Ch. 6
Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the six tasks that make up the job are 4, 6, 7, 2, 6, and 5 minutes, and the cycle time is 10 minutes?
(4 + 6 + 7 + 2 + 6 + 5) / 10 = 3
Using the assembly-line balancing procedure, which of the following is the theoretical minimum number of workstations if the task times for the eight tasks that make up the job are 7, 4, 7, 8, 9, 4, 3, and 6 minutes, and the cycle time is 8 minutes?
(7 + 4 + 7 + 8 + 9 + 4 + 3 + 6) / 8 = 6
Using the assembly-line balancing procedure, which of the following is the required cycle time if the production time in minutes per day is 1440 and the required output per day in units is 2000?
1,440 minutes / 2000 units = 0.72 minutes per unit
Using the assembly-line balancing procedure, which of the following is the required cycle time in minutes per unit if the daily production time is 480 minutes and the required daily output is 50 units?
480 minutes / 50 units = 9.6 minutes per unit
Which of these expressions is Little's Law?
All of the above A. Inventory/Flow time = Throughput rate: B. Inventory/Throughput Rate = Flow time C. Inventory = Throughput rate × Flow time D. Throughput Rate/Inventory = 1/Flow Time
A firm will work with a customer to design the product, and then make it from purchased materials, parts, and components. This firm is called:
An assemble to order firm
Which of the following basic types of process structures is one which equipment or work processes are arranged according to the progressive steps by which the product is made?
Assembly line
Which of the following is not a step in developing a manufacturing cell layout?
Disposing of left-over machinery and outsourcing ungrouped processes
The placement of which of the following is not determined by production process organization decisions?
Emergency exits
Which of the following is not considered a major work flow structure?
Fabrication
According to Little's Law, which of the following ratios is used to find throughput rate?
Inventory /Flow time
A firm fills its customer's orders from finished goods inventory. It is a:
Make to stock firm
Which of the following is not a basic type of process structure?
Product-process matrix
When balancing an assembly line, which of the following is not a way to reduce the longest task time below the required workstation cycle time?
Speed up the assembly line transfer mechanism
A difference between project and continuous flow categories of process flow structures is which two of the following?
The size and bulk of the product
According to Little's Law, which of the following can be used to estimate work-in-process inventory?
Throughput rate times Flow time
Which of the following basic types of process structures is one which similar equipment or functions are grouped together?
Workcenter
Which of the following is a basic type of process structure?
Workcenter
You have just determined the actual number of workstations that will be used on an assembly line to be 6 using the assembly-line balancing procedure. The cycle time of the line is 5 minutes and the sum of all that tasks required on the line is 25 minutes. Which of the following is the correct value for the resulting line's efficiency?
[25 / (6 x 5)] = 0.833
You have just determined the actual number of workstations that will be used on an assembly line to be 8 using the assembly-line balancing procedure. The cycle time of the line is 10 minutes and the sum of all that tasks required on the line is 60 minutes. Which of the following is the correct value for the resulting line's efficiency?
[60 / (8 x 10)] = 0.750