18 Components of Project Management Plan-- From Which Process?
scope baseline
create wbs
cost baseline
determine budget
development approach
develop project management plan
project life cycle description
develop project management plan
performance measurement baseline
develop project management plan - a record of what was planned for scope, schedule, and cost (3 baselines)
change management plan
develop project management plan - how change requests will be managed
configuration management plan
develop project management plan - how documentation changes concerning deliverables and processes will be managed
schedule baseline
develop schedule
tip for xyz management plan
if xyz is one of the 10 knowledge areas then it's plan xyz management, otherwise they're all develop project management plan except for baselines
tip for baselines
they come from the last process of the Planning column