P - O)/6
Free Float belongs to _____________, while Total Float belongs to the ____________
Activity, Path
What are the 4 duration estimating techniques?
Analogous Parametric Three point/range/PERT Detailed
An estimate of durations on a current project using duration on a previous project is:
Analogous estimate
A start-start relationship from activity A to activity B means:
B cannot start until A has started
What are the triple constraints?
Cost, Schedule, Scope
What are two examples of physical constraints?
Crane erection material availability
Total float is the number of days an activity can be delayed without delaying the __________
END OF THE PROJECT
Differentiate between effort and duration
Effort - the time spent on a specific task Duration - total length of time it takes to complete that task
Free float can be greater than total float
False
The shortest schedule is always the best schedule
False
Total activity duration normally equals the duration of work
False
The number of days an activity can be delayed without delaying any successor activities is _________________
Free float
Provide an example of a start to start relationship
Installing underlayment on a roof cannot begin until sheathing installation has started
The amount of time the early start of an activity can be delayed without delaying the project completion but which will delay at least one successor
Interfering Float
Total float - free float =
Interfering float
What is the purpose of finding the early start and early finishes?
It gives you the earliest possible project completion date
Provide an example of a finish to finish relationship.
Landscaping cannot finish until the driveway is finished
The latest an activity can finish without delaying the project is known as:
Late Finish
Total float =
Late start - Early start
What are 3 of the 6 inputs to construction?
Materials/Installed equipment Craft labor Support equipment Tools Predecessor activities Information
In forward passes ______________ early finish of the predecessor controls the early start of the successor (Finish-Start relationship)
Maximum
In backward passes the _____________ late start of the successor controls the late finish of the predecessor (Finish-Start relationship)
Minimum
What may need to happen before actual work begins and is usually not included in the activity duration?
Mobilization
Constrained end date earlier than calculated late finish
Negative Float
Can a successor with a finish-finish task relationship be completed before the predecessor?
No
What are the 6 categories of constraints?
Physical Environmental Management Contractual Regulatory Safety
The duration of the activity is typically the duration that meets or exceeds what four requirements?
Quality standards Safe work environment Within budget Project complete on-time
What are the two reasons for leveling resources?
Reduce overallocation of a resource Smooth resource usage across an activity
What are two factors that impact total duration?
Resource availability Work environment External factors
The least used type of relationship is:
Start-Finish
What two types of relationships cannot be combined in a precedence network?
Start-Start Finish-Finish
Which method of entering dependencies is best for non-finish-to-start relationships?
Task Information Dialog
What are the five methods used to enter dependencies in Microsoft Project?
Task Information Tab Dragging Link Icon Task Form Gantt Chart Column
What is the difference between total float and free float?
Total float is the number of days an activity can be delayed without delaying the end of the project. Free float is the number of days an activity can be delayed without delaying any successor activity.
___________ float has to do with the path duration and __________ float has to do with the activity duration
Total, free
Interfering float is available to more than one activity.
True
Reassigning resources from an activity with free float to an activity on the critical path can help reduce duration
True
Total float is greater than free float
True
Total float is the number of days an activity can be delayed without delaying the project.
True
What are the three options for accounting for weather?
add to activity duration add weather activity to project phase add weather activity at the end of the schedule
When a subcontractor gives you a duration it is a:
best guess of actual days will not exceed will be exact
The three point estimate adds ____________ to duration.
contingency
Who has the option to own float?
contractor owner project team
Name one of the top reasons why planned work is not done on time
craft labor coordination material accessibility
Activities with no total float are ___________ activities
critical
The forward pass will calculate __________ starts and finishes
early
For a finish-start relationship with lag, the early finish of the predecessor activity plus the lag equals the ____________ of the successor activity.
early start
Two activities can have both a start-start and finish-finish relationship
false
Earliest early start of a successor activity - early finish =
free float
When you need to cut time out of the schedule, you look for activities with the most:
free float
Name two factors that affect construction for CMU block
height block size reinforcement and grout
What are some potential problem areas when determining durations?
in the dirt underground weather complex design
Name two inputs to the construction work area that can affect production
information tools support equipment craft labor predecessor activities
The backward pass gives the __________ starts and finishes.
late
In a finish-finish relationship, late finish of a predecessor is found by:
late finish of a successor - lag
In a start-start relationship, late start of a predecessor activity is found by:
late start of a successor - lag
Free float must be _____________ total float.
less than or equal to
What are the three points in the three point estimate?
optimism most likely pessimism
When performing a forward pass, start with activities what have no ____________
predecessors
An analogous estimate is based on using durations of _____________, _____________ projects to estimate current projects
previous, similar
Float is used to _________ project duration.
reduce
A parametric model is a mathematical representation of cost _________________ that provide a logical and predictable correlation between the physical or functional characteristics of a plant and its resultant cost.
relationships
Free float is determined by
successor
To perform a backward pass, start with an activity with no:
successor
How do you cut time out the schedule using free float?
take resources from the activities with free float and apply them to critical activities, but make sure to not delay these activities longer than the float
After the forward and backwards passes are completed, what can be calculated?
total float and free float
Initial schedule should include estimate of days lost to ____________ based on normal conditions
weather
Duration =
work/resources per time period
Can multiple critical paths exist?
yes, but they must connect at some point