CM 1011 FINAL

Lakukan tugas rumah & ujian kamu dengan baik sekarang menggunakan Quizwiz!

Gantt charts are also known as network diagrams.

FALSE

The first task in contract administration is to create a contact list for every single person associated with the project.

TRUE

The superintendent is the person responsible for organizing the job site and managing construction on a daily basis.

TRUE

The three stages of a precedence diagram schedule are planning, sequencing, and scheduling.

TRUE

When the work plan does not work, stop and re-plan.

TRUE

Availability of materials is not a contractor risk.

FALSE

BIM does not help a contractor coordinate subcontractors.

FALSE

BIM will not allow collaboration among students from the different design-build disciplines.

FALSE

Because every project is different, quality does not happen on purpose.

FALSE

Budget is not a factor to be considered when setting the quality standard.

FALSE

Change orders always come from the owner for a variety of reasons.

FALSE

Change work does not involve taking on more risk.

FALSE

Change work should be seen as an opportunity to increase profit.

FALSE

Comparing actual job costs to estimated costs is not risk management.

FALSE

Continuous improvement is not one of the six tenets of Lean.

FALSE

Documentation should be provided at the end of the project but not throughout the project.

FALSE

Each time number in a network diagram represents a calendar day, not a work day.

FALSE

Eco-friendly building materials may be obtained from anywhere in the world.

FALSE

Entry-level CM's are seldom, if ever, used to keep up with RFI's.

FALSE

A BIM model cannot perform clash detection before the project goes to the field.

FALSE

A LEAN program, once initiated, is good for many years without improvement.

FALSE

A change order adjustment amount does not include general overhead and profit.

FALSE

A claim can only be made after the project is complete.

FALSE

A poor quality design is not a contractor risk.

FALSE

A project debriefing is not meant to be a training mechanism.

FALSE

A project is considered totally complete even if paperwork has not been delivered to the owner.

FALSE

A project may go forward without paperwork.

FALSE

A public project has less governmental involvement than a private project.

FALSE

A risk mitigation plan happens before construction starts and does not vary thereafter.

FALSE

A short-interval schedule is not the same as a look-ahead schedule.

FALSE

A time extension is a contract adjustment used when a monetary adjustment is not owed.

FALSE

After quality, safety is the number-one priority when managing construction operations.

FALSE

All BIM does is add a 3D component to 2D plans and specs.

FALSE

All construction risks have to do with jobsite events.

FALSE

An execution plan works better without the involvement of the personnel working under it.

FALSE

An overcrowded worksite does not affect productivity.

FALSE

Archeological findings are not a risk of the contractor.

FALSE

Assigning durations to each activity precedes sequencing.

FALSE

Attic stock and extra materials belong to the contractor.

FALSE

Enhancing indoor environmental quality is not one of the six fundamental principles of sustainable building design.

FALSE

Gray water is the same as drinking water.

FALSE

Hiring the right people to do the job is part of quality control.

FALSE

If you are only a user of BIM, and not a designer, you do not need to know anything about BIM.

FALSE

Initial cost of the net-zero energy building is lower than the conventional building.

FALSE

It was an LSU building where the architect undersized the door openings in order to keep the artsy effect.

FALSE

John Manion works for Boh Brothers in their Broad work division.

FALSE

LCI member companies produced less than 10% of the total construction revenue in 2019.

FALSE

Meeting minutes are unnecessary if it is a meeting of the owner's construction representative and the superintendent.

FALSE

One of the least important contract administration functions is the contractor getting paid on time.

FALSE

Partnering is a concept involving only the owner and prime contractor.

FALSE

Platinum is the lowest level of LEED certification.

FALSE

Productivity is the most predictable element of project planning and project control.

FALSE

Scheduling and coordinating material deliveries is not one of the contractor's tasks.

FALSE

Sequencing of activities is not the same as network logic.

FALSE

Submittals are totally different that RFI's.

FALSE

Successful subcontractor coordination is not based on proper scheduling, preparation, and planning.

FALSE

Sustainability does not involve operational and maintenance practices.

FALSE

Sustainability has to do with a small part of an entire life cycle.

FALSE

Sustainability is an unexpected mainstream design and construction deliverable.

FALSE

Sustainability is the fifth dimension of BIM.

FALSE

Sustainable development goals only focus on environmental development.

FALSE

Team activities do not included communications guidelines.

FALSE

The Construction close-out does not include commissioning.

FALSE

The biggest disadvantage to Gantt charts is that they show the interrelationship among the activities.

FALSE

The company does not need to have a feedback loop for the work force.

FALSE

The contractor selects the contract form.

FALSE

The cost of rework is about the same as the first time the work was done.

FALSE

The financial strength of the owner is not a risk of the prime contractor.

FALSE

The first stage in the project control cycle is the documentation stage.

FALSE

The initial building costs are the only numbers used in the life-cycle cost analysis.

FALSE

Unfortunately, a more dangerous work environment is one of the results of Lean.

FALSE

Very little that comes out of the construction site is recyclable.

FALSE

Very seldom does a job site required temporary utilities.

FALSE

Waste is a relatively minor issue in construction.

FALSE

Which of the following is NOT part of the LEED credit category?

OUTDOOR ENVIRONMENTAL QUALITY

A project control system utilizes the plans, specs, estimate, and schedule.

TRUE

Adding contingencies may be a pre-bid method to offset a risk.

TRUE

Administrative activities include permitting, submittals, inspections, and testing.

TRUE

Change order philosophy: "First do no harm."

TRUE

Clash detection allows for the effective identification, inspection, and reporting of unintended interferences of materials and systems.

TRUE

Collaboration of communication and activities is part of a Lean project delivery.

TRUE

Commissioning includes HVAC testing.

TRUE

Cost codes are used to compare actual job costs with the estimated job costs.

TRUE

Employee parking is a staging issue that must be addressed when organizing the job site.

TRUE

Energy consumption in the building sector is higher than the industrial sector.

TRUE

Establishing the work hours is the responsibility of the superintendent.

TRUE

Evaluation of a project includes determining what worked and what didn't work.

TRUE

It is important for quality control personnel be familiar with the standards associated with a number of trades.

TRUE

Keeping accurate labor records is one of the most important functions of CM's in the field.

TRUE

LEED stands for Leadership on Energy and Environmental Design.

TRUE

Labor costs are directly impacted by a construction company's safety record.

TRUE

Lean can be defined as "a culture of respect and continuous improvement aimed at creating more value for the customer while identifying and eliminating waste.

TRUE

Once a progress payment is received by the prime contractor it is obligated to promptly pay its subcontractors and vendors.

TRUE

Optimizing energy use is one of the six fundamental principles of sustainable building design.

TRUE

Our presenter on Change Work was John Manion.

TRUE

Planning and scheduling concern two interrelated elements of construction management: strategy and time.

TRUE

Political, legal, and regulatory risks are the ones over which the contractor has the least control.

TRUE

Project size may impact what type of schedule will be used.

TRUE

Quality control is only done during a construction project.

TRUE

Risk management involves identification, quantification, and mitigation of the risks.

TRUE

Site logistics (project staging) is crucial to the overall efficiency and coordination of the work.

TRUE

Some production activities do not actually require any physical effort.

TRUE

Steel beams are an example of a construction product that requires a shop drawing.

TRUE

Substantial completion is part of contract close-out.

TRUE

Summary schedules group activities under broader headings such as mobilization, site work, foundation, and rough framing.

TRUE

TQM stands for Total Quality Management.

TRUE

Taking corrective action is called crashing the schedule.

TRUE

Team activities include identification of who has what responsibilities.

TRUE

The Lemoine Company five close-out objectives include substantial completion.

TRUE

The big advantage to Gantt chart schedules is that they are very easy to understand.

TRUE

The correct tools and equipment are necessary for workers to get the job right the first time.

TRUE

The distributed repository approach is the path most contractors use to implement their BIM activities.

TRUE

The number one quality issue is installation of the wrong materials, not poor workmanship.

TRUE

The two key process tools used to track all inquiries, decisions, and approvals that occur during construction are the requests for information (RFI'S) and submittals.

TRUE

The ultimate goal of jobsite management is to keep the project on schedule, within budget, and of high quality.

TRUE

There are three close-out reports.

TRUE

Total float is the amount of time an activity can be delayed before it impacts the project's completion as planned.

TRUE

Triple Bottom Line performance involves economic, environmental, and social performances.

TRUE

Use of subcontractors is considered as more efficient and expert than self-performance by the contractor.

TRUE

One of the eight LEAN wastes hurrying.

FALSE

While BIM is a verb, VDC is a noun.

FALSE

Contract close-out includes final payment.

TRUE

Taking advantage of the sun can be used for passive solar heating.

TRUE

The goals of a construction team includes safety.

TRUE

A construction team does not need diversity.

FALSE

A zero-punch list should not be a goal of the project.

FALSE

AHJ does not include permits and inspections.

FALSE

Baton Rouge was on the map of LCI (Lean Construction Institute) Communities of Practice.

FALSE

Subcontractors should not be pre-qualified.

FALSE

Application for payments is made on an AIA G702 form.

TRUE

Environmental risks may delay a schedule.

TRUE

Identifying performance deviations is one of the seven steps in the project control cycle.

TRUE

Not bidding on a project may be a pre-bid method to offset a risk.

TRUE

Quality is one of The Lemoine Company's core ideologies.

TRUE

Site selection and building layout is the first area where sustainability can be applied.

TRUE

Testing of materials during construction is part of quality control.

TRUE

The Lean speakers were from Landis Construction Co. and Jack's Electric Service.

TRUE

Risk retention is a mitigation strategy.

TRUE

Environmental protections do not include storm water pollution.

FALSE

LEED is the only building rating system worldwide.

FALSE

Where to locate a crane on the job site is a relatively unimportant issue.

FALSE

BIM helps with consideration of alternative approaches to design and construction.

TRUE

Design discrepancies may cause a change order.

TRUE

Each activity in the budget is assigned a cost code.

TRUE

Earned value analysis may be used to determine the overall status of the project relative to both cost and schedule.

TRUE

RFI logs should be kept throughout the project.

TRUE

Local government is seldom, if ever, involved in construction projects.

FALSE

One of the eight LEAN wastes lack of motion.

FALSE

The Work Breakdown Structure (WBS) groups together work done by many subcontractors.

FALSE

Delivery tickets are one of the sources of information used to track job performance.

TRUE

Indoor environmental quality of a building has to do with impacts on the inhabitant's comfort, health, and productivity.

TRUE

It is important to develop a standardized risk assessment approach that can be applied to each project.

TRUE

Job signage is a good way to advertise the construction company.

TRUE

Lean results in more completions under budget.

TRUE

One of the benefits of LEAN is a safer environment.

TRUE

One of the eight LEAN wastes is defects.

TRUE

One of the reasons for a pre-construction meeting is to clarify the lines of authority and communication

TRUE

ProCore is a comprehensive project management platform that enables the entire project team to access and participate in every type of construction application from a centralized hub.

TRUE

The Lemoine Company started construction activities in the mid-1970's.

TRUE

Create waste is one of the six tenets of Lean.

FALSE

Sustainability does not involve using standard sizes of materials.

FALSE

The critical path never changes.

FALSE

Which of the following is NOT part of the triple bottom line of sustainability?

PERFORMANCE

Which of the following is the highest rank of LEED certificates?

PLATINUM

"Standardize" is one of the 5 S's.

TRUE

A clean site is a safe site.

TRUE

A tailgate meeting to review safety procedures is risk management.

TRUE

AHJ stands for local Authorities Having Jurisdiction.

TRUE

According to our presenter "inspection is a necessary evil."

TRUE

An ITP Inspection Test Plan includes the agreement as to when it will be done.

TRUE

Arbitration can be more expensive than litigation.

TRUE

Hard hats and steel-toed shoes are examples of PPE.

TRUE

It was General Dwight D. Eisenhower who said "Plans are worthless, but planning is everything.

TRUE

Key performance indicators formulate plans for improvement.

TRUE

LEAN thinking demands a mindset of continuous improvement.

TRUE

Managing the many changes on a project is one of the contract administration functions

TRUE

Quality and safety are ultimately achieved at the labor force level.

TRUE

Quality assurance is done prior to a project being started.

TRUE

Quality attitude must emanate from the highest levels of leadership and management.

TRUE

The fourth dimension of BIM is scheduling.

TRUE

The goal of sustainability is to reduce the impacts construction has on buildings being built, and the environment, quality of life, and human health.

TRUE

The schedule of values represents the owner's budget

TRUE

With BIM the various stages of design are classified as level of development (LOD).

TRUE

LEAN concepts came from the General Motors management principles.

FALSE

Labor availability is not a contractor risk.

FALSE

Major subcontractors and vendors do not need to attend a pre-construction meeting.

FALSE

Most budget problems originate from inaccurate labor estimates.

TRUE

Part of being a construction manager is anticipating risks.

TRUE

Part of network logic is answering the question: Which activities can be started once this activity is completed?

TRUE

Productivity has to do with how much work can be accomplished in a certain time frame.

TRUE

Programmable thermostats are an example of how energy consumption can be optimized.

TRUE

Quality, along with cost and time, are the three primary elements of construction management.

TRUE

Respect for people is one of the six tenets of Lean.

TRUE

Retention of good workers is important in building a good work force.

TRUE

Risk abatement involves reducing the loss potential of a risk.

TRUE

The Lemoine Company has a program called LEAP, which stands for Lemoine Engineering Advancement Program.

TRUE

The acronym DOWNTIME represents the eight wastes of LEAN.

TRUE

There are actually wood building materials that may be certified.

TRUE

There are programs available that integrate estimating, accounting, and contract administration functions into a single program.

TRUE

Additional time should always be asked for when processing a change order.

TRUE

BIM cannot be accommodating to facility management.

FALSE

BIM cannot help with site planning and utilization.

FALSE

Fossil fuels are considered a renewable source of energy.

FALSE

A BIM model serves as a shared knowledge resource for the entire design and build team.

TRUE

Most schedule glitches have to do with productivity.

TRUE

Lean Project Delivery results in minimizing waste and rework.

TRUE

The first goal of quality management is to get things done right the first time.

TRUE

Wetlands is a risk of a contractor.

TRUE

Unforeseen conditions may cause a change order.

TRUE

3D CAD is the same as BIM.

FALSE

Which of the following is not the social benefit of sustainability?

REDUCE GLOBAL WARMING

Surplus materials belong to the owner.

TRUE

Which of the following may impact human health, comfort, and productivity in an indoor environment?

ALL OF THE ABOVE

A preparatory inspection is unnecessary to avoid miscues and rework.

FALSE

Contract time is not a consideration when working on a change order.

FALSE

Contractor close-out reports are not meant to be given to the estimating department.

FALSE

Cost overruns do not need to be addressed until the project is completed.

FALSE

Equipment rentals is not a consideration when working on a change order.

FALSE

It does not make sense to do much upfront planning of the BIM model.

FALSE

It is the obligation of the owner to provide job site security.

FALSE

Keeping score is unnecessary in comparing performance against goals.

FALSE

One of the detriments of LEAN is decreased productivity.

FALSE

PPE stands for protecting people every time.

FALSE

Predicting durations is an exact science.

FALSE

Purchase orders and material invoices do not need to be monitored during the contract.

FALSE

Quality failures affect only cost and time.

FALSE

Quality impacts aesthetics, appearance, and durability, but not performance.

FALSE

Regulatory compliance will never cause a change order.

FALSE

Retainage is an amount retained by the owner from progress payments as a penalty for mistakes made by the contractor.

FALSE

Safety is not one of The Lemoine Company's core ideologies.

FALSE

Safety training does not require buy-in from the trainees.

FALSE

Sales is not a phase of a construction project according to our presenter.

FALSE

Subcontracting work is not a risk mitigation strategy.

FALSE

Subcontractors and suppliers should not be involved is a risk evaluation.

FALSE

Submittal of shop drawings is part of quality assurance.

FALSE

The primary tool associated with project planning is the estimate.

FALSE

The three types of activities that must be planned and included in a schedule are: pre-construction, construction operations, and post-construction.

FALSE

There are 10 tenets of LEAN.

FALSE

Tracking project time is not as important as tracking project cost.

FALSE

Which stage of the building life cycle is responsible for higher energy consumption?

OPERATION

"By failing to prepare, you are preparing to fail."

TRUE

"It is the will to prepare to win that separates success from failure."

TRUE

"Quality is meeting the acceptance criteria 100% of the time."

TRUE

A BIM design begins with intelligent objects such as walls, roof, and windows

TRUE

A BIM file contains construction details, performance characteristics, and product specs.

TRUE

A LEAN program generates value.

TRUE

A comprehensive quality control plan is the best way to control quality during construction.

TRUE

A network diagram is nothing more than a work plan.

TRUE

A team should measure its performance against its goals.

TRUE

An inspection is a check used when tracking quality.

TRUE

An objective of sustainability is to reduce consumption of nonrenewable resources, to minimize waste, and to create better environments.

TRUE

As-built drawings are part of contract close-out.

TRUE

Construction impact costs may include noise control

TRUE

Contract administration is all about managing the business details and relationships.

TRUE

Contracting with the subcontractors is part of quality assurance.

TRUE

Critical path method (CPM) is the most common type of schedule used in the commercial, civil, and industrial construction industry.

TRUE

JSA stands for job safety analysis.

TRUE

Jobsite overhead is a consideration when working on a change order.

TRUE

Jobsite tablets have made it a lot easier for field personnel to manage every aspect of project coordination in real time

TRUE

John Manion's company does industrial, commercial, and institutional construction work.

TRUE

John Manion's company has a project in the Super Dome at this time.

TRUE

Key performance indicators determine the level of compliance.

TRUE

Liquidated damages is an agreed upon amount per day for the project finishing late.

TRUE

One definition of "sustainable' is meeting the needs of the present without compromising the ability of future generations to meet their own needs.

TRUE

One of the reasons for a toolbox meeting is to emphasize safe work habits.

TRUE

One of the reasons for subcontractor meetings is to discuss potential conflicts.

TRUE

Pre task safety analysis is sometimes called a toolbox meeting.

TRUE

Quality is defined as meeting or exceeding the requirements established in the design documents.

TRUE

Risk evaluation is subjective.

TRUE

Scheduling addresses "How long?"

TRUE

The first rule on construction management is "read the contract."

TRUE

The need for a clear and accurate paper trail in construction is paramount.

TRUE

The tracking tool for cost is the estimate.

TRUE

Weather is probably the most common and most obvious reason for work slowdown.

TRUE

The Lemoine Company has a term called "LIFE" which stands for "Living an Injury Free Environment."

FALSE

The Lemoine Company works in various construction industries, including single family residential.

FALSE

The bid amount is converted to a project budget.

FALSE

An activity is a task, function, or decision that has a time commitment, or duration, associated with it.

TRUE

Back charges may be used to encourage subcontractors to clean up after themselves.

TRUE

With BIM you get a chance to build the project in a virtual environment before you build it for real.

TRUE

A BIM model is a 3D representation of the physical and functional characteristics of a building.

TRUE

A good win-win example is using recycled concrete as a base material for new roadways or driveways.

TRUE

Commissioning does not include testing of life safety systems.

FALSE

Detailed schedules do not break major work activities down into smaller tasks.

FALSE

The number one cause of jobsite accidents are electrical shocks.

FALSE

The owner (client) should not be a member of the team.

FALSE

Everything CM's do is tied to the plans and specs.

TRUE

Home office overhead a consideration when working on a change order.

TRUE

The pre-construction meeting should include discussion about schedule issues.

TRUE

The purpose of The Lemoine Company is to achieve excellence.

TRUE


Set pelajaran terkait

Chapter 3 - Constitutions, Statutes, Administrative Law, and Court Rules

View Set

Binary, Hexadecimal, octal and all that shizzle

View Set

Chapter 22: Management of Patients with Arrhythmias and Conduction Problems

View Set

Energy and Forms of Energy, Energy Transformation

View Set

2.1 Concepts of Effective Communication

View Set

Chapter 1: The Sociology of Health, Illness, and Health Care

View Set