Supply Chain Ch. 3

अब Quizwiz के साथ अपने होमवर्क और परीक्षाओं को एस करें!

True

In project management, crashing an activity must consider the impact on all paths in the network.

D. 0.4773

A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36. What is the probability that the project can be completed between days 108 and 120? A) -2.00 B) 0.0227 C) 0.1058 D) 0.4773 E) 0.9773

A. has been established by the Project Management Institute.

A code of ethics especially for project managers: A) has been established by the Project Management Institute. B) has been formulated by the Federal government. C) has been formulated by the World Trade Organization. D) is inappropriate, since everyone should use the same guidance on ethical issues. E) does not exist at this time.

A. 33% to 40 minutes

A combination of effective Gantt chart use and other tactics allowed Delta to cut the average time for a plane layover by what % of the original 60 minute duration? A) 33%, to 40 minutes B) 50%, to 30 minutes C) 20%, to 48 minutes D) 25%, to 45 minutes E) 40%, to 36 minutes

A. 0.1057

A contractor's project being analyzed by PERT has an estimated time for the critical path of 120 days. The sum of all activity variances is 81; the sum of variances along the critical path is 64. What is the probability that the project will take 130 or more days to complete? A) 0.1057 B) 0.1335 C) 0.8512 D) 0.8943 E) 1.29

B. 0.0228

A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, what is the probability that the project will be completed in 95 days or less? A) -0.4 B) 0.0228 C) 0.3444 D) 0.9772 E) 4.2

D. may require crashing multiple tasks simultaneously

A network has been crashed to the point where all activities are critical. Additional crashing: A) is unnecessary. B) is impossible. C) is prohibitively expensive. D) may require crashing multiple tasks simultaneously. E) can be done, but all critical tasks must be reduced in duration.

B. 0.3446

A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 90 days with a project variance of 25, what is the probability that the project will be completed in 88 days or less? A) 0.0228 B) 0.3446 C) 0.6554 D) 0.9772 E) 18

C. 0.1587

A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, what is the probability that the project will take 224 days or more to complete? A) near zero B) 0.0126 C) 0.1587 D) 0.8413 E) 2.14

A. PERT

A project manager is interested in crashing a project with variable activity times. Which of the following tools should he/she employ?

B. matrix organization

A project organization that becomes permanent is often referred to as a: A) fixed project organization. B) matrix organization. C) normal organization. D) standard organization. E) permanent project organization.

False

A project organization works best for an organization when the project resides in only one of its functional areas

A. is effective for companies with multiple large projects

A project organization: A) is effective for companies with multiple large projects. B) is appropriate only in construction firms. C) often fails when the project cuts across organizational lines. D) is most helpful for ongoing projects with no termination date. E) is most helpful when the work contains simple and unrelated tasks.

B. 112

A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day)? A) 98 B) 112 C) 120 D) 124 E) 220

C. 807

A project whose critical path has an estimated time of 820 days with a variance of 225 has a 20% chance that the project will be completed before which day (rounded to nearest day)? A) 631 B) 689 C) 807 D) 833 E) 1009

B. there are four paths in this network

A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Which of the following statements is true? A) There are two paths in this network. B) There are four paths in this network. C) There are five paths in this network. D) There are 25 paths in this network. E) There are six paths in this network.

A. the critical path is A-B-C, duration 15

A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=8. A) The critical path is A-B-C, duration 15. B) The critical path is A-C, duration 12. C) The critical path is A-B-C, duration 13.5 D) The critical path cannot be determined without knowing PERT expected activity times. E) The network has no critical path.

A. the critical path is D-E-F, duration 15

A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=8. A) The critical path is D-E-F, duration 15. B) The critical path is D-F, duration 12. C) Slack at D is 3 periods. D) Slack at E is 3 periods. E) Both A and C are true.

Work Breakdown Structure

A(n) ________ divides a project into more and more detailed components.

Project Organization

A(n) ________ is an organization formed to ensure that programs (projects) receive the proper management and attention.

D. D is critical, and has zero slack

Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 6. B's earliest finish is 18, while C's is 20. F's late start is 26. Which of the following is definitely true? A) B is a critical activity. B) C is completed before B. C) D has no slack but is not critical. D) D is critical, and has zero slack. E) F is critical, and has zero slack.

C. the set of times cannot all be possible

Activity R on a CPM network has predecessors M and N, and has successor S. R has duration 5. N's late finish is 18, while M's is 20. S's late start is 14. Which of the following is definitely true? A) R is critical and has zero slack. B) R has no slack but is not critical. C) The set of times cannot all be possible. D) N is a critical activity. E) S is a critical activity.

B. 2.33

An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. What is its expected activity time? A) 2.00 B) 2.33 C) 2.67 D) 4.67 E) 14.00

A. 3.67; 1

An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and pessimistic = 8. What is its expected activity time and variance? A) 3.67; 1 B) 3.67; 6 C) 4.33; 1 D) 4.33; 6 E) none of the above

B. 5.33

An activity on a PERT network has these time estimates: optimistic = 2, most likely = 5, and pessimistic = 10. What is its expected activity time? A) 5.00 B) 5.33 C) 5.67 D) 10.67 E) 32.00

E. 118

Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64. There is a .90 probability that the project will be completed before approximately day: A) 98. B) 108. C) 109. D) 115. E) 118.

D. 0.9599

Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline? A) 0.0401 B) 0.4599 C) 0.8056 D) 0.9599 E) near 1.0000, or almost certain

The differences between a Gantt chart and a PERT/CPM network are mainly that PERT/CPM has the ability to consider precedence relationships and interdependence of activities.

Describe the differences between a Gantt chart and a PERT/CPM network.

A. Level 1, Level 2, Level 4, Level 3, Level 3

Develop Windows 8 Operating System ? System Testing ? Compatible with Windows 7 ? Develop GUI's ? Module Testing ? A) Level 1, Level 2, Level 4, Level 3, Level 3 B) Level 1, Level 2, Level 3, Level 4, Level 5 C) Level 0, Level 1, Level 2, Level 3, Level 4 D) Level 0, Level 2, Level 2, Level 3, Level 3 E) Level 5, Level 3, Level 4, Level 1, Level 2

True

Ethical issues that can arise in projects include gifts from contractors, pressure to mask delays with false status reports, and pressure to compromise project quality to meet bonuses or avoid penalties related to schedules.

E. all of the above

Ethical issues that may arise in projects large and small include: A) gifts from contractors. B) exaggerated expense reports. C) compromised quality standards to meet bonuses or avoid penalties related to schedules. D) pressure to mask delays with false status reports. E) all of the above.

True

Every network has at least one critical path.

True

Gantt charts give a timeline for each of a project's activities, but they do not adequately illustrate the interrelationships between the activities and the resources.

The advantages include (1) its usefulness for scheduling and controlling large projects, (2) its straightforward concept, (3) its graphical displays of relationships among activities, (4) its critical path and slack time analyses, (5) its ability to document processes, (6) its wide range of applicability, (7) and its usefulness in monitoring schedules and costs.

Identify several advantages of using PERT (and CPM).

Project managers are directly responsible for making sure that (1) all necessary activities are finished in proper sequence and on time; (2) the project comes in within budget; (3) the project meets its quality goals; and (4) the people assigned to the project receive the motivation, direction, and information needed to do their jobs.

Identify the responsibilities of project managers.

1. Define the project and prepare the WBS. 2. Develop the relationships among the activities. 3. Draw the network connecting all of the activities. 4. Assign the time and/or cost estimates to each activity. 5. Compute the critical path-the longest time path through the network. 6. Use the network to help plan, schedule, monitor, and control the project.

Identify, in order, the six steps basic to both PERT and CPM.

A. $500

If an activity whose normal duration is 13 days can be shortened to 10 days for an added cost of $1,500, what is the crash cost per period A) $500 B) $1,500 C) $750 D) $13,000 E) $15,000

A. $400

If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $2,000, what is the crash cost per period? A) $400 B) $2,000 C) $10,000 D) $20,000 E) $30,000

True

In PERT analysis, the identification of the critical path can be incorrect if a noncritical activity takes substantially more than its expected time.

B. because near-critical paths could become critical paths with small delays in these activities.

In a PERT network, non-critical activities that have little slack need to be monitored closely: A) because PERT treats all activities as equally important. B) because near-critical paths could become critical paths with small delays in these activities. C) because slack is undesirable and needs to be eliminated. D) because they are causing the entire project to be delayed. E) because they have a high risk of not being completed.

True

One phase of a large project is scheduling

True

One responsibility of a project manager is to make sure that the project meets its quality goals.

False

PERT, but not CPM, has the ability to consider the precedence relationships in a project.

True

Project managers have their own code of ethics, established by the Project Management Institute.

False

Shortening the project's duration by deleting unnecessary activities is called "project crashing."

True

Slack is the amount of time an activity can be delayed without delaying the entire project.

True

The ES of an activity that has only one predecessor is simply the EF of that predecessor.

False

The PERT pessimistic time estimate is an estimate of the minimum time an activity will require.

B. beta

The ________ distribution is used by PERT analysis to calculate expected activity times and variances. A) Normal B) Beta C) Alpha D) Gaussian E) Binomial

Project Management Institute

The ________ has established a code of ethics especially for project managers.

Critical Path Method

The ________ is a project management technique using only one time factor per activity that enables managers to schedule, monitor, and control large and complex projects.

Critical Path

The ________ is the computed longest time path(s) through a network.

E. none of the above

The beta distribution is used in project management to: A) calculate slack on activities not on the critical path. B) calculate the probability that a project will be completed within its budget. C) calculate pessimistic and optimistic activity times. D) determine which activity should be crashed. E) none of the above

C. calculate expected activity times

The beta distribution is used in project management to: A) determine which activity should be crashed. B) calculate the probability that a project will be completed within its budget. C) calculate expected activity times. D) calculate slack for activities on the critical path. E) none of the above

E. all of the above

The control of projects involves close monitoring of which of the following? A) resources B) costs C) quality D) budgets E) all of the above

False

The critical path can be determined by use of either the "forward pass" or the "backward pass."

E. all of the above are true

The difference between AON and AOA networks is that: A) AOA networks sometimes require dummy activities. B) nodes consume no resources or time in AOA networks. C) both are acceptable in practice; however, Microsoft Project uses AON. D) nodes designate activities in AON, while arrows designate activities in AOA. E) All of the above are true.

B. the weighted average of a, m, and b, with m weighted 4 times as heavily as a and b.

The expected activity time in PERT analysis is calculated as: A) the simple average of the optimistic, pessimistic, and most likely times. B) the weighted average of a, m, and b, with m weighted 4 times as heavily as a and b. C) the sum of the optimistic, pessimistic, and most likely times. D) the sum of the optimistic, pessimistic, and most likely times, divided by six. E) the sum of the activity variances, divided by six

False

The fundamental difference between PERT and CPM is that PERT uses the beta distribution for crashing projects while CPM uses cost estimates

E. PERT employs three time estimates for each activity.

The main difference between PERT and CPM is that: A) PERT is more accurate than CPM. B) PERT assumes that activity durations are known. C) PERT ignores activity costs. D) CPM assumes activity durations can vary. E) PERT employs three time estimates for each activity.

PERT

The network analysis method that allows activity times to vary is ________.

A. planning, scheduling, and controlling

The phases of project management are: A) planning, scheduling, and controlling. B) planning, programming, and budgeting. C) planning, organizing, staffing, leading, and controlling. D) different for manufacturing projects than for service projects. E) GANTT, CPM, and PERT.

C. I, III, V

The project organization works best when which of the following conditions are satisfied? I. Work tasks can be defined with a specific goal and deadline. II. The job is typical and familiar to the existing organization. III. The work contains interrelated tasks requiring specialized skills. IV. The project is temporary but unimportant to long-term organizational success. V. The project cuts across organizational lines. A) I, II, III, IV, V B) None of the above conditions need to be satisfied. C) I, III, V D) I, II, III, V E) I, III, IV, V

False

The shortest of all paths through the network is the critical path

False

The standard deviation of project duration is the average of the standard deviation of all activities on the critical path.

B. the pessimistic time

The time an activity will take assuming very unfavorable conditions is: A) the optimistic time. B) the pessimistic time. C) the activity variance. D) the minimum time. E) exactly twice as long as the expected time.

D. work breakdown structure

WBS stands for which of the following project management tools? A) work break schedule B) work breakdown status C) work breakdown schedule D) work breakdown structure E) work break status

The activity variances influence the probability of project completion. Specifically, the sum of the variances of the critical tasks equals the variance of the project. Further, large variances on noncritical tasks need to be monitored. Such an activity might have an actual completion time so large that the task becomes a critical task.

What is the purpose of this calculation, i.e. what's the role of variances in PERT analysis?

E. Project Phoenix

What was the name of the construction project to rebuild the Pentagon after the terrorist attacks on Sept. 11, 2001? A) Project Panther B) Project Pit Bull C) Project Python D) Project Piranha E) Project Phoenix

C. only one time estimate can be used for each activity

Which of the following is NOT a limitation of PERT? A) Project activities have to be clearly defined, independent, and stable in their relationships. B) Precedence relationships must be specified and networked together. C) Only one time estimate can be used for each activity. D) Time estimates tend to be subjective and are subject to fudging by managers. E) There is the inherent danger of placing too much emphasis on the critical path.

D. budgeting

Which of the following is NOT one of the phases of project management? A) planning B) scheduling C) controlling D) budgeting E) All of the above are project management phases.

C. providing PERT probability calculations

Which of the following is NOT performed by Microsoft Project? A) drawing the project AON network B) identifying the critical path C) providing PERT probability calculations D) tracking the progress of the project E) creating the project Gantt chart

E. All of the above were Bechtel projects

Which of the following projects were completed by Bechtel? A) Hoover Dam B) Boston Central Artery/Tunnel C) Rebuilding Kuwait after Iraq's invasion in 1990 D) Rebuilding Iraq after the U.S. invasion, starting in 2003 E) All of the above were Bechtel projects

B. Bechtel is the world's premier manager of massive construction and engineering projects

Which of the following statements about Bechtel is true? A) Even though Bechtel is over 100 years old, the Kuwaiti oil fields was its first "project." B) Bechtel is the world's premier manager of massive construction and engineering projects. C) Bechtel's competitive advantage is supply chain management. D) While its projects are worldwide, its network of suppliers is largely in the United States E) All of the above are true.

D. The late finish of an activity is the earliest late start of all preceding activities.

Which of the following statements concerning CPM activities is false? A) The early finish of an activity is the early start of that activity plus its duration. B) The late finish is the earliest of the late start times of all successor activities. C) The late start of an activity is its late finish less its duration. D) The late finish of an activity is the earliest late start of all preceding activities. E) The early start of an activity is the latest early finish of all preceding activities.

E. All of the above are true

Which of the following statements regarding Bechtel is true? A) Its competitive advantage is project management. B) Bechtel was the construction contractor for the Hoover Dam. C) While helping to rebuild Iraq, Bechtel's crews had to travel under armed escort. D) Bechtel's procurement program is global in nature. E) All of the above are true.

D. All activities on the critical path have their LS equal to the maximum EF of all immediate predecessors

Which of the following statements regarding CPM is true? A) The critical path is the shortest of all paths through the network. B) The critical path is that set of activities that has positive slack. C) Some networks have no critical path. D) All activities on the critical path have their LS equal to the maximum EF of all immediate predecessors. E) All activities on the critical path have their ES equal to their LF.

D. If a specific project has multiple critical paths, all of them will have the same duration

Which of the following statements regarding CPM networks is true? A) There can be multiple critical paths on the same project, all with different durations. B) The early finish of an activity is the latest early start of all preceding activities. C) The late start of an activity is its late finish plus its duration. D) If a specific project has multiple critical paths, all of them will have the same duration. E) None of the above are true.

C. Gantt charts are visual devices that show the duration of activities in a project.

Which of the following statements regarding Gantt charts is true? A) Gantt charts give a timeline and precedence relationships for each activity of a project. B) Gantt charts use the four standard spines of Methods, Materials, Manpower, and Machinery. C) Gantt charts are visual devices that show the duration of activities in a project. D) Gantt charts are expensive. E) All of the above are true.

D. Only critical activities contribute to the project variance.

Which of the following statements regarding PERT analysis is true? A) Each activity has two estimates of its duration. B) Project variance is the sum of all activity variances. C) Project standard deviation is the sum of all critical activity standard deviations. D) Only critical activities contribute to the project variance. E) The most likely time is equivalent to the expected activity time.

C. The expected time estimate is calculated as t = (a + 4m + b)/6.

Which of the following statements regarding PERT times is true? A) The expected time is an estimate of the time an activity will require if everything goes as planned. B) The optimistic time estimate is an estimate of the maximum time an activity will require. C) The expected time estimate is calculated as t = (a + 4m + b)/6. D) The pessimistic time estimate is an estimate of the minimum time an activity will require. E) The most likely time estimate is an estimate of the maximum time an activity will require.

A. The optimistic time estimate is an estimate of the minimum time an activity will require.

Which of the following statements regarding PERT times is true? A) The optimistic time estimate is an estimate of the minimum time an activity will require. B) The optimistic time estimate is an estimate of the maximum time an activity will require. C) The expected time estimate is calculated as t = (a + 4m + b). D) The pessimistic time estimate is an estimate of the minimum time an activity will require. E) The most likely time estimate is an estimate of the maximum time an activity will require.

D. On a specific project, there can be multiple critical paths, all with exactly the same duration.

Which of the following statements regarding critical paths is true? A) The shortest of all paths through the network is the critical path. B) Some activities on the critical path may have slack. C) Every network has only one critical path. D) On a specific project, there can be multiple critical paths, all with exactly the same duration. E) The duration of the critical path is the average duration of all paths in the project network.

B. crashing sometimes has the reverse result of lengthening the project duration

Which of the following statements regarding time-cost tradeoffs in CPM networks is false? A) Crashing shortens project duration by assigning more resources to critical tasks. B) Crashing sometimes has the reverse result of lengthening the project duration. C) Crashing must consider the impact of crashing an activity on all paths in the network. D) Activities not on the critical path can become critical after crashing takes place. E) A negative crash cost per period would imply that either crashing is cheaper than not crashing or that the crash time was slower than the normal time.

D. Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.

Which of these statements regarding time-cost tradeoffs in CPM networks is true? A) Crashing is not possible unless there are multiple critical paths. B) Crashing a project often reduces the length of long-duration, but noncritical, activities. C) Activities not on the critical path can never be on the critical path, even after crashing. D) Crashing shortens the project duration by assigning more resources to one or more of the critical tasks. E) The crash time always exceeds the normal time.

False

Work breakdown structure is a useful tool in project management because it addresses the timing of individual work elements.

Crashing

________ is decreasing activity time in a network to reduce time on the critical path so total completion time is reduced.


संबंधित स्टडी सेट्स

Financial Institutions and Markets Test 1

View Set

Chapter 30: Perioperative Nursing

View Set

EXAM3: Membrane potential and synapse

View Set

Chapter 4: Common Reproductive Issues - ML8

View Set

NEUROSCIENCE FINAL, biopsychology chapter 2, Chapter 2 Biopsychology, Psychology Chapter 3: Biopsychology, pinel biopsychology chapter 3, Pinel Biopsychology Chapter 4, BIOPSYCH Chapter 4, Biopsychology-Pinel CH. 7

View Set

Electrified Vehicle Technologies

View Set