HMP 5820 Ch 4
According to PMI, which of the following would not be good wording for a WBS item? a) install software b) software c) software installation d) software training
a) install software
A requirements ______ ______ is a table that lists requirements, various attributes of each requirement, and the status of the requirements to ensure that all of them are addressed. a) traceability matrix b) management plan c) management matrix d) tracking tool
a) traceability matrix
The entire project is considered to be level _____ in the WBS. a) 0 b) 1 c) 2 d) 3
b) 1
The main purpose of project planning is to: a) obtain funding for projects b) guide project execution c) clarify roles and responsibilities d) keep senior managers informed
b) guide project execution
Project teams develop a _____ to coordinate all other project plans. a) strategic plan b) project management plan c) master plan d) project website
b) project management plan
A _______ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project. a) contract b) Gantt Chart c) WBS d) network diagram
c) WBS
A WBS _____ is a document that describes the deliverables on the WBS in more detail. a) glossary b) statement c) dictionary d) appendix
c) dictionary
What can project teams create to help promote teamwork and clarify team communications? a) a project website b) a team-building plan c) a team roster d) a team contract
d) a team contract
A WBS is often depicted in a ____ format, similar to an organizational chart. a) tabular b) mind-map c) block d) graphical
d) graphical
A _______ is a deliverable at the lowest level of the WBS that represents the level of work that the project manager uses to monitor and control the project. a) WBS dictionary b) budget item c) line item d) work package
d) work package